New DCC Status and Plans Jim Rohlf, Eric Hazen, Arno Heister,

Slides:



Advertisements
Similar presentations
José C. Da Silva OFF DETECTOR WORSHOP, April 7, 2005, Lisboa SLB and DCC commissioning for 904.
Advertisements

The LAr ROD Project and Online Activities Arno Straessner and Alain, Daniel, Annie, Manuel, Imma, Eric, Jean-Pierre,... Journée de réflexion du DPNC Centre.
CMS Week Sept 2002 HCAL Data Concentrator Status Report for RUWG and Calibration WG Eric Hazen, Jim Rohlf, Shouxiang Wu Boston University.
HCAL FIT 2002 HCAL Data Concentrator Status Report Gueorgui Antchev, Eric Hazen, Jim Rohlf, Shouxiang Wu Boston University.
Status and planning of the CMX Philippe Laurens for the MSU group Level-1 Calorimeter Trigger General Meeting, CERN May 24, 2012.
TID and TS J. William Gu Data Acquisition 1.Trigger distribution scheme 2.TID development 3.TID in test setup 4.TS development.
Tuesday September Cambridge1 GDCC “next replacement of the LDA” Franck GASTALDI.
Status and planning of the CMX Wojtek Fedorko for the MSU group TDAQ Week, CERN April , 2012.
Instrumentation DepartmentCCLRC Rutherford Appleton Laboratory28 March 2003 FED Project Plan 2003 FED Project aiming to satisfy 2 demands/timescales: Module.
John Coughlan Tracker Week October FED Status Production Status Acceptance Testing.
Andrew Peck 1 CSC OTMB Firmware Meeting February 21, 2014 ALCT/TMB/RAT Test Stand at CERN Setting up complete duplicate of the ALCT-TMB-RAT test stand.
Rutherford Appleton Laboratory September 1999Fifth Workshop on Electronics for LHC Presented by S. Quinton.
DHH Status Igor Konorov TUM, Physics Department, E18 PXD DAQ workshop Münzenberg –June 9-10, 2011.
E. Hazen - DTC1 DAQ / Trigger Card for HCAL SLHC Readout E. Hazen - Boston University.
E. Hazen -- Upgrade Meetings1 AMC13 Project Development Status E. Hazen, S.X. Wu - Boston University.
E. Hazen1 MicroTCA for HCAL and CMS Review / Status E. Hazen - Boston University for the CMS Collaboration.
E. Hazen - Detector Systems1 HCAL Initialization Cooling it Down!
E. Hazen -- ACES ACES 2011 MicroTCA in CMS E. Hazen, Boston University for the CMS collaboration.
Eric Hazen1 Ethernet Readout With: E. Kearns, J. Raaf, S.X. Wu, others... Eric Hazen Boston University.
E. Hazen -- CMS Week HCAL Back-End MicroTCA Upgrade Status E. Hazen Boston University.
E. Hazen -- Upgrade Week1 AMC13 Project Status E. Hazen - Boston University for the CMS Collaboration.
E. Hazen -- Upgrade Week1 HCAL uTCA Readout Plan E. Hazen - Boston University for the CMS HCAL Collaboration.
10/28/09E. Hazen FNAL Workshop1 HCAL DAQ / Timing / Controls Module Eric Hazen, Shouxiang Wu Boston University.
9/29/2016E. Hazen - oSLB1 HO Trigger Links ● oSLB produced (69 pieces) – First few tested (by me) -- seem OK – Production testing to be done by student.
E. Hazen1 New DCC Status and Plans Jim Rohlf, Eric Hazen, Arno Heister, Phil Lawson, Jason St John, Shouxiang Wu Boston University.
New HCAL DCC aka “DCC2” Eric Hazen, S. X. Wu, A. Heister, P. Lawson, J. Rohlf, J. St John Boston University.
New HCAL DCC Eric Hazen, S. X. Wu Boston University.
E. Hazen -- Upgrade Meetings1 AMC13 Project DAQ and TTC Integration For MicroTCA in CMS Status Report E. Hazen - Boston University for the CMS.
E. Hazen -- HCAL Upgrade Workshop1 MicroTCA Common Platform For CMS Working Group E. Hazen - Boston University for the CMS Collaboration.
E. Hazen1 Fermilab CMS Upgrade Workshop November 19-20, 2008 A summary of off-detector calorimeter TriDAS electronics issues Eric Hazen, Boston.
E. Hazen1 AMC13 Project Status E. Hazen - Boston University for the CMS Collaboration.
E. Hazen1 DCC2 Spares Situation and Failure Speculation E. Hazen - Boston University.
E. Hazen1 HCAL DAQ To Do List Here come the protons! But still lots to do... DQM Tweaks HO Trigger Links New DCC Selective readout.
HO / RPC Trigger Links Optical SLB Review E. Hazen, J. Rohlf, S.X. Wu Boston University.
E. Hazen1 New DCC Status and Software issues Eric Hazen, Phil Lawson, Shouxiang Wu, Jim Rohlf, Arno Heister, Jason StJohn Boston University.
E. Hazen - Back-End Report1 AMC13 Status Update ● Version 1 (5Gb/s links, Virtex-6 chip) ● 15 modules built, all but 3 distributed to colleagues.
DAQ / Trigger Card for HCAL SLHC Readout E. Hazen - Boston University
Some first observations
The CMS HCAL Data Concentrator: A Modular, Standards-based Design
AMC13 Project Status E. Hazen - Boston University
DAQ and TTC Integration For MicroTCA in CMS
HCAL DAQ Path Upgrades Current DCC Status New DCC Hardware Software
Status of the ECL DAQ subsystems
AMC13 T1 Rev 2 Preliminary Design Review E. Hazen Boston University
E. Hazen - Back-End Report
Current DCC Design LED Board
AMC13 Status Report AMC13 Update.
Production Firmware - status Components TOTFED - status
CCS Hardware Test and Commissioning Plan
The CMS HCAL Data Concentrator: A Modular, Standards-based Design
L1Calo upgrade discussion
TELL1 A common data acquisition board for LHCb
A New Clock Distribution/Topology Processor Module for KOTO (CDT)
HCAL Data Concentrator Production Status
The CMS HCAL Data Concentrator: A Modular, Standards-based Design
MicroTCA Common Platform For CMS Working Group
MicroTCA Common Platform For CMS Working Group
HCAL DAQ (hardware) Debugging Status
AMC13XG (XG = Ten Gigabit)
ECAL OD Electronic Workshop 7-8/04/2005
DAQ Interface for uTCA E. Hazen - Boston University
Irakli MANDJAVIDZE DAPNIA, CEA Saclay, Gif-sur-Yvette, France
8-layer PC Board, 2 Ball-Grid Array FPGA’s, 718 Components/Board
8-layer PC Board, 2 Ball-Grid Array FPGA’s, 718 Components/Board
UK ECAL Hardware Status
CPM plans: the short, the medium and the long
USCMS HCAL FERU: Front End Readout Unit
TELL1 A common data acquisition board for LHCb
FED Design and EMU-to-DAQ Test
HCAL DAQ Interface Eric Hazen Jim Rohlf Shouxiang Wu Boston University
Presentation transcript:

New DCC Status and Plans Jim Rohlf, Eric Hazen, Arno Heister, Old DCC Update New DCC Status and Plans Jim Rohlf, Eric Hazen, Arno Heister, Jason St John, Shouxiang Wu Boston University 2008-12-09 E. Hazen

Old DCC HTR/DCC communications fixed – zero errors in MonLogger A few outstanding issues Anecdotal evidence for backpressure @ 50kHz L1A rate with ZS Put on back burner until HTR ZS code settles down Un-tested features... will we every use these? Calibration triggers – Yes! Need to test Hardware re-sync – Maybe CRC calculation on flash firmware – ?? Anything else? 2008-12-09 E. Hazen

New DCC Overview Single VME slot; 15 HTR spigots, Ethernet, TTC, TTS on front Optional P3 rear transition module for selective readout Xilinx XC3S200A FPGA 32MByte DDR SDRAM XC3SD1800A 64MByte TTCrx UMD board LVDS Tx TTS TTC Buffers VME VME64x S-Link LSC DAQ Data TP Out / Readout bits in Out In optional rear transition module Ethernet (WizNet) RJ-45 2008-12-09 E. Hazen

2008-12-09 E. Hazen

Hardware Prototype Status 10 Bare PCBs here; assembled by 12/17 Initial firmware ~ ready Test Plans Test at BU test stand until ~ working (1 month?) Tests at CERN starting ~ 1 February 2008-12-09 E. Hazen

Software Goal: plug-compatible with old DCC One crate may contain both old and new DCC! How to manage this? Current hcalDCC class becomes a wrapper DCC1 and DCC2 classes represent old/new boards All current methods will exist at least as stubs Strategy Add new classes to CVS very soon so new releases will have this structure to avoid divergent code Add functionality to DCC2 class as it is developed Who will do it? Phil, Eric, Arno 2008-12-09 E. Hazen

Software Trouble Spots Firmware programming – different set of files Firmware DB will need some updating Old: Log1/2/3 plus Xilinx New: LRB, Xilinx, VME Benefits: Everything is reprogrammable, much faster Jeremy says this is easy to support MonLogger Many counters expand from 8 to 32 bits Some totally new items Some old items disappear How to make this compatible? Initially, just pretend it's an old DCC and accept some trouble Expert View Same issues as monlogger 2008-12-09 E. Hazen

Strategic Decision Plan A Deploy New DCC as fully and quickly as possible; make one-way changes to fix trouble spots Plan B Code full support for a mixed system Most flexible, but requires extra software effort We don't have to decide right now, as we need at least basic support for a mixed system. This requires management input (discuss) 2008-12-09 E. Hazen