3 issues identified in review

Slides:



Advertisements
Similar presentations
A/C Generator Systems.
Advertisements

New HV test specification for the LHC N. Catalan for the EI section.
1 Copper Stabilizer Continuity Measurement Project CSCM Mini Review Powering Implementation H. Thiesen 30 November 2011.
David Nisbet – LIUWG 17 th July 2008 LIUWG – Options for Powering Phase I David Nisbet Summary of points from LIUWG 7 Existing topology Future topology.
A. Verweij, TE-MPE. 3 Feb 2009, LHC Performance Workshop – Chamonix 2009 Arjan Verweij TE-MPE - joint stability - what was wrong with the ‘old’ bus-bar.
HOW THE DUMP RESISTOR’S TANK LOOKS LIKE COOLING OF THE LHC ENERGY EXTRACTION RESISTORS G. Peón (ST/CV), K. Dahlerup-Petersen, G. Coelingh (AT/MEL) Air.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
The diode lead resistance ‘issue’ A. Verweij, TE-MPE, CSCM workshop 7/10/2011 Contents:  Diode geometry  Measurements performed in the past  Measurements.
LHC diodes: Status report (for information)
19./20. September 2007 Current leads for FAIR Cryogenic Expert Meeting 19./20. September 2007 Birgit Weckenmann.
1 CSCM-7TeV Powering Implementation and ELQA Third LHC Splice Review November 2012 M. Bajko, M. Bernardini, B. Bordini, k. Brodzinski, J. Casas-Cubillos,
CSCM type test: Diode Leads and Diodes Gerard Willering & Vincent Roger TE-MSC With thanks to Bernhard Auchmann, Zinour Charifoulline, Scott Rowan, Arjan.
Simulation results for powering serial connected magnets Daniel Siemaszko, Serge Pittet OUTLINE : Serial configuration of full rated converters.
CSCM Project Status and Prospects Andrzej Siemko on behalf of the CSCM project core team: Mike Koratzinos, Jens Steckert, Hugues Thiessen and Arjan Verweij.
Measurement and data extraction. How to measure the splice and diode interconnections. Accuracy and issues of these measurements. Data extraction issues.
5 th Joint Hi-Lumi LHC-LARP Annual Meeting 2015 SC Link Protection A.Ballarino 28/10/2015.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
Actual Circuit Total inductance:15.4 H (154x0.1H) Total resistance:1 m  RB output current:13 kA RB output voltage:190 V Main Power Converter RB circuit.
Faster ramp rates in main LHC magnets Attilio Milanese 7 Oct Thanks to M. Bajko, L. Bottura, P. Fessia, M. Modena, E. Todesco, D. Tommasini, A. Verweij,
Advanced simulations of events in the RB circuit Short circuit to ground Quench of a dipole provoked by the quench heaters Emmanuele Ravaioli Thanks to.
The integration of 420 m detectors into the LHC
AT-ACR B. VULLIERMECSOC Meeting 29 September Cryogenics for LHC Test Benches Safety Aspects Overview of the Test Station Overview of the Operation.
Main dipole circuit simulations Behavior and performance analysis PSpice models Simulation results Comparison with QPS data Ongoing activities Emmanuele.
E.Sbrissa EP/TA3 - IC ATLAS EDR_MAG Magnet Project Fault analysis, QA & Failure rate.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
TE-MPE –EI, TE - MPE - TM 8/12/2011, Antonopoulou Evelina RQS circuit Simulation results Antonopoulou Evelina December 2011 Thanks to E. Ravaioli.
Powering the damping rings wigglers Daniel Siemaszko, Serge Pittet OUTLINE : Powering superconductive magnets, Powering wigglers strategy, Existing.
CSCM (Thermal Amplifier) Sequence and detailed planning 07/10/2011 M.Solfaroli Thanks to: K.Brodzinski, G.D’Angelo, M.Koratzinos, M.Pojer, R.Schmidt, J.Steckert,
XVII SuperB Workshop and Kick Off Meeting - La Biodola (Isola d'Elba) Italy May 28 th June 2 nd 2011 P.Fabbricatore Sezione di Genova The air core magnets.
SC Undulators protection and commissioning W. Venturini Delsolaro Acknowledgements: R. Denz, R. Maccaferri.
Comparison of magnet designs from a circuit protection point of view Arjan Verweij, CERN, TE-MPE with input from M. Prioli, R. Schmidt, and A. Siemko A.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
TEST FACILITY STATUS FOR TESTING CERN Marta Bajko WP10. EUCARD 2 Task 4 - HTS Magnet Tests, June 2015.
The most likely cause of death for a superconducting magnet Input data for thermal modeling of Nb 3 Sn Superconducting Magnets by Andrew Davies Find the.
Inner Triplet Protection Strategy LHC & HL-LHC Daniel Wollmann with Inputs from B. Auchmann, G. Ambrosio, R. Denz, P. Fessia, E. Ravaioli, F. Rodrigues.
Quench behavior of the main dipole magnets in the LHC By Gerard Willering, TE-MSC On behalf of the MP3-CCC team Acknowledgements TE-MSC, MP3, BE-OP, TE-MPE,
CSCM Test description and Risk assessment  Goal  The typical and ultimate current cycle  Test sequence for type test and regular test  Risk assessment.
HNC/D Engineering Science
SIS 100 Vacuum chamber Recooler String system Components
Considerations from machine protection and the ELQA teams
Existing Prototype Test Facility (PTF) and planned Series Test Facility Schroeder, Claus Cryo-Review Darmstadt
HL-LHC IT STRING and Series test of SC link
D1 and D2 powering and protection
Cryogenic behavior of the cryogenic system
Electrical insulation of magnet circuits in sector 7-8
Powering LHC magnets version 30/3/2007.
Quench estimations of the CBM magnet
The HL-LHC Circuits: Global View and Open Questions
Circuit-protection aspects of different preliminary magnet-design options
Powering the LHC Magnets
Hollow e- lens, Cryogenic aspects
MPE main activities planned for LS2
Functional specification for the consolidated LHC dipole diode insulation system and consolidation strategy C. Scheuerlein on behalf of the LHC dipole.
Concepts for magnet circuit powering and protection M
Update on circuit protection simulations of the HL-LHC Inner Triplet circuit Matthias Mentink, Circuit specifics + STEAM simulations: Samer Yammine, LEDET.
Comparison of magnet designs from a circuit-protection point-of-view
Dipole circuit & diode functioning
Powering from short circuit tests up to nominal
Circuits description and requirements - Closed Session-
Block 4 and Cluster D - Safety
WP3 Meeting – December the 10th 2015 H. Prin
Hilumi WP3 meeting, 1 October 2014
Cryogenic behavior of the magnet
Quench calculations of the CBM magnet
Hardware Commissioning
Electronics Topic 6: Diodes.
Other arguments to train two sectors to 7 TeV
MBHSP109 and MBHSP May 2019, Gerard Willering.
Review Bloc 4 and SM18 facilities and upgrade
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

3 issues identified in review Some data for the cryogenic load and quench test in SM18 on an 11T magnet following a trip of the trim PC . 3 issues identified in review Overcurrent in trim lead if R_crowbar is too small (not an issue since R_crowbar is foreseen at 60 mOhm) During trim trip current will pass through the diode, depositing heat (discussed in this presentation) Control of two PC’s. (not discussed in this presentation) G. Willering, 22-04-2016

Trim circuit trip in the LHC Input 6 kA in main circuit Trim crowbar 60 mOhm Diode opening voltage 5.5 V Output Energy deposited = 1.6 kJ Maximum current in diode 158 A Current through crowbar 92 A Input 6 kA in main circuit Trim crowbar 60 mOhm Diode opening voltage 2.75 V (half) Output Energy deposited = 2.7 kJ (+ 70%) Maximum current in diode 204 A (+ Current through crowbar 46 A

Trim circuit trip in SM18 – MB in series with 11T Input Connecting 130 mH 11T in series with 100 mH MB magnet. 6 kA, assuming a trip in the main PC after trip in Trim circuit Trim crowbar 60 mOhm Diode opening voltage 5.5 V Output Energy deposited = 0.7 kJ Maximum current in diode 158 A Current through crowbar 92 A Trip of main PC Main PC disconnected Only trim Main PC stable Assuming no trip of the main PC and stable regulation at 6 kA the decay will be similar as in the LHC Trim current independent of main circuit current: Trim at -250, trip -> Same current profile in trim circuit as in the LHC.

Possibilities for testing cryogenic loads in diode container 1.Simplest ??, most versatile method (for this we could use any MB magnet with diode) Place temperature probe on the diode lead close to the SC busbar Put a 1 kW heater in the diode container 2. Simple but representative way of pushing current through diode: Disconnect main converter. Same decay as in LHC. Use T-probe to validate if a quench could happen or not. No magnet protection needed. No trim PC control test possible Only with 2*5.5m assembly (130 mH) Main dipole gets close (100 mH) Cold diode -250 A crowbar 3. More complex way, but allowing test of trim PC in the Main PC circuit by connecting 2 cold magnets in series – use watercooled cable to connect them. Same decay as in LHC if main PC does not trip. T-probe will be still important to validate the measurement. Modification of PLC and protection needed.

Can the heat deposition quench the magnet? The total heating is 1.6 kJ, if spread over 5 liter of helium (volume of diode container with diode installed) the helium warms up from 1.9 to 2.2 K. With the heat spread out over the whole magnet (about 250 liter) the delta T < 10 mK. No quench. Only helium is taken into account, no heat capacity of the cold mass nor the diode heat sinks. Energy Tmax diode container Tmax magnet 1.6 kJ 2.2 K <1.91 K 3 kJ 3.1 K <1.92 K

The decay of Vf will probably be considerably faster at 1.9 K due to What do we know about diode behavior at small currents at low temperature. Forward voltage with low currents in the magnet, see CSCM tests in all sectors. Slow diode opening with some 150 A lead to very slow decay of V_f, which indicates slow heating, see examples below. Start of diode conduction Start of diode conduction MQ magnet: (higher current, same diode, smaller heat sinks) MB magnet (bit lower current) The decay of Vf will probably be considerably faster at 1.9 K due to - lower heat capacity - higher dVf/dT - double heating power (double voltage).

Conclusion No quench will occur, so to make the cryogenic load test usefull a temperature probe should be placed on the diode bus bar, close to the T-junction with the SC leads In SM18 testing current through diode after a trip in the trim can be done easily with the main converter disconnected, even with a NbTi main dipole. T-probe is usefull. Connection of two magnets on two benches in series will mainly serve the test of the control of the main PC and the trim PC.