MONTHLY STATUS REPORT– May 2013 Title Slide MONTHLY STATUS REPORT– May 2013 LOS ALAMITOS UNIFIED SCHOOL DISTRICT Los Alamitos High School Track Modernization Project May 21, 2013 Los Alamitos, California
ACTIVITY SUMMARY ON TIME AND ON BUDGET General Site Conditions Executive Summary ACTIVITY SUMMARY General Site Conditions Mobilization of Site Complete Initial Surveying Complete Storm-water Pollution Prevention Plan Implemented Demolition Complete Soil Extraction Complete Grading and Compaction 90% Complete Concrete Retaining Curb at Parking Lot 95% Complete ON TIME AND ON BUDGET
ACTIVITY SUMMARY Track – Start of Construction Progress 21 ACTIVITY SUMMARY Track – Start of Construction Track – After First Day of Construction Track Prior to Construction
ACTIVITY SUMMARY Demolition Complete Dust Mitigation Progress 21 ACTIVITY SUMMARY Demolition Complete Dust Mitigation Typical Equipment on Project
ACTIVITY SUMMARY Storm-water Pollution Prevention On-Going Progress 21 ACTIVITY SUMMARY Storm-water Pollution Prevention On-Going Hay Tubes at Perimeter of Site Crushed Rock at Entry – Dust Mitigation
ACTIVITY SUMMARY Site Leveling 90% Complete Laser Leveler on Blade Progress 21 ACTIVITY SUMMARY Site Leveling 90% Complete Laser Leveler on Blade Laser Leveling Equipment
ACTIVITY SUMMARY Concrete Curb at Parking Lot 95% Complete Progress 21 ACTIVITY SUMMARY Concrete Curb at Parking Lot 95% Complete Formwork for New Concrete Curb Curb at Parking Lot Saw-Cut
ACTIVITY SUMMARY Soil Excavation/Compaction 90% Complete Progress 21 ACTIVITY SUMMARY Soil Excavation/Compaction 90% Complete Current “Track” Current “Track”
SCHEDULE General Site Conditions Begin Electrical and Timing Conduit Installation Begin Main Drain Tie-In Begin Installation of Site Curbing Begin Installation of Trench Drains Begin Installation of Fence Posts