Magnet electrical and hydraulic (dis)connections for coating

Slides:



Advertisements
Similar presentations
Brio 2000 / Brio 2000-M E-Learning Service Manual Rev. 0.0.
Advertisements

LS1 Status Report – 116 th LHCC Frédérick Bordry 4 th December 2013.
FGD-Limestone Grinding Plants General Technical Training MJ /
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Shielded Metal Arc Equipment, Setup, and Operation
Warm magnets and the remote handling system in the J-PARCν beam line E. Hirose, K. H. Tanaka, Beam Channel Group.
30/05-03/06/2007 LCWS2007 and ILC2007, DESY Hamburg Germany Vacuum System Specifications What needs to be specified in Vacuum Specification for ICL Damping.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
September 19/20, 2007 SIS 100 Magnet cooling and cryogenic distribution.
20 th SPS Upgrade Study Team meeting – 18 th November 2008 – J.Bauche, - AT/MCS/MNC 1.
1 Air Conditioning Breaker Panels and Disconnects.
ATC / ABOC Days – Session 4 – January D. Smekens AT-MCS-MNC 1 MAGNETS FOR SPS & BEAM LINES MTTR & Spare Policy for the LHC Injectors & Exp.
Bulding 245 schedule update LIU Booster Meeting Fulvio Boattini & Michel Obrecht TE-EPC / EN-CV TEEPC.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
IEFC Workshop 9 th March 2012 – Magnet activities in IEF during LS1 – J. Bauche 1 Magnet activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section.
CLEX TBM T0 Cooling system Design strategy 1 V. Soldatov, A. Vamvakas, BE-RF
SPSU – May 19, 2009 – Resources needed for SPS coating project– J. Bauche 1 Coating of the SPS Main Dipoles Vacuum Chambers: Resources Needed for Project.
Update: Puck and Gun Magnet March 1, Magnetized Gun 2 K 2 CsSb Preparation Chamber HV Chamber.
LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 1 SPS Magnet Test Campaign and Consequences for LS1 J. Bauche*, P. Catherine,
Facility to coat the SPS magnets with carbon Objective: coat at least 90% of the SPS with a carbon thin film with low secondary electron emission in order.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
AWAKE p+ beam line HWC C. Bracco, J. Schmidt Acknowledgment: MCS, EPC, MPE, SPS-OP, BI, ABP (survey),STI, EA, ACE, RP.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 24/05/2006 LHCb - Install Meeting 24/05/06 TS/CV/DC activities for LHCb: - IT, TT, OT & SPD/PS, RICH.
MVD COOLING STATUS COOLING PLANT: -UPDATE of THE HYDRAULIC SYSTEM -INTEGRATION OF THE MVD COOLING CIRCUIT PATHS INSIDE THE PANDA AREA -DEFINITION OF THE.
S A Griffiths CM42 June 2015 Electrical & Control.
New Magnet Design for FCC- ee Attilio Milanese, CERN 26 Oct presented by Frank Zimmermann.
MVD COOLING STATUS MVD COOLING PROJECT: CHOICE of COOLING FLUID,
SIS 100 Vacuum chamber Recooler String system Components
Update on the PSB Cooling and Ventilation Systems
Magnet activities in SPS during EYETS
Follow up of Soft clamps production & testing Thomas Kaltenbacher & Christine Vollinger LIU-SPS, 26/05/2016 Thomas Kaltenbacher.
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
Linac4-PSB 160 MeV connection readiness review
Performance Car Wash Systems wants to be your supplier of automatic tunnel equipment whether the requirements are small or large. We will earn your respect.
E4 HVACR Electrical Installation
ARAC/H/F Air-cooled water chillers, free-cooling chillers and heat pumps Range: kW.
TE-MSC activities in SPS during LS2
Update of MVD services and requests
LHC Hardware Commissioning Training
HFM Test Station Main Cryostat
E4 HVACR Electrical Installation
TE-MPE LS1 review Vision from EN-EL(CF)
SPS - EYETS 2016/17 Vacuum systems planning
12 October 2009 RRB Plenary R.-D. Heuer
M. Alcaide Leon, Paolo Fessia
LIU–PLI report LIU SPS meeting.
Arc magnet designs Attilio Milanese 13 Oct. 2016
Powering the LHC Magnets
SPS EN-CV Planning LS (initial draft)
SPS Planning for the EYETS Meeting 8 (07/12/2016)
Renovation of the 45-year old PS magnets
SPS activities during LS2 TE-EPC (Power Converter Group)
TE-MSC activities in SPS during YETS
The 11T cryo-assembly: summary of design and integration aspects
EYETS septa status Septa activities TE/ABT Thierry Masson
Cryostat design Mechanical design: Thermal screens: Specifications:
Subsea 100 Global Services Products Presentation
NEC Wiring Diagrams.
Measure Hose as 14”, 12.5”, 12.25”, 9” & cut it.
WP3 Meeting – December the 10th 2015 H. Prin
Filling of SAPPHIRE 25 & 42 Bar Systems (TFPP Hardware)
SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 20/02/2019.
Hardware Commissioning
Shortening the long RQF/RQD busbar segments in points 1 and 5
Presentation transcript:

Magnet electrical and hydraulic (dis)connections for coating J. Bauche, aC coating and impedance reduction meeting, 2015-12-07

SPS main magnet powering and cooling principles Main dipole and quadrupole magnets powered and water-cooled through hollow copper bus-bars Cooling circuit valves at each half-sextant (no individual valves at each magnet) Powering Principle Cooling Principle

Cross-section of bus-bar system in the SPS tunnel

Bus-bar connection details Busbar to Magnet Connection Hollow Water Cooled Copper Bar (d: 26 mm) RETURN ~11 bars INLET ~18 bars Quadrupole QF/QD Busbars Hollow Water Cooled Copper Bar (2 x d: 40.5 mm) Dipole Busbars Hollow Water Cooled Copper Bar (2 x d: 49.5 mm)

Bus-bar brazing

Power and water disconnection / reconnection process (mains) Consignation main power circuits  TE-MSC and EN-EL Switching off demineralized circuit water pumps; closing half-sextant valves; purging half-sextant water  EN-CV Cutting bus-bar jumpers with cutting clamp  TE-MSC Re-brazing new bus-bar jumpers  TE-MSC Refilling water circuits  EN-CV Déconsignation main power circuits  TE-MSC and EN-EL (Other operations not detailed…)

SPS SSS magnet powering and cooling principles Main dipole and quadrupole magnets powered with “dry” cables” and water-cooled through flexible hoses Individual valves for each water-cooled magnet

Power and water disconnection / reconnection process (SSS) Consignation of power circuits  TE-MSC and TE-EPC Closing cooling circuit valves at magnet  TE-MSC Disconnection of electrical cable lugs and of cooling flexible hoses  TE-MSC Re-connections and opening of water valves  TE-MSC Re-commissioning of the circuit (polarity check)  TE-MSC (support from BE-OP) Déconsignation of power circuits  TE-MSC and TE-EPC (Other operations not detailed…)

Spare slides

Typical half-cell

Handling and transport of main magnets  Use of the ‘Dumont’ machines: - Trailers designed for the SPS tunnels, equipped with 2 handling manipulators, - Hydraulic system, not automated - For long distances, magnets are unloaded on standard trailers in the access galleries Installation of main dipole in the SPS Transport of dipole