Instrument Preliminary Design Review (I-PDR) September 28th, 2005

Slides:



Advertisements
Similar presentations
NASA’s Goddard Space Flight Center LRO SRR Project Management.
Advertisements

GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
GLAST LAT ProjectDOE Rebaseline Review, February 13, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Chief Engineer.
GLAST LAT Project Engineering Meeting – ISOC Peer Review 1 Gamma-ray Large Area Space Telescope GLAST Large Area Telescope ISOC Peer Review ISOC Detail.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
STEREO IMPACT Preliminary Design Review 2001-September 11,12 David Curtis1 IMPACT Project Overview.
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
LSU 07/07/2004Communication1 Communication & Documentation Project Management Unit – Lecture 8.
1 Engineering the James Webb Space Telescope Paul Geithner JWST Deputy Project Manager - Technical March 26, 2011.
TEMPO Mission Project July 23, 2013 Project Manager: Alan Little.
FIELDS iCDR Solar Probe Plus FIELDS Instrument CDR Introduction 1Peter Harvey.
C osmic R Ay T elescope for the E ffects of R adiation CRaTER Pre-Ship Review (I-PSR) R. Foster January 3-4, 2008.
1 PFP MSR, 11/17/2009 Particles and Fields Package Monthly Status Review (MSR) November 17, 2009 Dave Curtis, PFP PM.
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
( ELR) - 1 STEREO - Solar Terrestrial Relations Observatory Mission STEREO SWG STEREO OBSERVATORY Status Edward Reynolds APL STEREO Project Manager.
NASA’s Goddard Space Flight Center Systems Engineering Mike Pryzby Swales Aerospace August 16-17, 2005.
THEMIS SRR Requirement Overview - 1 UCB, 07/08/2003 REQUIREMENT DEVELOPMENT OVERVIEW Ellen R. Taylor Mission Systems Engineer Space Science Laboratory.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
NMP EO-1 TECHNOLOGY WORKSHOP Section 2 Meeting Objectives.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
Plan ENTERPRISE Assess Handle Monitor RISK MANAGEMENT Communicate David Hall, SRS Technologies Minimizing (Some Of) The Subjectivity in Risk Assessments.
[PROJECT] PROJECT KICKOFF PRESENTATION MONTH DAY, YEAR.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Overview and Status Keith Goetz University of Minnesota.
TOF Preliminary Design and Safety Review Project Management Controls R. L. Brown.
SOLUTION What kind of plan do we need? How will we know if the work is on track to be done? How quickly can we get this done? How long will this work take.
24b - 1 NASA’s Goddard Space Flight Center LRO Safety Dave Bogart Code 302 August 16-17, 2005.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
Evaluate Phase Pertemuan Matakuliah: A0774/Information Technology Capital Budgeting Tahun: 2009.
GLAST LAT ProjectI&T&C Pre PDR Presentation – Oct 2, 2001 B. Grist1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
CENF CIVIL ENGINEERING : - DESIGN TENDER AND ESTIMATED COSTS John Osborne GS/SE 19 July 2013.
SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair.
Keck Next Generation AO Next Generation Adaptive Optics Meeting #2 Caltech November 14, 2006 P. Wizinowich for NGAO Executive Committee.
Cost Estimating. –Process of collecting, analyzing and summarizing data –Prepare educated projection of anticipated cost of project –Prepared by PM or.
23-Nov-1999STScI Projects Monthly Status Review1 of 8 SpaceTelescopeScienceInstitute COS Status Report for period December, 1998 to November, 1999 Tony.
C osmic R Ay T elescope for the E ffects of R adiation June 27, 2005Larry Kepko - Data ProcessingPage 1 CRaTER Characterization Data Products & Production.
C osmic R Ay T elescope for the E ffects of R adiation CRaTER Pre-Environmental Review (I-PER) Spacecraft I&T Mike Golightly September 10-11, 2008.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct 2, 2001 Darren Marsh1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
SwCDR (Peer) Review 1 UCB MAVEN Particles and Fields Flight Software Critical Design Review Peter R. Harvey.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW CDR /30-10/1 9 EFW Overview and Status Keith Goetz University of Minnesota.
PROJECT CYCLE MANAGEMENT Reporting. Management Management Unit Establish policy and strategy Steer project direction Minimize risks & fill gaps Coordinate.
SPF MAG Quarterly Report – Feb 2015
I&T&C Organization Chart
GLAST Large Area Telescope:
ILC PROJECT ENGINEERING DESIGN REPORT CFS Europe – KICK OFF MEETING
0.0 Instrument Suite Name Presenter’s name
Lunar Reconnaissance Orbiter CRaTER Critical Design Review
Enterprise Content Management Owners Representative Contract Approval
CRaTER Pre-Environmental Review (I-PER) Programmatics Rick Foster
Peer Review Agenda (Suggested).
CRaTER Pre-Environmental Review (I-PER) Completed Verification Results Bob Goeke September 10-11, 2008.
Integration, Test, and Calibration
GLAST Large Area Telescope:
Cosmic Ray Telescope for the Effects of Radiation (CRaTER)
NASA Independent Reviews -Lessons Learned-
BRIAN KLATT MISSION ASSURANCE MANAGER
Systems Engineering Management
Systems Engineering Bob Goeke.
Lockheed Martin Canada’s SMB Mentoring Program
CRaTER Pre-Environmental Review (I-PER) Spacecraft I&T Mike Golightly
Integration and Test Organization Chart
Click to add title Planning for LSST Verification George Angeli LSST All Hands Meeting Tucson August 15, 2016.
Project Management Process Groups
CRaTER Pre-Environmental Review (I-PER) Completed Verification Results Bob Goeke September 10-11, 2007.
Instrument Preliminary Design Review (I-PDR) June 27th, 2005
Instrument PDR Summary of Objectives
Helping Active Missions Convert to PDS4
GLAST Large Area Telescope
CONTOUR NGIMS Electronics Test History
Introduction and Overview
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

Instrument Preliminary Design Review (I-PDR) September 28th, 2005 CRaTER Project Instrument Preliminary Design Review (I-PDR) September 28th, 2005

CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu) CRaTER Team CRaTER is a multi-Institutional Project lead by Harlan Spence of B.U. Aerospace Corporation Air Force Research Laboratory Boston University Massachusetts Institute of Technology National Oceanographic and Atmospheric Administration University of Tennessee Science Mission involves all of the Institutions Flight Hardware Design, Fabrication, Test & Calibration is being done by three of the Institutions Aerospace Corp B.U. MIT Detailed roles and responsibilities within the hardware team have been defined and documented. Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)

CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu) Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)

CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu) Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)

CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu) Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)

General Organizational Roles in the Project Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)

CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu) What are we building? Flight Model CRaTER Instrument (Deliverable to NASA) Fully Qualified and Calibrated Flight Spare Instrument The incremental costs associated with putting spare components together is minimal CRaTER Project has only budgeted for a few spare detectors. Yield may be a factor The science team will utilize the spare for instrument characterization at different particle accelerators, both pre and post launch to help develop SOC analysis tools. Using the spare reduces risk to the flight unit. Engineering Model Instrument Fairly high fidelity model Not Flyable Mass/CG Simulator Command & Data Handling Simulator It may be possible that we will use the EM for this function, but still under review. M&E GSE for internal CRaTER project use Will be used up thru post shipment testing at NASA-GSFC Various jigs and fixtures for instrument testing and calibration Shipping containers for instrument transportation Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)

CRaTER Project Schedule The CRaTER Project Schedule tracks the NASA LRO Top Level Schedule LRO schedule being used by CRaTER currently at Rev 0.7 The CRaTER Project Schedule Holy Grail A fully qualified & calibrated flight unit to NASA-GSFC by Oct 2007 Even with the some problems getting the project started, the schedule prognosis is plausible. After I-PDR, the next technical milestone will be the submittal of the of the Engineering Model detector technical specification to Micron Semiconductor for quotation and subsequent procurement. Oct 2005 Near I-PDR, the next programmatic milestones will be the issuance of a no cost extension to the Phase ABCbridge contract and then completion of the Phase CDE contract (extension) Current estimation for the completion of the Phase CDE contract extension signoff is before the end of November 2005 Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)

CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu) Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)

CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu) Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)

CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu) Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)

CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu) Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)

CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu) Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)

CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu) Risk Management CRaTER Risk Management methodology detailed in CRaTER plan doc# 32-01202 Classification of risk modeled on NASA methodology Likelihood and impact assessment. At I-PDR, there is one green level identified risk. The identified risk is the possibility of receiving the flight detectors and finding or developing problems with them during flight instrument I&T These detectors are “made to order” and typically have a 6 month lead time. 2 detectors have been beam tested already, two more on order 6 detectors will have been test in the EM model prior to I-CDR CRaTER Plans to build a flight and flight spare instrument High   Significant Low 1 Negligible Likilihood Impact Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)

CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu) Sept 28, 2005 CRaTER Project Overview ... Rick Foster (rickf@space.mit.edu)