XRN4361 – UK Link Release 2 Data Migration Plan for XRN /03/18

Slides:



Advertisements
Similar presentations
1 Project Smart Metering Portfolio Foundation & DCC Day 1 Updates April 2013.
Advertisements

1 Project Smart Metering Portfolio Foundation Updates June 2013.
UK Link Programme Dashboard Report Change Overview Board: 13/05/2014 Critical HLD activities complete enabling entry into Detailed Design Detailed Design.
Generic & Enduring Functionality to Allow Xoserve to Confirm a Supply Point into a Shipper’s Portfolio UK Link Committee – April 2013.
xrn4361 UK Link Future Release 2
XRN4361 – UK Link Release 2 - Delivery
UKL Future Release 2 Cutover/Implementation
Change Assurance Dashboard
Background - Tolerance Rules
Overall Project RAG Status
Overall Project RAG Status
DSC Change Committee Summary – 12th December
Overall Project RAG Status:
XRN4770 – NDM Sample Data – Modification 0654 delivery – Amended file format ChMC – 9th January 2019.
Change Management Committee – June 2019 Update
Release 3 Update December 2018.
DSC ChMC CSS update 7th November 2018
DSC Change Committee Summary – 7th November
Overall Project RAG Status
Change Management Committee – June 2019 Update
2019 Release Planning Options inc Modification 0621 / GB Charging Project DSC Change Management Committee update July 2018.
Release 3 Update November 2018.
XRN4361 – UK Link Release 2 - Delivery
DSC Change Committee Summary – 12th September
DSC Change Committee Summary – 11th July
Overall Project RAG Status
DSC Change Committee Summary – 10th October
DSC Change Committee Summary – 9th May
XRN4361 – UK Link Release 2 - Delivery
Change Proposals Capture to Delivery
Overall Project RAG Status:
Release 3 Update 13th February 2019.
Release 2 Scope Business Benefit Review
DSC Change Committee Summary – 9th January ‘19
June 2019 Release Scope DSC Change Management Committee
Overall Project RAG Status:
DSC Change Committee Summary – 13th March ‘19
Release 3 Scope & Proposed Plan
Transporter Initiated SPA Confirmations on behalf of User Potential Impact Discussion with UK Link Committee.
XRN4361 – UK Link Release 2 Project Status Update
DSC Change Committee Summary – 13th February ‘19
XRN4249 – Part B Data Migration Plan
Release 3 scope update – cont’d
UK Link Future Release 3: Track 1 Implementation Approach for Approval at ChMC 2nd October 2018.
Overall Project RAG Status:
Overall Project RAG Status:
Overall Project RAG Status
XRN June 19 Release - Status Update
Change Management Committee – November 2019 Release Update
XRN4361 – UK Link Release 2 - Delivery
Release 2 Baselined Customer Training Requirements
MOD Proposal 0224 Facilitating the use of AMR in the Daily Metered Elective Regime Distribution Workstream Update Following Completion of Analysis 23rd.
XRN November 2019 Release - Status Update
XRN Nov 19 Release - Status Update
UK Link Future Release 3: Track 1 Implementation Approach for Approval at ChMC 2nd October 2018.
XRN June 19 Release - Status Update
High Level System Solution Impact Assessment
High Level System Solution Impact Assessment
High Level System Solution Impact Assessment
January 2018 ChMC update 5 new change proposals were approved
DSC ChMC Switching Programme Update 10th July 2019
XRN Nov 19 Release - Status Update
UK Link Timeline June-19 Sept-19 (EUC) Nov-19
DSG Governance Group Recommendations.
XRN June 19 Release - Status Update
XRN June 19 Release - Status Update
XRN Nov 19 Release - Status Update
RAASP DSC Change Management Committee update
DSC Change Committee Update
XRN Enabling large scale utilisation of Class 3 – MOD0700
Presentation transcript:

XRN4361 – UK Link Release 2 Data Migration Plan for XRN4249 28/03/18

Introduction/Problem Statement Change XRN4249 is part of the scope of changes planned to be implemented as part of UK Link Release 2 on the 29th June 2018. Following analysis of this change, discussion was held with Customers at both ChMC and DSG. Concerns were raised around the migration of the PAF updates from when the process was suspended in April 2017. These concerns relate to the volume of updates required over the period April 17 through to June 18 that could have a downstream impact to Customer systems and business processes. To minimise the impact of loading all retrospective PAF updates from April 2017, Xoserve are recommending a staggered approach to migrate the data over a number of weekends. This would have checkpoints built into the plan to review the process and agree the volume of updates to be loaded on the next planned date. This approach is expected to reduce the impacts to Customer systems and business processes.

Data Migration Plan No Activity Start Date End Date 1 Code Deployment as part of R2 Cutover/Implementation 30/06/2018 01/07/2018 2 Initial 10K Load 07/07/2018 3 NAC File / Portfolio Files / Daily Delta on the back of the initial 10K address update 08/07/2018 4 Data Load to SAP BW 09/07/2018 5 Agreement with Shippers to load safe volume (100k) records into SAP ISU (BW?) 13/07/2018 Load the safe volume (100k) records 14/07/2018 6 NAC File / Portfolio Files / Daily Delta on the back of the initial safe volume (100K) address update 15/07/2018 7 Daily Load to SAP BW 16/07/2018 8 Agreement with Shippers to load the next set of safe volume records (100k) into SA 20/07/2018 9 Load the 2nd set of safe volume (100K) records into SAP ISU 21/07/2018 10 NAC File / Portfolio Files / Daily Delta on the back of the 2nd set of safe volume (100K) address update 22/07/2018 11 Agreement with Shippers to load the remaining updates (approx. 40K) 23/07/2018 27/07/2018 12 GB places the first Regular PAF file received 28/07/2018 13 Load the remaining updates (approx. 40K) into SAP ISU 14 NAC File / Portfolio File / Daily Delta on the back of the remaining (approx. 40K) address updates 29/07/2018 15 30/07/2018 16 PO Team to pull the first regular file from GB Mailing shared area 01/08/2018 17 First regular file load into SAP ISU (and SAP BW) - Proposed 1st production BAU run 05/08/2018 18 NAC File / Daily Delta on the back of the first regular PAF file 06/08/2018

Next Steps Present options to Customers at the Delivery Sub Group on 09th April Agree if proposed approach is acceptable to Customers Split XRN4249 into 2 Change Packs, to agree: Implementation of the SAP ISU solution to reinstate the GB Mailing Update file process Agreement of the proposed Data Migration Plan to apply updates from April 17 to June 18 Update the DSC ChMC Implementation Plan to reflect XRN4249 code implementation and Data Migration Plan Review and approve proposed Data Migration plan with ChMC on 11th April