WP 3 coordination meeting Saclay May 2008

Slides:



Advertisements
Similar presentations
Progress and Plan for Superconducting RF Cavity RF Group.
Advertisements

LCLS-II Cryomodules Production Plans at Fermilab
SM18 Vertical/Horizontal Test Setup LHC Crab Cavity Engineering Meeting Session: Cavity Cryostat Testing & Integration in SM18Cavity Cryostat Testing &
FNAL-SCRF 会議報告 1. Cryomodule, Plug-compatible Interface ( 大 内) 2. High Pressure Code, 5K Shield (Tom Peterson)
S1 Global Module Cavity String Assembly Workflow Tug Arkan January 15, 2010.
Needs of a European SCRF Facility - the BIG plan Lutz Lilje DESY -MPY- DESY 11/2006 Planning Resource needs.
LCLS-II cryomodule alignment. 2 Wednesday meeting, 6/17/2015 Topics Alignment of Components inside the CM Tunnel Network Tolerances LCLS-II cryomodule.
CERN status - Nb cavity – Manufacturing 1 15/Nevember/2010, Ofelia Capatina EN/MME 1 SPL Cavity Working Group Meeting TaskExternal Company CERN Provide.
Assembly Procedures of the cavities Ancillaries (RF power coupler, Tuning system, RF cables) 19/03/2014Mathieu Therasse BE/RF/SRF1 Special Linac WG meeting:
Summary ( Cryomodule, Plug-compatible Interface) Norihito Ohuchi.
56 Mhz Vacuum Mike Mapes Mhz Insulating Vacuum TURBO PUMP WITH GATE VALVE AND GAUGE SET MOUNTED ON TANK SIMILAR TO RHIC CRYOSTAT & VALVE.
LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.
Accelerator/ Medium Beta Cavities Paolo Michelato INFN Milano - LASA April 21, 2015.
Mickaël LACROIX (LAL)ILC-HiGrade Scientific and Annual Meeting 1 IN2P3 Les deux infinis IN2P3 Les deux infinis Mickaël LACROIX (LAL) ILC-HiGrade Scientific.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
LCLS-II Cryomodules Production at Fermilab Tug Arkan, 7/17/2014.
CMS Double Chooz HESS Edelweiss Herschel ALICE Detecting radiations from the Universe. EXPERIENCE WITH HARDWARE PREPARATION FOR XFEL TTC topical workshop.
CMS Double Chooz HESS Edelweiss Herschel ALICE Detecting radiations from the Universe. EXPERIENCE WITH VACUUM SYSTEM FROM DESY AND CEA SOLUTIONS TTC topical.
Guillaume Olry, Sébastien Bousson CNRS/IN2P3/ IPN Orsay – Paris-Sud University Experience on Spiral2 cavity cleanliness degradation during clean room assembly.
Visiting DESY for S1-G module Norihito Ohuchi 2009/8/251 19th Biweekly Webex meeting (S1-G, Cryomodule, Cryogenics)
Overview on DESY Infrastructure and up date/ grade Activities schedule status and plans Axel Matheisen DESY.
C.MADEC - TTC meeting E-XFEL cryomodule assembly : prototyping phase at Saclay.
201 Mhz Cavity Installation. Removing Old 201 Cavity Came in through door with fork lift Will go out through labyrinth Requires new 3 ton Gantry crane.
Status Report of the Review of Vacuum Systems and Procedures Tug Arkan, Allan Rowe.
Cryomodule Assembly Facility (CAF) at Fermilab: Feasibility Overview for Project X & future SRF Cryomodules Assemblies Tug Arkan February 21, 2012.
Hao Guo LINAC Department Institute of Modern Physics.
Cryomodule Assembly Facility Fermilab Cleanroom: Assembly/Disassembly Tools Tug Arkan 1.
Vacuum experiences on XFEL Beam Position Quadrupole Units (BQU) preparation Marco Schalwat TTC Topical Workshop on SRF Cryomodule Clean Room Assembly CEA.
FNAL Cryomodule Assembly and Installation Plans Tug Arkan May 22, 2015.
Warm Girder UHV Components John Heckman Anthony DiPette Vacuum Group 2/29/2016.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
S. Barbanotti - DESY Requirements Conformance for SRF Cryomodules Workshop 16/10/2014 – ESS, Lund XFEL cryostat main components: Quality Assurance and.
Overview of elliptical cryomodules vacuum system Vacuum Equipment Standardization meeting February 2014 P. Bosland – C. Darve – N. Elias.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Vacuum Related Procedures and Tools of IHEP ILC Test Cryomodule Assembly Jiyuan Zhai (IHEP) TTC Topical Workshop on SRF Cryomodule Clean Room Assembly.
JLAB Cryomodule Assembly Facilities Visit Report Tug Arkan, Yuriy Orlov March 26, 2012.
ILC-HiGrade annual meeting - 22 November 2010 ILC-HiGrade Meeting Cavity-Treatment at CEA Saclay (WP6) F. Eozénou.
JLab UHV omponent leaning and nitrogen blow off procedures and development Ari D. Palczewski JLab Ari D Palczewski, TTC topical 13Nov2014 Sacley France.
Status Report of the Review of Vacuum Systems and Procedures Tug Arkan, Allan Rowe 3/7/
Update on Work Package 12 Beam Transport Modules (LWUs) - UK-A-6 Dr Paul Aden, STFC Daresbury Laboratory ESS Beam Diagnostics Forum, Lund, 11 th February.
Infrastructure status and plans at CERN 1) W. Weingarten/CERN TTC Milano 28 February - 3 March W. Weingarten/CERN 1)Most of the slides are based.
ASSEMBLY OF THE IFMIF CRYOMODULE Janic Chambrillon On behalf of the SRF-Linac Team TTC Meetting - June 5th – 8th, Saclay.
Status of E-XFEL Module Assembly at Saclay
Status of the M-ECCTD F. Peauger - P. Bosland
Field Emission Minimization for LCLS-II
Cryomodule test stand at ESS site
Assembly of Crab Cavities couplers in SM18 clean room
Medium beta cryomodule demonstrator M-ECCTD
DESY Experiences on Use of Gas overlay during Assemblies
Mark Pendleton – STFC Daresbury Laboratory
TTC Topical Workshop on SRF Cryomodule Clean Room Assembly
Definition of work flow for string DESY Example on critical operation
Acceptance criteria for cleanroom infrastructure
The situation is far better than I had thought.
DESY experiences on education and training of cleanroom team
XFEL Vacuum System Commissioning
XFEL Cold mass & vacuum vessel non-conformities Detected At saclay
Degradation and possible sources Statistic of resonators
IMP Cryomodule Assembly and Alignment
INSTITUTE OF HIGH ENERGY PHYSICS
Cryomodule Assembly Plan
Daresbury ESS In-Kind Contributions
F. Peauger (mainly for CM components)
Incoming inspection of the cavities at saclay
Critical design review #1 for medium beta cavity cryomodules 3-4 APRIL SAFETY AND RAMI INPUTS - Franck Peauger OLIVIER KUSTER (INSTALLATION AND.
Issues of “Particle Free”
SNS Coupler Shipping Plans
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Procedure for MEBT installation in the accelerator tunnel at ESS
Presentation transcript:

WP 3 coordination meeting Saclay 26-28.May 2008 2nd session String assembly WP 9 (in side cleanroom) 4 topic to be presented and discussed o Cleaning and hand over conditions ( update on Cavity transport) o Vacuum o Alignment of string o Control options ( QC QA)

XFEL Cryomodule Workshop Saclay Cleaning and hand over conditions A.Matheisen XFEL Cryomodule Workshop Saclay May 26 – 28 2008

Cleaning and hand over conditions News on Cavity Transportation system Actual hand over of Cavities @ DESY during Actual layout of CV transport frame / Insert Proposal on work steps to be done (from transport insert to class 10) Cleanliness conditions on infrastructure material “Personal” Baseline list of parts and hand over conditions

News on cavity transportation system a) Actual hand over of Cavities @ DESY Insert with Cavity Transportation cart (Fork lifter) Portable cleanroom

News on cavity transportation system b) Actual layout of CV transport frame / insert Transport- and test frame will be Loaded with cavities at company Transported to DESY Used for cavity test at DESY Transported to CEA Unloaded from cavities at CEA  Send back to companies NEEDS PERFECT COORDINATION AND DEFINITION AT HAND OVER POSITIONS

News on cavity transportation system b) Actual layout of CV transport frame / Insert Local pumping line at place of installation Fork lifter connection Hand over Actual design of Cavity Test frame No Cavity frames on during test and transport !!

News on cavity transportation system Schematic of Vacuum system Vacuum connection on Cavities “Hand over” point Basic design issues: Central pumping line and UHV pumps are local !!

Proposal on work steps to be done transport insert to class 10 Install transport frame to “cavity delivery station” Install local cleanroom Connect Vacuum line under cleanroom cl 10 Open CV valves and control vacuum Close CV valves Control RF Vent main pump line and “pump circle” Dismount “pump circle” Remove local cleanroom Install frame to Cavity Remove CV from transport insert Car was cavity and dry it Control cleanliness Install CV to stock / power coupler installation place

News on cavity transportation system To be discussed 3 ways to clean parts Manually Clean each area with cleanroom wipers + alcohol Blowing with ionized air Cleanliness ok drawback: Time and man power consuming / risk of missing areas 2) US cleaning and rinsing US bath with water overflow and recirculation required Draw back: Separate rinsing bath required for fast removal of solvent Large amount of water (Design of basin/ size) 3) “car wash” / “dish washer” High pressure to remove particulates circulation of water Washes particulates away draw back: Not commercialized system ????

Cleanliness conditions on infrastructure Details on QC Talk N.Krupka

Cleanliness conditions on material

Cleanliness conditions on “Personal”

Baseline list of parts and hand over conditions Parts to deliver cleaning done by Transport Way Cavities WP 4 To be cleaned to cl 10 quality WP 9 SACLAY internal Bellows Gate valve No 2 WP 8 See talk H Remde Vacuum: L <1E-10 mbar l/sec Particulates: << Cl 10 ready for installation Boxes ? DESY to SACLAY BPM / Quad WP 11 as a unit BPM Quad Gate valve Vacuum: L <1E-10 P <1E-7 or vented Particulates: Box ? Under investigation

Baseline list of parts and hand over conditions (continue.) Parts to deliver condition cleaning done by Transport Way Bolts Nuts Washer Gaskets WP 9 Cleaned to << cl 10 Saclay Internal CEA Power coupler WP5 tested on test stands See discussion SACLAY ORSAY DESY See workshop Orsay to SACLAY Infra structure else conditioned to <<cl 10