T DAY in The Vale of Glamorgan By David Powell Energy Manager
WHY? Unreliable deliveries of LPG Good return on investment (and ethical) Save 5 Tonnes per annum emissions of CO2
Why Wind?
What Next? Take the plunge – apply for planning permission (£288) Sort out export agreements/installation of export meter (£75) Apply to the Low Carbon Buildings Programme – for grant (£5,000) Deposit to installer (£4,000) Ground works Installation Claim grant
T Day 13th Dec 2006
Performance so far Since Dec 13th 2006 – 3800 kWh (as of 27th March) = £380 Average daily generation – 37 kWh Exporting 10.16 p/kWh ROCs from April 1st 2007 - £33.24 per 1000 kWh
Useful Contacts EDF – Mark Thompson Mark.Thompson@edfenergy.com NPOWER - Sue Warman Sue.Warman@npower.com Western Power (Export Meter) Ian Dobson - 0117 933 2364