Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Status of the LHC Mike Lamont for the LHC team. The LHC Very big Very cold Very high energy 2.
LHCC 3rd June 2015 Mike Lamont for the LHC team
LHC status and commissioning plans Gianluigi Arduini, CERN, AB/ABP 10 th September 2007 Acknowledgements: R. Bailey, M. Lamont.
LHC status and commissioning plans. LHC in 4 slides Lest we forget Progress to date Present schedules Consequent plan for 2008.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
LHC status & 2009/2010 operations Mike Lamont. Contents Consolidation – brief recall Splices Operational energies Potential performance Present status.
Stefano Redaelli Beam Department - Operations Group Operational Aspects of the Phase II Crab Cavity System LHC-CC09 3 rd LHC Crab Cavity Workshop European.
Partikeldagarna, Göteborg 21 September 2007 LHC: Status and Plans Lyn Evans.
LHC progress Report LHCC Wednesday 23 rd March 2011.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
RHIC Run14 Time Meeting. Run14 Status – Apr. 15 Operations running well, 12 stores over the past 7 days with 1 lost to another “super quench”. Testing.
EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont.
Running scenario 2009/10 Run through components – and then synthesis.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
Turnaround time in modern hadron colliders & store-length optimization
LHC Status Report 1 Jan Uythoven For the LHC Team LPCC
News from the LHC J. Wenninger CERN Beams Department Operation Group
Mike Lamont An attempt at synthesis Acknowledgements all round
LHC commissioning and interaction with the experiments
Wednesday 8.9 External crossing angles:
LHC Commissioning with Beam
Minimum Hardware Commissioning – Disclaimer
Status of LHC installation & New Installation Schedule
MPI-ATL Calor Meeting 7-Sep-2009 H. Oberlack MPI für Physik, Munich
LHC schedule.
The LHC - Status Is COLD Is almost fully commissioned
Long Shutdown for the LHC: Vacuum Beam Pipes
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Powering the LHC Magnets
Powering from short circuit tests up to nominal
Summary of week 7 Hardware Commissioning:
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
LHC status Benoit Salvant (Beams department, Accelerator and Beam Physics group) for the LHC complex teams With many thanks for their inputs to J. Boyd,
The Status of the LHC machine
Machine plans - Alignment workshop
Status of the LHC December 2009
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
LHC status & 2009/2010 operations
LHC Morning Meeting - G. Arduini
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Machine Protection Xu Hongliang.
Beam requirements and operational scenarios in 2010
CSP Meeting CERN CERN Accelerators in th November 2010
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
6 months of beam operation in 2010
Overall commissioning strategy for protons (estd. 2005)
LHC Beam Operations Past, Present and Future
Machine Tolerances in Cleaning Insertions
Sunday/Monday & :30 Stable beams. Fill #1851.
Machine plans - CMS startup workshop
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
LHC status & 2009/2010 operations
SLHC-PP kick-off meeting, CERN 9 April 2008
Collimators: Operations - Baseline Assumptions
Thursday 26th July 13:21 Fill 2880 beam dumped
Luminosity and time estimates
Summary for LPC (March 7th, Ralph Assmann)
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Hardware Commissioning
Beam commissioning plans, 2007 and 2008
15/12/2009 Vacuum interlock in sector 78 understood  out-gassing of a Penning gauge ignited as a result of ionization or dust arcing In conclusion: NO.
LS 1 start date 12th June Schedule Extension 2012 run Extension of 2012 run approved by the DG on 3rd July 2012.
LHC Machine Advisory Committee, CERN 12th June 2008
Presentation transcript:

Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008 LHC status

Overview Before beam With beam What’s has to be done Present status Review of Particle Physics, PDG, Chapter 25 Before beam What’s has to be done Present status Schedule With beam Commissioning plans Early luminosity expectations 18/01/2008 LHC status

8 essentially independent sectors 3.3 km of dipoles/quadrupoles++ mostly at 1.9 K 18/01/2008 LHC status

Hardware Commissioning Pre-beam Installation Interconnection Pressure tests (vacuum leaks, design faults) Electrical quality assurance (earth faults, bad splices…) Cool-down (cryogenics, vacuum leaks) Hardware Commissioning (Quenches, electrical problems, non-conformities) 18/01/2008 LHC status

Installation - dipoles Descent of the last magnet, 26 April 2007 30’000 km underground at 2 km/h 18/01/2008 LHC status

Installation - RF Plus collimators, beam dump, injection hardware, instrumentation etc… 18/01/2008 LHC status

Magnet interconnections Vacuum, bellows, RF contacts plus leak checks Thermal shield, heat exchanger Bus bars: superconducting splices x 10,000 (induction welding) Corrector circuits: splices x 50,000 (ultrasonic welding) 18/01/2008 LHC status

Closure of continuous cryostat - November 07 18/01/2008 LHC status

Pressure tests 18/01/2008 LHC status

Cryogenics – huge system ~120 tonnes of He 10,000 tonnes LN2 Cold mass 31,000 tonnes X 8 18/01/2008 LHC status

Cryogenics flushing… Sector 81 18/01/2008 LHC status

Cool down 2 3 1 18/01/2008 LHC status

Cool down Sector 7-8 June 2007 18/01/2008 LHC status

Cool down Sector 4-5 today 18/01/2008 LHC status

Hardware Commissioning (HWC) Commissioning of continuous arc cryostat & LSS cryostats (insertion quadrupoles…, inner triplet, etc.) Cryogenics, Vacuum, QPS, PIC, Powering: Electrical Quality Assurance, Tests prior to powering, Powering (QPS, PC, MPS) of all circuits one by one, Magnets, busbars, DFBs, services, UPS, AUG, controls… Powering of all the circuits of a sector together Power converters: protection, calibration, ramp tests performed Interlocks, compatibility tests, protection tests Stored magnetic energy up to 1.29 GJ per sector. [154 dipoles per sector powered in series: ~11700 A at 7 TeV] 18/01/2008 LHC status

HWC - example 18/01/2008 LHC status

LHC Status – January 2008 1-2 Global leak test completed. Leak localization and repair. 2-3 Start cryogenics purging and flushing week 5 3-4 Pressure test. Leak repair. 4-5 Sector cold at around 2 K. Seen 8.5kA in main dipole circuit. 5-6 Cool-down will be re-started w.5. ~120 K at the moment. 6-7 Cool-down delayed until week 8-9. 7-8 Start cool-down in week 4. Has been at 1.9 K already. 8-1 Start cool-down in week 6. 18/01/2008 LHC status

Priority now is to get the machine cold and leak tight. LHC status – January 2008 Installation effectively complete Interconnection work effectively complete First two sectors cooled down to nominal temperature and operated with super-fluid helium Power tests progressing well Third sector in cool-down Priority now is to get the machine cold and leak tight. 18/01/2008 LHC status

Latest schedule – October 9 . 2007 2008 Mar. Apr. May Jun. Jul. Aug. Oct. Sep. Nov. Dec. Jan. Feb. 12 23 34 45 56 67 78 81 Machine Checkout Beam Commissioning to 7 TeV Consolidation 10 11 13 14 15 16 17 19 18 20 21 22 24 25 26 27 29 28 30 31 32 33 35 36 37 39 38 40 41 42 43 44 46 47 49 48 50 51 52 01 02 03 04 05 07 06 08 09 2-3 weeks behind at the moment Interconnection of the continuous cryostat Leak tests of the last sub-sectors Inner Triplets repairs & interconnections Global pressure test &Consolidation Flushing Cool-down Warm up Powering Tests General schedule Baseline rev. 4.0 18/01/2008 LHC status

Schedule 2008 High parallelism for the power tests Machine closed April 2008 The machine should be entirely cold beginning of June Will take 450 GeV beam once machine is cold, even if some sectors are not qualified for 7 TeV. Success-oriented schedule. Acknowledge possibility of possible problems requiring additional warm-up/cool-down of sector Quantum of 2-3 months Delay in one sector or more  possible sector test 18/01/2008 LHC status

Machine cold – beam in at 450 GeV 450 GeV beam commissioning before main circuits fully commissioned to 7 TeV Important checks with beam – aperture, magnets Provides some lead time for problem resolution Interleaf with commissioning circuits to 7 TeV 18/01/2008 LHC status

Beam - energy 2808 bunches, 1.15 1011 protons per bunch Energy per beam up to 360 MJ British aircraft carrier at 12 knots Through a very cold, very dark, very small hole... 18/01/2008 LHC status

Machine Protection is critical… June 2009 18/01/2008 LHC status

Can leave the crossing angle off with up to 156 bunches per beam Beam - Crossing angle With 2808 bunches per beam work with a crossing angle to avoid parasitic collisions. Can leave the crossing angle off with up to 156 bunches per beam 18/01/2008 LHC status

Beam - Squeeze Small beam in the IP  big beams in the inner triplets  reduced aperture Therefore inject & ramp (& collide initially) with bigger beam sizes at IP. 18/01/2008 LHC status

Commissioning stages Safely establish colliding beams as quickly as possible Initial optics: β*= 11 m in IR 1 & 5 β*= 10 m in IR 2 & 8 Crossing angles off Low bunch intensity 1, 12, 43, 156 bunches per beam No parasitic encounters - no long range beam-beam Larger aperture in IRs 18/01/2008 LHC status

Stage A: commissioning phases 18/01/2008 LHC status

Stage A: commissioning phases 18/01/2008 LHC status

Beam Commissioning to 7 TeV Collisions Rings Total [days] 1 Injection and first turn 2 4 Circulating beam 3 450 GeV - initial 450 GeV - detailed 5 450 GeV - two beams 6 Snapback - single beam 7 Ramp - single beam 8 Ramp - both beams 9 7 TeV - setup for physics 10 Physics un-squeezed -   TOTAL TO FIRST COLLISIONS 30 11 Commission squeeze 12 Increase Intensity 13 Set-up physics - partially squeezed. 14 Pilot physics run 18/01/2008 LHC status

Stage A: First Collisions Approx 30 days of beam time to establish first collisions Un-squeezed Low intensity Optimistic! Approx 2 months elapsed time Given reasonably optimistic machine availability Continued commissioning thereafter Increased intensity Squeeze RHIC 2000: - First beam April 3rd - First successful ramp: June 1st - First collisions June 12th 18/01/2008 LHC status

Stage A - Luminosities 1 to N to 43 to 156 bunches per beam N bunches displaced in one beam for LHCb Pushing gradually one or all of: Bunches per beam Squeeze Bunch intensity IP 1 & 5 Bunches * Ib Luminosity Event rate 1 x 1 11 1010 ~1027 Low 43 x 43 3 x 1010 6 x 1029 0.05 4 1.7 x 1030 0.21 2 4 x 1010 6.1 x 1030 0.76 156 x 156 1.1 x 1031 0.38 9 x 1010 5.6 x1031 1.9 1.1 x1032 3.9 18/01/2008 LHC status

Pilot physics – the first month Interleaved physics and commissioning Push number of bunches, intensity, squeeze… 156 x 156 3 x 1010 protons per bunch β* = 2 m. Peak luminosity: ~1.2 x 1031 Integrated: few pb-1 Pushing the bunch intensities with 156x156 with reasonable operational efficiency another month would see 30-40 pb-1 Acceptable exit condition for 2008 18/01/2008 LHC status

Stage B – 75ns Up to 936 bunches Parameter tolerances: Tightened up. Optics/beta beating under control Emittance conservation through the cycle Commission crossing angles. Injection, ramp and partial squeeze Long range beam-beam, effect on dynamic aperture, Need for feedback Orbit plus adequate control of tune and chromaticity through snapback. Lifetime and background optimization in physics with a crossing angle and reduced aperture Won’t happen overnight Plus Machine Protection with increased intensity 18/01/2008 LHC status

Stage B - Luminosities * Ib Luminosity Event rate % Total I Per month [pb-1] 4 4 x 1010 5.6 x 1031 0.32 0.12 40 2 1.1 x 1032 0.64 100 6 x 1010 2.5 x 1032 1.1 0.17 220 8 x 1010 4.5 x1032 2.6 0.23 400 18/01/2008 LHC status

2009 Of the order 2-3 fb-1 Initial luminosity 8 x 1032 cm-2s-1 (say) Commission and exploit 75 ns. Move to 25 ns Initial luminosity 8 x 1032 cm-2s-1 (say) 2808 bunches, β* = 2 m, 6 x 1010 protons per bunch Luminosity lifetime: 27 hours Fill length: 12 hours Turn around time: 5 hours 100 days of physics Operational efficiency 60% Of the order 2-3 fb-1 18/01/2008 LHC status

+ Nominal LHC beam in SPS LHC transfer lines 23.10.2004  first beam at end of TI 8 IR8 28.10.2007, 12:03 first beam at end of TI 2 TI 8 SPS LHC IR2 + Nominal LHC beam in SPS TI 2 TI 2 beam test 28./29.10.07 PMI2 18/01/2008 Courtesy of V. Mertens LHC status

Expectation management! Conclusions Priority is to get the machine cold and leak tight Machine should be cold in June 2008 Caveat: problems found at cold cost ~3 months to fix Take beam at 450 GeV before machine ready for 7 TeV First 7 TeV collisions 2+ months after first taking beam Expectation management! The LHC is a huge, complex beast. Progress is good It will work BUT it is going to take time 18/01/2008 LHC status