Budget Budget Contingency/ Cost Risks Descope Options

Slides:



Advertisements
Similar presentations
SALT RSS-NIR MID-TERM REVIEW MAY 20 & 21, 2009 ANALYTIC OPTICS KENNETH NORDSIECK UNIVERSITY OF WISCONSIN.
Advertisements

NGAO Instrumentation Overview September 2008 Updated Sean Adkins.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
Systems Engineering Management
WMKO Next Generation Adaptive Optics: Build to Cost Concept Review Peter Wizinowich et al. December 2, 2008 DRAFT.
NGAO Instrumentation Preliminary Design Phase Planning September 2008 Sean Adkins.
Technical Performance Measures Module Space Systems Engineering, version 1.0 SOURCE INFORMATION: The material contained in this lecture was developed.
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
Oct 17, 2001SALT PFIS PDR - Structure1 Structure Interface/ constraints Loads Structure design rationale Truss Weight and CG Finite Element Analysis/ Image.
Oct 22, 2007SSWG #18 UKZN1 Robert Stobie Prime Focus Imaging Spectrograph Status Optics repair Schedule Status of other fix and improvement projects Budget.
The Michigan/Magellan Fiber System (M2FS): An MRI Instrument Development Proposal to NSF.
Nov 6, 2005SSWG1 Robert Stobie Prime Focus Imaging Spectrograph Status Reassembly and retesting in Cape Town Estimated CTC $343,000 (7.3%) over PDR cap.
Common PDR Problems ACES Presentation T. Gregory Guzik March 6, 2003.
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
STARLight PDR 3 Oct ‘01 F.1.1 Rashid STARLight STARLight Mechanical Tahir Rashid STARLight Mechanical Engineer (734)
Oct 17, 2001SALT PFIS Preliminary Design Review Optical Integration and Test Plan 1 Southern African Large Telescope Prime Focus Imaging Spectrograph Optical.
EddiCam: The Eddington Photometric Camera EddiCam Definition Phase Kick-Off Meeting J. Miguel Mas-Hesse Vienna, 17th Sept., 2001.
GMTNIRS (Giant Magellan Telescope Near-IR Spectrograph) Survey Science Group Workshop 3 조 김상혁 김재영 최나현
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Multiplexed High Res Spectroscopy at Keck – J. Cohen (PI), H. Epps (Optical Design), M. Rich (Project Scientist) Keck instruments for optical spectroscopy.
Oct 17, 2001SALT PFIS Preliminary Design Review1 PFIS/ IMPALAS Issues Outside Reviewer's Comments Post-PDR tasks Valuation Issues.
Pre-Project Components
Oct 30, 2003PFIS - Student Wkshop1 The Prime Focus Imaging Spectrograph – Old Challenges and New Ones K. Nordsieck, Principal Investigator Jeff Percival,
Advanced Virgo Optical Configuration ILIAS-GW, Tübingen Andreas Freise - Conceptual Design -
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
The Prime Focus Imaging Spectrograph Design and Capabilities
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
Oct 26, 2007SALT Workshop UKZN1 Robert Stobie Prime Focus Imaging Spectrograph Science Rationale Modes –Fabry-Perot Spectral Imaging –Grating Spectroscopy;
P.NapierEVLA Advisory Comm, 14 Dec 2004 Project Overview Peter Napier, EVLA Project Manager Status 2003 Committee Response.
Oct 17, 2001SALT PFIS Preliminary Design Review1 Southern African Large Telescope Prime Focus Imaging Spectrograph Mechanical Mechanism Design Michael.
Oct 24, 2006SSWG1 Robert Stobie Prime Focus Imaging Spectrograph Status On-telescope throughput analysis Ghost analysis Repair plan Status of other current.
Mark McKinnon NSF Mid-Project Review May 11-12, Baseline Project Definition Mark McKinnon Project Manager.
Solar Probe Plus Fluxgate Magnetometer QSR – Oct SPF MAG Quarterly Report – Oct 2014 The MAG EM1 (EQM) (board and frame at right) was successfully.
Apr 29, 2003SSWG1 Prime Focus Imaging Spectrograph Status Passed CDR- moving into fabrication phase Mechanism design complete: fabrication drawing packages.
H.E.S.S. - MAGIC – CTA meeting Technical aspects of current & future instrumentation Telescope structures Camera designs Photon detectors Mirrors.
Oct 17, 2001SALT PFIS PDR - Optics1 Optics Refractive Optics - Design rationale Performance Slitmasks Gratings Polarimetric Optics Risks and Concerns Kenneth.
Oct 10, 2002SSWG1 Prime Focus Imaging Spectrograph Status Engineering Status Optics Mechanical Control System Management Budget Schedule.
Oct 17, 2001SALT PFIS Preliminary Design Review1 Operation Concepts Definition Document (OCDD) Chip Kobulnicky University of Wisconsin.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Apr 29, 2003SSWG - CDR Comments1 PFIS Critical Design Review Comments Detailed response available in document SALT- 3100BP0011 (PFIS web site) Responses.
Oct 17, 2001SALT PFIS Preliminary Design Review Management, Schedule, & Budget 1 Southern African Large Telescope Prime Focus Imaging Spectrograph Management,
AST3-NIR camera for the AST3-3 telescope for the Kunlun Infrared Sky Survey (KISS) Management and planning Julia Tims, Jon Lawrence 20 August 2015.
The Prime Focus Imaging Spectrograph for the Southern African Large Telescope: Operational Modes Chip Kobulnicky – Instrument Scientist, University of.
WP 12.3 Moderator & Reflector Systems D. Lyngh, M. Kickulies, J. Ringnér, J. Jurns, M. Andersson, M. Pucilowski, T. Hedlund, A. Olsson TAC11 Lund, 1 st.
Sept 16, 2005Ast 920 Meeting 21 Astronomy 920 Commissioning of the Prime Focus Imaging Spectrograph Meeting 2 Intro; VPH Grating Spectroscopy Ken Nordsieck.
Accelerator Readiness Review October 31, 2006
Prime Focus Imaging Spectrograph Status
Astronomy 920 Commissioning of the Prime Focus Imaging Spectrograph
Prime Focus Imaging Spectrograph Status
Presented To: 3rd Annual CMMI Technology Conference and User Group
Cost estimation and budgeting
COSMOS Status David Sprayberry, Sean Points & Jay Elias
KOSMOS Design Considerations
The Features of a Product or System
SmartMeterTM Steering Committee Update – September 2012
Management Breakout: MREFC Budget Summary Victor L
Budget, Schedule, Contingency
Overview Instrument Role Science Niches Consortium science
Lockheed Martin Canada’s SMB Mentoring Program
Polarimetry: Waveplate Modulation; Calibration
Click to add title Planning for LSST Verification George Angeli LSST All Hands Meeting Tucson August 15, 2016.
Control System Summary of Changes Since PDR
Mark McKinnon EVLA Project Manager
LGS Project Meeting December 21, 2006 Agenda SWIFT update - A. Bouchez
Meeting 11 Polarimetry: Beamsplitter; data formats Ken Nordsieck
SmartMeterTM Steering Committee Update – July 2012
Chapter # 4 Development and Quality Plans
Presented by (Abdisamad Abdullahi Abdulle)
SmartMeterTM Steering Committee Update – November 2012
PFIS Commissioning - SSII
Presentation transcript:

Budget Budget Contingency/ Cost Risks Descope Options Kenneth Nordsieck University of Wisconsin Budget Contingency/ Cost Risks Descope Options Oct 17, 2001 SALT PFIS PDR Budget/ Summary

SALT PFIS PDR Budget/ Summary Bottom Line Base Dollars 3,645,947 3,942,697 2,426,501 734,661 484,786 2,351,162 810,000 Oct 17, 2001 SALT PFIS PDR Budget/ Summary

Comparison to Concept Proposal Increase is in UW (contractor) budget Unbudgeted items: slitmask factory; structure and mechanisms; travel Additional 2.5 manyrs: mechanical and software Base Dollars Oct 17, 2001 SALT PFIS PDR Budget/ Summary

SALT PFIS PDR Budget/ Summary Contingency Contingency not placed on Concept Proposal ROM (no basis) PDR budget contingency 15% on all purchased items, except CCD's and etalons (firm quotes) 3 months manpower in CDR phase and in Fabrication Phase. Would be applied by hiring help, if schedule is firm, or by stretching schedule, if it is not Suggest valuation at the baseline value, with increases within the contingency budget if necessary, approved by Project Scientist Possible cost savings transferred to contingency (eg CCD) Oct 17, 2001 SALT PFIS PDR Budget/ Summary

SALT PFIS PDR Budget/ Summary Descope Options Base Dollars Design Phase Beam size 150 mm -> 116 mm etalons -$21K optics -$25K - $75K redesign +$60K (6 weeks) Net +$14K - -$36: Save very little, if anything, with significant loss of resolution Field of View at camera (3 -> 2 chips) Chips -$70K (note: need to do this immediately!) Optics -$25K - -$50K redesign +$40K (4 weeks) Net -$55K to -$80K: Again, Save very little, with significant loss of resolution elements Oct 17, 2001 SALT PFIS PDR Budget/ Summary

SALT PFIS PDR Budget/ Summary Descope Options - Cont Base Dollars Fabrication Phase third etalon -$~120K quarterwave plate -$71K slitmask factory -$106K Total -$297K These purchases will be delayed as long as possible in case of contingency overrun. Could be used to replace contingency: "descope as you go" Commissioning Phase Fewer commissioned modes Transfer some modes to project Oct 17, 2001 SALT PFIS PDR Budget/ Summary

Summary Status Risk reassessment Kenneth Nordsieck University of Wisconsin Status Risk reassessment Oct 17, 2001 SALT PFIS PDR Budget/ Summary

SALT PFIS PDR Budget/ Summary Status PFIS on track to deliver SALT first light instrument competitive or superior to those on other large telescopes low - medium resolution multiobject spectroscopy double-etalon Fabry-Perot spectroscopy high-speed spectroscopy spectropolarimetry Oct 17, 2001 SALT PFIS PDR Budget/ Summary

SALT PFIS PDR Budget/ Summary To do.. Open ends to be resolved in next 6 weeks (scheduled system conceptual design final iteration) slitviewer proposal waveplate configuration resolution of mass property budget structure iteration to remove flexure trouble spots definition of interfaces Oct 17, 2001 SALT PFIS PDR Budget/ Summary

SALT PFIS PDR Budget/ Summary Risk Reassessment Optics complexity (technical, cost, schedule) Refractive Optics Low to medium Polarimetric Optics Medium. Cost cap NaCl elements (technical) Manufacturability: Low Structure (technical, cost, schedule) flexure: Low to medium weight: Low? articulation: Low mechanisms: Low to medium Oct 17, 2001 SALT PFIS PDR Budget/ Summary

SALT PFIS PDR Budget/ Summary Oct 17, 2001 SALT PFIS PDR Budget/ Summary