A Stitch in Time Saves Nine

Slides:



Advertisements
Similar presentations
N O T E “CLICK” TO CONTINUE… If the slide show is not launched, click on View  Slide Show in the menu bar at the top of the Power Point window. When the.
Advertisements

TITLE OF PROJECT PROPOSAL NUMBER Principal Investigator PI’s Organization ESTCP Selection Meeting DATE.
Monitoring and Information Systems
TITLE OF PROJECT PROPOSAL NUMBER Principal Investigator PI’s Organization ESTCP Selection Meeting DATE.
1 Schedule Risk Assessment (SRA) Overview July 2013 NAVY CEVM.
Project Change Management
Monitoring and Control Earned Value Management (EVM)
Project Cost Management Sections of this presentation were adapted from A Guide to the Project Management Body of Knowledge 4 th Edition, Project Management.
Chapter 10: Monitoring and Controlling Change
OPMA 5364 Project Management Part 6 Project Control
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
This work is licensed under a Creative Commons Attribution 3.0 Unported LicenseCreative Commons Attribution 3.0 Unported License (CC-BY). Project Management.
1 NASA OSMA SAS02 Software Reliability Modeling: Traditional and Non-Parametric Dolores R. Wallace Victor Laing SRS Information Services Software Assurance.
Project Management Methodology Project monitoring and control.
PPMT CE-408T Engr. Faisal ur Rehman CED N-W.F.P UET P.
Software Project Management Lecture # 7. What are we studying today? Chapter 24 - Project Scheduling  Effort distribution  Defining task set for the.
Project Cost Management
Software Project Management (SPM)
9-1 Project Management from Simple to Complex. 9-2 This work is licensed under the Creative Commons Attribution-Noncommercial-Share Alike 3.0 Unported.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
Presented by: Meysam rahimi
Agenda Interthink – 2003 Organizational Project Management Baseline Study –Industry Profile –Country Profile –Organization Size –Data On Schedule –Data.
Chapter 3: Software Project Management Metrics
UU Master Class Earned Value 17 July Earned Value Contents What is Earned Value / Earned Value Analysis Why and where is it used A brief history.
1 Software Quality Engineering. 2 Quality Management Models –Tools for helping to monitor and manage the quality of software when it is under development.
EARNED VALUE MANAGEMENT (EVM) TUTORIALS
Evaluating EVM January 13, EVM Issues and Opportunities ▪ EVM Basics ▪ EVM Issues ▪ EVM ETC and EAC Calculations ▪ EVM Cost and Schedule Value Calculations.
Report Performance Monitor & Control Risk Administer Procurement MONITORING & CONTROLLING PROCESS.
Where Module 04 : Knowing Where the Project Is 1.
Understanding Earned Value Management & Analysis Abba Consulting Federal Acquisition Conference & Exposition Washington, DC June 19-20, 2007 Wayne Abba.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Project Management 1 Project Control. Project Management 2 Topics Project Control Status Reporting Earned Value Analysis.
EAC Evaluation Methods: Do They Work On Post-A12 Contracts?
Principal Investigator ESTCP Selection Meeting
Project Cost Management
Camera PDR/CD1 Planning 19 September 2008
Project Cost Management
Monitoring and Information Systems
TOPIC-8B- PROJECT COST CONTROL
Budget Planning.
Project Management (x470)
CHAPTER:7 Project Cost Management
IEVMC Lesson 8 FY14 Analysis Case Study Performance Management Analysis Tools Student guide page 8-5.
Project Communication, Tracking, and Reporting
Overview May 24, 2017.
Principal Investigator ESTCP Selection Meeting
EVM 202—Lesson 7 Tools Analysis Case Study
September 2016 EVM 202—Lesson 4 Integrated Baseline Review Process (Part 4: Baseline Maintenance)
September 2016 EVM 202—Lesson 8 Integrated Product Team (IPT) Analysis and Performance Case.
Dave Bachman DAU / CDSC September 9, 2004
Integrated Program Management Case Study Briefing
EVM 202—Lesson 7 Tools Analysis Case Study
Project Cost Management
Schedule Risk Assessment (SRA) Overview
فرآيند كنترل پروژه.
MGT 605: CH-13 Progress and Performance Measurement and Evaluation
Schedule Risk Assessment (SRA) Overview
Schedule Risk Assessment (SRA) Overview
Project Cost Management
Linac Coherent Light Source (LCLS)
Principal Investigator ESTCP Selection Meeting
Schedule Risk Assessment (SRA) Overview
CAD DESK PRIMAVERA PRESENTATION.
M. Kezunovic (P.I.) S. S. Luo D. Ristanovic Texas A&M University
Managing Project Work, Scope, Schedules, and Cost
Principal Investigator ESTCP Selection Meeting
Where We Are Now. Where We Are Now Structure of a Project Monitoring Information System Creating a project monitoring system involves determining:
Presentation transcript:

A Stitch in Time Saves Nine Program diagnostics using the Rayleigh model for executive decision-makers (generic brief) Dan Davis, Gary Christle, Wayne Abba 18 September 2018

Research Task: Questions to Be Addressed How can an executive effectively use questionable EVM data for management decisions? Can new tools be developed or “old” tools modified to give earlier warning of impending contract execution problems? 18 September 2018

Briefing Agenda Summarize Rayleigh model Summarize results of validation Demonstrate tool One module for “traditional” analysis One module for assessment of an original plan before actual cost data has been collected Potential Impact of study Potential for future work Recommendations 18 September 2018

The Rayleigh Model Cumulative cost as a function of time (in millions of $) Shape parameter. When will peak spending rate occur? Duration time (in years). What is the current duration of the program? Scale factor. How much will the program cost? Proportion of work completed at time t. 18 September 2018

An Example of a Rayleigh Schedule The parameter d tells us the height of the curve. What is the upper bound on cumulative cost? The parameter α tells us the shape of the curve. When does the peak spending rate occur? This curve inflects when the rate curve below reaches a maximum. 18 September 2018

Rayleigh Model Advantages Rayleigh is a plausible model of cumulative cost accrual over the life of a contract The model is based on current (then-year) dollars The model depends only on standard currently available EVM data (no new reports) The model only requires 3 actual cost submissions and a budget 18 September 2018

Rayleigh Model Advantages The model does not depend on the reliability of Earned Value (BCWP) submissions The model predicts both EAC and completion date The model predicts the path of actuals to completion date The model is Excel-based using standard Solver add-in 18 September 2018

Validation of the Rayleigh model Compared accuracy of predictions considering cost at completion and completion time Methods compared Rayleigh estimate Contractor estimate PM Estimate 18 September 2018

Validation (cont) Methods compared (cont) EAC1 (BAC/CPI plus max of contractor and PM time estimate) EAC 2 (Actuals+(BAC-EV)/(.8CPI+.2SPI) plus max of contractor and PM time estimate) EAC 3 (Actuals +(BAC-EV)/(CPI X SPI) plus max of contractor and PM time estimate) Note: EAC1, EAC2, and EAC3 methods do not produce an independent estimate of duration time 18 September 2018

Validation (cont) Selected programs for regression analyses Selected only R&D programs Selected complete programs Eliminated programs less than 90% complete to get valid baselines Eliminated programs with over 2 years between work start and first submission to evaluate early warning utility 18 September 2018

Validation (cont) Began with entire CAS database Selected 74 programs Consisting of 115 contracts Earliest start date 1/1/1970 Latest start date 8/1/2002 All services included 18 September 2018

Rayleigh validation results 18 September 2018

How much better were Rayleigh predictions? (EAC) All estimates underestimate final cost over 78% of the time. When they underestimate cost: Rayleigh underestimates final cost on average by 30% The contractor underestimates on average by 35% The PM underestimates on average by 37% The EAC1 method underestimates on average by 34% The EAC2 method underestimates on average by 34% The EAC3 method underestimates on average by 32% 18 September 2018

How much better were Rayleigh predictions? (time) All estimates underestimate final contract duration over 73% of the time. When they underestimate duration : Rayleigh underestimates duration on average by 24% The contractor underestimates on average by 35% The PM underestimates on average by 55% 18 September 2018

Conclusions from database validation Rayleigh yields best estimate of final cost Rayleigh yields best estimate of time duration 18 September 2018

Conclusions from database validation (cont) Rayleigh is still short of final cost on average by 30% A basic assumption of all EAC techniques is that we know full scope at the time of prediction and we fit the sparse data with a single Rayleigh curve Earlier CNA study (“Program Cost Growth: The Navy’s Experience 1983-2004”) Total cost growth is level from 1978-2004 Within the total, the “overrun" component is declining and the “changes” component is increasing We think the bulk of the 30% shortfall is attributable to contract changes 18 September 2018

Executive Cost and Schedule Assessment (XCaSA) tool Executive Plan Assessment Module (XPAM) Allows executive to assess plan realism before any actuals are submitted Executive Contract Assessment Module (XCAM) Allows executive to assess contract performance after at least 3 submissions of actuals 18 September 2018

XCaSA (cont) XCAM (cont) Incorporates Rayleigh estimates Displays “traditional” analysis for comparison Incorporates relevant DCMA tripwires 18 September 2018

New metrics (XCAM) Cost Overrun Vulnerability Index: Schedule Slip Vulnerability Index: 18 September 2018

New features (XPAM) Plan Validity Index “What if” drills 18 September 2018

XCaSA advantages User friendly Interactive Provides useful information early in life of contract Uses built-in Solver add-in with widely used Excel spreadsheet software Provides business insights 18 September 2018

Dashboard view of XCAM 18 September 2018

Dashboard view of XPAM 18 September 2018

XPAM Advantages Only XPAM can assess the initial plan Current EVM diagnostics cannot assess the the plan until after submission of some number of full EVM data Often more than a year after contract start 18 September 2018

XCaSA Tool Status Tested XCAM with multiple current programs Tested XPAM with notional initial program management baselines 18 September 2018

Potential Impact Improve oversight of programs Obtain early assessments of plan and contract execution Make better informed tradeoff decisions Make EVM tool of choice across the government 18 September 2018

Potential Future Studies Investigate use of the model with program level budget data Apply model to procurement contracts Upgrade tools with user feedback Open source management of tool Develop Monte Carlo policy simulation package with Rayleigh spline for tool Upgrade “insight” prompts in tool 18 September 2018

Recommendations Require Rayleigh EAC and estimate of duration time for R&D contracts Lower estimates must be explained Fund XCAM upgrades upgrade insight aspect of tool Examine the “missing” 30% of EACs Evaluate use with program level budget data Upgrade code functionality and user interface Fund study of indicators of a reliable contractor EVM system 18 September 2018

Conclusions Questions/Comments 18 September 2018