Study Results Common Case Study This slide deck contains results from the 2011 TEPPC Study Program. This study shows the results of the 2022 Common Case. This study serves as a base case for all 2011 and 2012 studies.
2022 PC1 – Common Case Central Question: What impact will future load growth and generation needs (as defined by the input assumptions) have on transmission congestion in the Western Interconnection? These Results will be used as the starting input assumptions for all 2011 and 2012 studies. Results follow…
2022 Common Case Results – Annual Generation by Resource Type
DRAFT
2022 Common Case Results – Region to Region Transfers Hourly transfers Presented at the end of this presentation.
2022 Common Case Results – Most Heavily Utilized Paths “Most Heavily Utilized” = A path that meets any one of the following criterion (10-year plan utilization screening): U75 > 50% U90 > 20% U99 > 5% Uxx = % of year that flow is greater than xx% of the path limit
2022 Common Case Results – Most Heavily Utilized Paths
Hourly region-to-region transfers AZNMNV To Ca_S
Hourly region-to-region transfers Basin To AZNMNV
Hourly region-to-region transfers Basin To Ca_N
Hourly region-to-region transfers Basin To Ca_S
Hourly region-to-region transfers Ca_N To Ca_S
Hourly region-to-region transfers Canada To NWUS
Hourly region-to-region transfers NWUS To Basin
Hourly region-to-region transfers NWUS To Ca_N
Hourly region-to-region transfers NWUS To Ca_S
Hourly region-to-region transfers RMPA To AZNMNV
Hourly region-to-region transfers RMPA To Basin
Hourly region-to-region transfers California Net Export Hours of net export = 6053 hrs
Questions or thoughts on this study?