2K CB FDR Conclusion:  Project Summary, Procurement Plan / Status

Slides:



Advertisements
Similar presentations
Developing a Comprehensive Program of Study for Sustainability Tempe Union High School District Innovative Energy Solutions and Sustainability Project.
Advertisements

DEC JAN FEB MAR APR MAY JUNE JULY AUG SEP OCT NOV DEC JAN 2006 Antenna Design updating Antenna Detailed Design PPDR K.O. PPDR Data Pack. Reflector Panels.
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
AzMERIT Arizona’s Statewide Achievement Assessment for English Language Arts and Mathematics November 20, 2014.
Financial Systems Needs Assessment Project Update Monthly Research Administrators Meeting March 11, 2010.
M. White – June 28, 2004 LCLS Requirements Meeting In a project, we live or die by the schedule. After we’re “baselined” it is our plan for what we will.
State Milestones Subsidized Insurance Workgroup High Level Timeline 2011 Jan 2011 Feb 2011 Mar 2011 Apr 2011 May 2011 Jun 2011 Jul 2011 Aug 2011 Sept 2011.
Red Light Safety Camera Program Update Presented by Public Works Department Traffic Engineering Division Board of County Commissioners June 19, 2012.
RF Cavity / Coupling Coil Module
The ESS vacuum team has overall responsibility for all technical vacuum systems used on the: Accelerator, Target and Neutron Scattering Instruments and.
CIRDA Procurement – Philosophy leading to Plans and Strategies John T. Snow CTA on Meteorology UNDP-CIRDA. August 2015 After Jeremy Usher June 2015.
Navajo Nation Integrated Justice Information Sharing Project NNIJISP Office of the Chief Prosecutor Conference Albuquerque New Mexico October 24, 2008.
Hall C Meeting SHMS Magnets and Support Structure Design and Procurement Status Paul Brindza January 26, 2009.
ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
Measles Partnership Meeting Update on Vaccine Supply Washington, 27-28th February 2007 UNICEF Supply Division.
Time and Attendance Software A Software Application to Replace the Current Paper Based, Manual Process Personal and Academic Success for All!
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
Summary Report Project Name: Infoway Testing Environment Brief Project Description: A set of tools to test that vendors have successfully implemented the.
Technical Procurement Plan
19 October 2017 Overview The Management Board, at its December 2015 meeting, has endorsed the timeframe for the implementation of the EU clinical trial.
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
Vishy Ravindranath LCLS-II 2 K Cold Box FDR March 9, 2017
Director’s Progress Review Closeout Meeting
Cryoplant Controls Installation
Cryogenic Plant Controls – Cost and Schedule
2K Cold Box Structural Analysis
4.5 K Cold Box Schedule Recovery Directors’ Review
Dana Arenius LCLS-II 4.5K Cold Box Director’s Review November 16, 2016
Cryogenic Plant Electrical and Controls
2 K Coldbox Safety and ESH
2K Cold Box FDR Introduction
2K CB Internal Piping Flexibility Analysis
Contracting Officer Podcast Slides
LCLS-II 2K Cold Box Controls Design Review
Overview of Mechanical Design
Panorama Project Status Lab Use Optimization, TB, and STI Implementation 27 August 2015 Update to the Panorama Clinical and Business Oversight Committee.
MLC Schedule Plan Proven in-house expertise and infrastructure for fabrication, assembly, and testing cryomodules Confident in our technical expertise.
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
SIS100 quadrupole status S. Kostromin, H. Khodzhibagiyan, G. Trubnikov, FAIR 11th MAC, GSI, May,
2K CB FDR Overview:  Agenda, Charge, Review Process
2K Cold Box Process Design
2K Cold Box Mechanical Design
2K Cold Box Internal Piping Flexibility Analysis
Director’s Progress Review Closeout Meeting
JEFFERSON LAB LCLSII CRYOPLANT INSTALLATION PACKAGE DIRECTOR’S PROGRESS REVIEW Welcome and Introduction Stuart Henderson June 1, 2017.
Pressure Piping Analysis
Cryoplant Installation Design Summary
2K Cold Box Cost, Schedule & Staffing
ctclink Steering Committee
2K Cold Box Cost, Schedule & FDR Summary
ESB Networks Market Release Meeting of the IGG, March 5th 2009
This Presentation Pack is brought to you by
LCLS-II Cryoplant Controls FDR Status of Past Reviews and Lessons Learned Dana Arenius Sept 13, 2017.
Documentation Chris Scanlon and Ritendra Bhattacharya
Far Experimental Hall Hutches Civil Construction
Far Experimental Hall Hutches Civil Construction
Control Hardware & Status
Testing Plan and Status
AN LOCAL CONTENT VERIFICATION
Change Management Committee – Retail & Networks Update
CryoPlant Commissioning
LCLS-II Cryoplant Controls Workshop.
CV-SALTS Beneficial Use and Objective Study
Undulator and Magnet Production Status 25 October 2006
XRN Nov 19 Release - Status Update
XRN 4927 – MiR Drop 4 - Status Update
SNS-PPU upgrades the existing accelerator structure
XRN Nov 19 Release - Status Update
Presentation transcript:

2K CB FDR Conclusion:  Project Summary, Procurement Plan / Status Joe Matalevich LCLS-II 2 K Cold Box FDR March 28, 2018

Project Summary Implement redesign decision Updated and comprehensive analyses performed Focused design effort to complete detailed design Procurement strategy developed to achieve earliest delivery Solicit early feedback: RFI JLab to procure multiple long lead items PRR & RFP prior to FDR LCLS-II 2 K CBX FDR, Mar 28, 2018

Procurement Plan - GFE Long lead items to be provided as Government Furnished Equipment (GFE) RFI information helped confirm that furnishing Top Plate Assembly will provide significant reduction in ultimate delivery date Cold Compressors Cryogenic Control Valves Female bayonets Flow meter venturis Top Plate Weldment Assembly LCLS-II 2 K CBX FDR, Mar 28, 2018

Procurement Plan LCLS-II 2 K CBX FDR, Mar 28, 2018

Procurement Plan LCLS-II 2 K CBX FDR, Mar 28, 2018

Procurement Plan – Current Status Drawings Completed 28 Feb PRR Held 2 Mar RFP released for Solicitation 7 Mar Vendor Questions Due 28 Mar Bids Due 9 Apr Anticipated Award Early July Anticipated Delivery June 2019 Expectation is that remaining funds in 2K CB WBS is adequate for procuring 2 cold boxes LCLS-II 2 K CBX FDR, Mar 28, 2018

Thank you for your time today. Conclusion Thank you for your time today. Questions? LCLS-II 2 K CBX FDR, Mar 28, 2018