MEDICAL OFFICE BUILDING at Tysons Corner

Slides:



Advertisements
Similar presentations
| Michael Gallagher | Construction Management AE Faculty Consultant: Dr. Riley The Pennsylvania State University AE Senior Thesis Project.
Advertisements

Jeremiah Ergas AE 482 – 5 th Year Senior Thesis Structural Option April 15 th, 2008 Faculty Consultant: Dr. Ali Memari Northside Piers – Brooklyn, NY Structural.
A Medical Office Building For The Primary Health Network Daniel Goff I Structural Option Dr. Thomas Boothby l Faculty Advisor Sharon, Pennsylvania Source:
Kyle Goodyear BAE in Construction Management Pennsylvania State University Senior Thesis Presentation April 12, 2010.
Ballenger East Building Final Presentation Design Development Architectural Engineering Senior Thesis Presentation 2009 Lighting / Electrical Option Student.
Bowie State University Fine and Performing Arts Center Zachary Lippert Faculty Advisor: Dr. Stephen Treado.
Crocker West Building State College, Pa Eric M. FosterStructural OptionSpring 2009.
The Edward St. John Student Center Zachary Haupt Faculty Advisor: Dr. William Bahnfleth 11 April 2011.
Daniel Suter Construction Management AE Senior Thesis Presentation The Pennsylvania State University Unknown Data Center Somewhere, USA
Bethesda Triangle Brian Groark Construction Management Faculty Consultant: Dr. Messner.
360 State Street New Haven  CT  Structural | Sabrina Duk | T. Boothby.
William H. Gates Hall University of Washington School of Law Katie Jenkins The Pennsylvania State University Architectural Engineering Lighting/Electrical.
George Read Hall The University of Delaware
Hershey Research Park Building One Jonathan Krepps Structural Option Senior Thesis 2013 Faculty Advisor: Dr. Hanagan.
Stephen Kelchaw – Construction ManagementSenior Thesis Final Presentation4/13/2010 Upper Dublin High School Construction Project The New Upper Dublin High.
The Office Building Washington, D.C. Penn State Architectural Engineering Senior Capstone Project Brett Miller | Construction Option Advisor: Dr. Ed Gannon.
GARY NEWMAN STRUCTURES OPTION ADVISOR: DR. HANAGAN SENIOR THESIS PRESENTATION SPRING 2008.
Kennedy Krieger Institute Outpatient Medical Center Baltimore, Marylan d Katie Sennett Construction Management Dr. Messner Spring 2008.
Charles Miller Construction Option Spring Dr. Riley WestEnd25.
Army National Guard Readiness Center Arlington, VA Arne Kvinnesland Construction Management AE Senior Thesis Final Presentation, Spring 2010 The Pennsylvania.
SEAN BEVILLE STRUCTURAL OPTION ADVISOR: PROF. BOOTHBY APRIL 13, 2009 TEMECULA MEDICAL CENTER “STRUCTURAL SYSTEM OPTIMIZATION” THE DEPARTMENT OF ARCHITECTURAL.
Paul Roberts Senior Thesis 2010 Construction Management.
The Health Care Center Dauphin County, PA Ken Lorenz Penn State University Architectural Engineering Construction Management April 17, 2007.
Wilsdorf Hall Materials Science Engineering & Nanotechnology Building University of Virginia Leaha Martynuska Construction Management Option Senior Thesis.
The Towers at the City College of New York Robin Scaramastro - Structural Option - Advisor: Dr. Memari Senior Thesis Final Presentation – Spring 2007.
Reinsurance Group of America (RGA) Global Headquarters Natasha Beck Structural Option Faculty Advisor: Heather Sustersic Images courtesy of Gensler & Tom.
Rensselaer, NY Meral Kanik Structural Option Advisor: A.M. Memari April 14, 2008.
Jonathan Goodroad Structural Option 2005 Thesis Penn State AE Delaware State University Administration and Student Services Building.
Project Introduction  New high-tech classroom and lab facility  Area : 30,000sq.ft.  Function –To provide a home for innovative courses that take a.
APPELL LIFE SCIENCES York College of Pennsylvania Joshua Martz | Dr. Srebric | April 11, 2011 Image Courtesy of RLPS, Ltd.
Craig Owsiany Architectural Engineering – Construction Management STEM Building Hagerstown Community College Hagerstown, Maryland Science Technology.
Oklahoma University Children’s Medical Office Building Oklahoma City, Oklahoma AE Senior Thesis Final Report April 14, 2014 Jonathan Ebersole Structural.
151 First Side William J. Buchko introduction overview proposal structural depth acoustics breadth cm breadth conclusions 151 First Side Pittsburgh, PA.
Computer Associates International, Regional Office
The Mary J. Drexel Home Assisted Living Addition Bala Cynwyd, PA Penn State AE Senior Capstone Project Gjon Tomaj – Construction Management Option Advisor:
Eastern USA University Academic Center Alexander AltemoseIStructural Option.
Presented by Cameron Mikkelson April 16, 2014 Silverado Senior Living Brookfield, WI Analysis Topics On-site Prefabrication of Interior Wall Panels Installation.
Arts & Humanities Instructional Building Noah J. Ashbaugh Construction Management 2006.
Malory J. Faust ∙ Mechanical Option ∙ Senior Thesis 2007.
Student Health Center Jacob Brambley - AE (structural option)
Brandon mckee ae senior thesis 2007 construction management penn state university ambridge area high school Ambridge Area High School ambridge, pennsylvania.
Hamot Women’s Hospital Erie, PA Michael Galleher Mechanical Option l AE-Senior Thesis l April 12, 2011 l Advisor Dr. Jelena Srebric.
THE NORTHBROOK CORPORATE CENTER Redesign of the Lateral Load Resisting System.
ANTONIO DESANTIS VERNE STRUCTURAL OPTION ADVISOR: PROF. PARFITT APRIL 14, 2008 BRIDGESIDE POINT II PITTSBURGH, PA “BUILDING SYSTEM OPTIMIZATION” THE DEPARTMENT.
Manoa Elementary School Amanda Cronauer Faculty Advisor: Dr. William Bahnfleth 14 April 2010.
Philip Mackey The Pennsylvania State University Architectural Engineering L/E Option HC HOLY CROSS HOSPITAL – NORTH ADDITION FINAL REPORTPhil Mackey Holy.
AE Senior Thesis Natalie Bockhorst│Construction Management Chimay Anumba, PhD. PE Advanced Individual Training A.I.T. Barracks Fort Eustis, VA.
Villanova University: School of Law Jason Greer The Pennsylvania State University Architectural Engineering Lighting/Electrical Option Senior Thesis –
North Hall | American University| Washington D.C.
Building Environmental Systems
The Stuckeman Family Building
LIGHTRUSS Size 2 LED.
David Anderson Mechanical Option
Multistory Office Building
Advisor: Professor M. Kevin Parfitt
Hyde Park Central School District
Redifer Commons Addition & Renovation Project
Multistory Office Building
Wrangle Hill Elementary School New Castle, DE
Ryan Johnson - Structural Option
Biobehavioral Health Building, University Park, PA
LONGWOOD AT OAKMONT HEALTHCARE CENTER
Epuni Primary School LED Lighting Trial 2016 Final Report
Justin Pennycoff AE Senior Thesis 2008 Construction Management
TOWERS CRESCENT BUILDING B Mike Synnott Structural.
Lehigh Valley Heritage Center
Project Background Type of building: Mixed-use residential building
Construction Management Option
Rutgers University Law School Building Addition and Renovation Nathan E. Reynolds Advisor: M. Kevin Parfitt Structural Option The Pennsylvania State.
Project: 250 West Street, Columbus, Ohio
Presentation transcript:

MEDICAL OFFICE BUILDING at Tysons Corner KAISER PERMANENTE MEDICAL OFFICE BUILDING at Tysons Corner McLean, Virginia Brooke Helgesen Advisor: Dr. Chimay Anumba Construction Management

MEDICAL OFFICE BUILDING at Tysons Corner KAISER PERMANENTE MEDICAL OFFICE BUILDING at Tysons Corner McLean, Virginia PRESENTATION OUTLINE Project Background Analysis 1-IPD Coffer Design Overview IPD Case Study Cost/ Schedule Impact Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements Brooke Helgesen Advisor: Dr. Chimay Anumba Construction Management

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management LOCATION: 8008 West Park Drive McLean , VA COST: $44,078,649 CONSTRUCTION DATES: March 16, 2011- May 8, 2012 SIZE: 241,175 SF FUNCTION: Short term care Medical Office Building: SCOPE OF WORK: Renovation & Construction of Mechanical Tower Addition N Kaiser Permanente MOB

Integrated Project Delivery Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Integrated Project Delivery Analysis 1- IPD Design Bid Build IPD Delegated risk Shared risk Uncertainties not foreseeable Uncertainties more predictable Hidden costs: increased claims/ disputes, change orders, reputation, etc. Upfront Cost: Adequate planning minimizes change orders, disputes, etc. Limits cooperation, coordination, innovation Promotes teamwork and more ideas Contract documents are known from the beginning although not always accurate. Lack of contract documents that spell out in detail what happens in failed events Everyone has their own risk/ goals. Built on trust/ must have good team IPD vs. DESIGN-BID-BUILD GOAL: To research and compare the costs and risks of IPD versus Design Bid Build specifically for the coffer design issue on the Kaiser Permanente Project.

Case Study: The House of Temple of Scottish Rite Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Case Study: The House of Temple of Scottish Rite The House of Temple Project: IPD LESSONS LEARNED about IPD: Save money & time More enjoyable atmosphere Promotes innovation and ideas! Investigation (Everyone) (1 year) Price increase 3-4% Putting team together (Owner) (1.5 years) Generating Contract “Real” Design (Currently) Construction (Future-Approx. 24 months) $2-3 million: Upfront cost The House of Temple Project: Design-Bid-Build (Hypothetical) Design Phase (Owner/ Architect) (Approx. 1 year) Bid Phase (Owner / Architect) (Approx. 3 months)   Construction (Owner, Architect, GC, Subcontractors) (24 months plus time for $7-8 million worth of change orders) Buyout of subcontractors (Owner, Architect, GC) $7-8 million: Change Orders How could this help Kaiser Permanente Project?...

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Analysis 1- IPD ISSUE: Fire Rating the Waffle Slab Coffers COST IMPACT: Lost labor hours Extra materials Removal/ re-installation Repeat inspections Total: $250,000 SCHEDULE IMPACT: Delayed: track installation, MEP overhead, interior wall framing Coffer production dropped: 25 coffers per day per man to 16 /day/ man Total: 5 Month Process

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Conclusions IPD could have helped to: Better understand severity of coffer design issue Integrate project team early on to increase communication Allocate accurate amount of money for coffer activity Early detection of coffer design issue using IPD could have saved a: 5 month & $250,000 process

Curtain Wall Façade Re-design Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Curtain Wall Façade Re-design PROBLEM IDENTIFICATION Unforeseen water infiltration from cracks in existing 1980’s precast panels & leaks in existing glazing. SOLUTION Removal of existing precast panels and glazing Installation of Curtain Wall System for: Improved water protection Increased day-lighting Updated aesthetic appeal

Curtain Wall Façade Re-design Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Curtain Wall Façade Re-design SYSTEM DESIGN Kawneer 1600 System 1 Curtain Wall CURTAIN WALL COVERAGE: West & East Facades: 11,584 SF About 27% of Building Surface Area North & South Facades: 22,708 SF About 53% of Building Surface Area Total: 34,292 SF About 81.3% Building Surface Area INSTALLATION Crane & swing stage at every floor Anchor to concrete slab at each level

Architectural Elevations Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Architectural Elevations PROPOSED CURTAIN WALL ELEV.ATIONS 30% Increase of Exterior Glass East West PREVIOUS WESTERN FACADE North South

Curtain Wall Façade Re-design Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Curtain Wall Façade Re-design COST IMPACT SCHEDULE IMPACT Curtain Wall 1600 System Total=$2,440,980 Comparison to Precast Injections/Glazing Replacement: Total=$2,038,860 Shop drawings: 8 weeks Fabrication: 8-10 weeks Removal: 120 days Replacement/Installation: 140 days   7 Month Duration. No Significant Impact September 6, 2010- April 4 2011 *7 Month duration before project construction begins* $402,120 cost difference

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Conclusions CONCLUSIONS FOUND FOR CURTAIN WALL 30% Increase of glass & day-lighting $402,120 cost increase No schedule impact Updated & improved aesthetic appeal Increased water infiltration protection

LED Temporary Lighting Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management LED Temporary Lighting Analysis 3- LED Temp Lighting PROBLEM IDENTIFICATION SOLUTION Lack of sustainable features High energy demand of the building systems Increased cost associated with maintenance of temporary lighting during construction Switch all temporary lighting from Fluorescent to energy saving LED’s Analyze power consumption, cost savings, and feasibility of this change

LED FLEX SLS Components Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management LED FLEX SLS Components Analysis 3- LED Temp Lighting POWER SUPPLY 450W transformer. 110-265VAC input Outputs 24VDC Can utilize 2 simultaneous bus lines 24 VDC Bus Line T-Connector & Module AC/DC Transformer & Power Supply Box Input Voltage 15 ft. 10 ft. 2000 lumens=8fc LED MODULE •2000 “focused” lumens • 8 fc @ 15 ft. spacing on center. 10 ft. mounting height. •Lumen Maintenance: 70% at 50,000 hours T-CONNECTOR & 24VDC BUS LINE •Easy and quick-to-install T-Splice •125’ length 12 gauge wire standard

LED Temporary Lighting Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management LED Temporary Lighting Analysis 3- LED Temp Lighting   LED Incandescent Metal Halide Fluorescent Durability Solid State circuitry, not affected by vibration and impact. No filament, no glass to break Easily damaged by vibration or impact causing failure Lifetime Minimum 50,000 hours at 70% lumen maintenance 50% failure rate at 2,000 hours for typical 75 Watt bulb 10,000-15,000 hours is common Typically 24,000 hours Efficacy Emit 100 lm/W Emit 15 lm/W. Emit 65+ lm/W range. Emit 48+ lm/W range. Photometric Graph- LED Flex SLS System Photometric Graph-F32T8 Fluorescent, 2 lamps, 2900 lumens/lamp 100 Degree Spread 360 Degree Spread

LED Temporary Lighting Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management LED Temporary Lighting Analysis 3- LED Temp Lighting POWER CONSUMPTION   Flex LED Incandescent Metal Halide Compact Fl. Power Consumption 16,764 W 246,580 W 119,340 W 104, 800 W Electricity cost of $.14/kWh Project Duration=13 months

LED Temporary Lighting Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management LED Temporary Lighting Analysis 3- LED Temp Lighting COST COMPONENTS CONSIDERED: Breakdown of Total Cost per system (13 month duration) Total Cost Breakdown Flex LED Incandescent Metal Halide Compact Fluorescent Component 155,034 43,750 37,500 Install/uninstall 21,829 62,500 Maintenance 30,469 153,563 82,875 120,335 Power 21,968 327,600 158,545 126,329 Total 198,832 562,413 341,420 325,314  

LED Temporary Lighting Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management LED Temporary Lighting Analysis 3- LED Temp Lighting Largest first to second project cost difference

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Analysis 3- LED Temp Lighting GOAL: Analyze further benefits of LED FLEX SLS System over Fluorescent lighting with a lighting layout and power plan for the Kaiser Tysons Project. LED Layout Fluorescent Layout

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Analysis 3- LED Temp Lighting LED FLEX Power Plan Fluorescent Power Plan 3rd 2nd 1st Lower Level Basement ASSUMPTIONS: 20’ spacing on center 27440SF/ 400 SF= 70 Fixtures needed 3 Ckts needed SCHEMATIC PLAN ASSUMPTIONS: LED Module Spacing: 15 ft 8 kits per floor= 120 Modules per floor

LED Temporary Lighting Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management LED Temporary Lighting Analysis 3- LED Temp Lighting Lighting/ Electrical Breadth Results:   Cost savings of $12,600 From reduction in wiring needed

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management LED Temp. Lighting Analysis 3- LED Temp Lighting CONCLUSIONS Cost: Reduces labor and maintenance costs Power savings cost for whomever is paying electric Reduces layout cost Safety Sustainability It is recommended to use the FLEX SLS LED System

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Green Roof Terraces Analysis 3- LED Temp Lighting GOAL: EXPECTED BENEFITS: Utilize the 3 exterior terraces as Green Roof space to add value for the owner and benefit patients. Provide patient views/access to nature to promote healing Add value and sustainable features to the design of the building Further promote Kaiser Permanente as an innovative healthcare facility

Research: Health Benefits Presentation Outline: Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Research: Health Benefits Analysis 3- LED Temp Lighting Results of Green Roof Health Benefit Research Quicker patient recovery process Patients needed less medication Less unfavorable assessments Reduces transmission of sound by about 40 decibels Reduces stress for patients, staff, and families. Increases productivity of workforce Increases job satisfaction of workforce Decreases employee sick days St Elizabeth Hospital in Appleton, Wisconsin

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Green Roof Terraces Analysis 3- LED Temp Lighting LIVE ROOF SYSTEM: MODULARIZED LITE ROOF Dead Load (Concrete Slab) = 150 psf Live Load for Assembly Areas (Non Reducible) = 100 psf Snow Load= 18 psf Total Load= 268 psf Structural Load + LiveRoof Load Percent Change Extensive: 268 psf + 15 psf= 283 psf 5%

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Analysis 3- LED Temp Lighting Lower Level Terrace: 3,248 SF Second Level Terrace: 1,290 SF First Level Terrace: 3,960 SF Total: 8,500 SF

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Green Roof Terraces Analysis 3- LED Temp Lighting COST CONCLUSION 8, 500 SF X $16/SF = $136,000 It is recommended to utilize Green Roof Terraces when comparing cost of $136,000 to the many benefits such as the healing process, sustainability, and quality offered. Typical payback period of 14 years from energy savings SCHEDULE 8 day duration to complete the 3 Green Roof Terraces

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management CONCLUSIONS Analysis 3- LED Temp Lighting Analysis 3: LED Temporary Lighting Cost savings: $165, 842 Saves 88,036 Watts Ease of installation Safety Implement Analysis 1: Integrated Project Delivery Help cost & time lost from coffer design issue Early collaboration/more enjoyable/ innovative Implement Analysis 2: Curtain Wall Façade Re-design $402, 120 cost increase No schedule impact Improved aesthetics Increase water infiltration protection Implement Analysis 4: Green Roof Terraces Cost: $136000 Health benefits Sustainable feature Implement

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Analysis 3- LED Temp Lighting Dr. Chimay Anumba AE Faculty Family & Friends! Thank you!

Presentation Outline: KAISER PERMANENTE MOB at TYSONS CORNER Project Background Analysis 1-IPD IPD Case Study Coffer Design Overview Analysis 2- Curtain Wall System System Design Cost/Schedule Impact Benefit Analysis Analysis 3- LED Temp. Lighting FLEX SLS System Lighting/ Electrical Breadth Feasibility Analysis Analysis 4- Green Roof Terraces Health Benefit Research Design Layout Final Conclusions Acknowledgements KAISER PERMANENTE MOB at TYSONS CORNER McLean, VA Brooke Helgesen Construction Management Questions Analysis 3- LED Temp Lighting