Modeling and Analysis of High Volume Manufacturing Systems

Slides:



Advertisements
Similar presentations
Statistical Inventory control models I
Advertisements

CONWIP (A pull alternative to kanban principle)
OPSM 301: Operations Management Session 12: Service processes and flow variability Koç University Graduate School of Business MBA Program Zeynep Aksin.
Flowlines: The prevailing layout for High Volume Manufacturing.
1 Variability Basics God does not play dice with the universe. ---Albert Einstein Stop telling God what to do. ---Niels Bohr.
Modeling and Analysis of High Volume Manufacturing Systems.
Silberschatz, Galvin and Gagne  2002 Modified for CSCI 399, Royden, Operating System Concepts Operating Systems Lecture 19 Scheduling IV.
Variability Basics God does not play dice with the universe.
23–1. 23–2 Chapter Twenty-Three Copyright © 2014 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Rescheduling Manufacturing Systems: a framework of strategies, policies, and methods Vieira, Herrmann and Lin.
MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 6 SCHEDULING E
1 Performance Evaluation of Computer Networks Objectives  Introduction to Queuing Theory  Little’s Theorem  Standard Notation of Queuing Systems  Poisson.
presented by Zümbül Bulut
An overview of design and operational issues of kanban systems M. S. AKTÜRK and F. ERHUN Presented by: Y. Levent KOÇAĞA.
Customer Service in Pull Production Systems Mark L. SPEARMAN Presented By: Ahu SOYLU.
Push and Pull Systems: Lecture 12
Little´s law Skorkovský ,KPH,ESF.MU
Analysis and Design of Asynchronous Transfer Lines as a series of G/G/m queues: Overview and Examples.
Operations Management
Chapter 16 - Lean Systems Focus on operations strategy, process, technology, quality, capacity, layout, supply chains, and inventory. Operations systems.
WINTER 2012IE 368. FACILITY DESIGN AND OPERATIONS MANAGEMENT 1 IE 368: FACILITY DESIGN AND OPERATIONS MANAGEMENT Lecture Notes #3 Production System Design.
1 Chapter 7 Dynamic Job Shops Advantages/Disadvantages Planning, Control and Scheduling Open Queuing Network Model.
Modeling and Analysis of CONWIP-based Flowlines as Closed Queueing Networks.
Operational Research & ManagementOperations Scheduling Flow Shop Scheduling 1.Flexible Flow Shop 2.Flexible Assembly Systems (unpaced) 3.Paced Assembly.
Dr. Cesar Malave Texas A & M University
1 Chapter 5 Flow Lines Types Issues in Design and Operation Models of Asynchronous Lines –Infinite or Finite Buffers Models of Synchronous (Indexing) Lines.
CONWIP (A pull alternative to kanban principle) Main resources : Mark Spearman, David Woodruff and Wallace Hopp Northwestern University, Evanson, Illinois,
Queueing Analysis of Production Systems (Factory Physics)
Analysis and Design of Asynchronous Transfer Lines as a series of G/G/m queues.
© Wallace J. Hopp, Mark L. Spearman, 1996, Variability Basics.
1 Control of Production-Inventory Systems with Multiple Echelons.
Facilities design. Main Topics Discrete vs. Continuous Flow and Repetitive Manufacturing Process vs. Product-focused designs and the other currently used.
Modeling and Analysis of CONWIP-based Flowlines as Closed Queueing Networks.
OPERATING SYSTEMS CS 3530 Summer 2014 Systems and Models Chapter 03.
The Effects of Process Variability 35E00100 Service Operations and Strategy #3 Fall 2015.
CONWIP (A pull alternative to kanban principle)
Analysis and Design of Asynchronous Transfer Lines as a series of G/G/m queues.
Facility Design Issues. Back to the course objectives... Forecasting Strategic Planning Aggregate Production Planning Disaggregation Production Scheduling.
Facilities design. Main Topics Process vs. Product-focused designs and the other currently used variations Technology selection and capacity planning.
Modeling and Analysis of High Volume Manufacturing Systems
The Revolution of Just-In-Time (JIT) and Lean Manufacturing
Manufacturing Planning and Control
OPERATING SYSTEMS CS 3502 Fall 2017
Lecture 14 – Queuing Networks
Some Introductory Remarks on Operations Scheduling
IE4803-REV: Advanced Manufacturing Systems Modeling and Analysis Fall 2017 Instructor: Spyros Reveliotis homepage:
An introduction to Factory Physics
Analytical Tools for Process Analysis and Improvement
Process Design and Analysis
CHAPTER 8 Operations Scheduling
Course Summary Organization: A process providing goods and services based on a set of inputs, including raw material, capital, labor and knowledge. The.
Flowlines: The prevailing layout for High Volume Manufacturing
Analysis and Design of Asynchronous Transfer Lines as a series of G/G/m queues: Overview and Examples.
The Revolution of Just-In-Time (JIT) and Lean Manufacturing
PRODUCTION SYSTEMS Terminology Concept: Production: Performance:
Intended Usage Estimation of various performance indices, e.g.,
FACILITY LAYOUT Facility layout means:
CPU Scheduling G.Anuradha
Chapter 5 Process Analysis.
IV-2 Manufacturing Systems modeling
Topics Modeling CONWIP Flowlines as Closed Queueing Networks
MANUFACTURING SYSTEMS
Lecture 14 – Queuing Networks
Using the queuing-theoretic approximations for the performance of “push” and “pull” production lines to address Design Problems.
Process Analysis “If you cannot describe what you are doing as a process, you do not know what you are doing.” W.E. Deming.
CSE 550 Computer Network Design
Flexible Assembly Systems
Example: Designing an asynchronous prod. line
Copyright ©2016 Cengage Learning. All Rights Reserved
Presentation transcript:

Modeling and Analysis of High Volume Manufacturing Systems

Discrete vs. Continuous Flow and Repetitive Manufacturing Systems (Figures borrowed from Heizer and Render)

Operation Process Chart Example for discrete part manufacturing (borrowed from Francis et. al.)

A typical (logical) Organization of the Production Activity in Repetitive Manufacturing Assembly Line 1: Product Family 1 Raw Material & Comp. Inventory S1,1 S1,2 S1,i S1,n Finished Item Inventory Fabrication (or Backend Operations) Dept. 1 Dept. 2 Dept. j Dept. k S2,1 S2,2 S2,i S2,m Assembly Line 2: Product Family 2

Major Layout Types (borrowed from Francis et. al.)

Advantages and Limitations of the various layout types (borrowed from Francis et. al.)

Advantages and Limitations of the various layout types (cont Advantages and Limitations of the various layout types (cont. - borrowed from Francis et. al.)

The product-process matrix Production volume & mix Low volume, low standardi- zation Multiple products, low volume Few major products, high volume High volume, high standardization, commodities Process type Jumbled flow (job Shop) Commercial printer Void Disconnected line flow (batch) Heavy Equipment Connected line flow (assembly Line) Auto assembly Continuous flow (chemical plants) Sugar refinery Void

A conceptual characterization of the considered environments Flow line: A sequence of workstations supporting the production of a single part type. Each workstation consists of one or more identical servers executing one particular stage of the entire production process. The part processing time at each workstation follows some general distribution which must be defined in such a way that accounts for the various detractors affecting the station operations; these detractors will include machine downtime, lack of consumables, operator unavailability, experienced set-up times, preventive maintenance, etc. Finished parts could constitute end items or raw material for some other downstream process. The operation of the line workstations can be synchronized through an interconnecting conveyor system, or decoupled through the installation of some buffering capacity between them.

Line Performance Measures Production rate or throughput, i.e., the number of parts produced per unit time Line capacity, i.e., the maximum sustainable production rate Line (expected) cycle time, i.e., the average time that is spend by any part into the line (this quantity includes both, processing and waiting time). Average Work-In-Porcess (WIP) accumulated at different stations Expected utilization of the station servers. Remark: The above performance measures essentially provide a link between the directly quantifiable and manageable aspects and attributes of the considered operational environments and the primary strategic concerns of the company, especially those of responsiveness and cost efficiency.

Production Authorization Mechanisms The issue here is to what extent part production is triggered from actual orders or from forecasted demand. In a “produce-to-stock” scheme, a certain amount of end-item inventory is maintained in an effort to serve the experienced demand with zero lead time. “Produce-to-stock” operation is most appropriate for highly commoditized and standardized items. A key performance measure for “produce-to-stock” production systems is the fill rate, i.e. the percentage of the experienced demand that is actually met from stock. A desired fill rate is attained by maintaining an appropriate safety stock level, that is computed from the statistics of the experienced demand and cycle times. In a “produce-to-order” scheme, end items are produced in response to particular orders. “Produce-to-order” operation is more appropriate for (highly) customized items. A key performance measure for “produce-to-order” production is the attained service level, i.e. the percentage of orders that are served within the quoted lead time. A target service level is attained through informed lead time quotation and some appropriate “capacity buffer”. Currently, many systems are a hybrid scheme consisting of “produce-to-stock” and “produce-to-order” components. In particular, mass customization is supported by an “assemble-to-order” scheme where end-items are assembled to order from a number of sub-assemblies that are produced to stock.

Shop-Floor / Line Control Mechanisms Mechanisms that control the part release and advancement through the line. They are broadly distinguished into “push” and “pull” mechanisms. A “push” mechanism releases material into the line according to a target production rate, and material is advanced to downstream stations as early as possible. Typical instantiations of “push” systems are: the asynchronous transfer line and the synchronous transfer line. A “pull” system controls the part release and advancement in the line taking into consideration the status of the various workstations in the line. Typical instantiations of “pull” systems are: the KANBAN and the CONWIP (controlled) production lines. In general, “pull” systems reduce congestion, since they take into consideration the actual shop-floor status in their decision making, but the same mechanisms will also make them more inert in case of shifts in the production level. Both mechanisms are effectively implementable in a “produce-to-stock” or “produce-to-order” context.

Asynchronous Transfer Lines W1 W2 W3 TH TH TH TH B1 M1 B2 M2 B3 M3 Some important issues: What is the maximum throughput that is sustainable through this line? What is the expected cycle time through the line? What is the expected WIP at the different stations of the line? What is the expected utilization of the different machines? How does the adopted batch size affect the performance of the line? How do different detractors, like machine breakdowns, setups, and maintenance, affect the performance of the line?

Synchronous Transfer Lines The key issue: Assembly Line Balancing (ALB) Given a set of tasks to be supported by the line stations each possessing a nominal processing time, a number of precedence constraints among these tasks, and a target throughput, determine a partitioning of these tasks to a number of stations that observes the aforementioned specifications, while it minimizes the resulting number of stations (and therefore, the resulting labor cost).

KANBAN-based production lines Station 1 Station 2 Station 3 Some important issues: What is the throughput attainable by a certain selection of KANBAN levels? What is the resulting cycle time? How do we select the KANBAN levels that will attain a desired production rate? How do we introduce the various operational detractors into the model?

CONWIP-based production lines Station 1 Station 2 Station 3 FGI Some important issues: Same as those for the KANBAN model, plus How can we compare the performance of such a system to that of an asynchronous transfer line and/or a KANBAN-based system?

Module Objectives Provide an analytical characterization of the operation of HVM systems and their performance, based on queueing-theoretic models Derive qualitative insights and quantitative results on the attributes and factors that shape the behavior and performance of these systems. Demonstrate the application of these results to the design and control of the considered class of systems Focus primarily on flow lines, since they are the main layout used in the context of high-volume, repetitive manufacturing. Also, flow line dynamics are easier to trace and analyze, and therefore, more enlightening in terms of qualitative and quantitative insights. However, many of the derived insights and results are extensible to more complex environments either directly or through some appropriate decomposition.

Plan for the remaining part of the module Modeling and Performance Analysis of Asynchronous Transfer Lines through a Series of G/G/m queues Modeling the impact of operational detractors Employing the above results in line diagnostics Design of Asynchronous Transfer Lines Design of Synchronous Transfer Lines (cf. the ALB problem in the module on Sequencing, Dispatching and Scheduling of HVM systems) Modeling and Performance Analysis of CONWIP-based production lines through Closed Queueing Networks An integrating framework for bounding and shaping the performance of a production line Analyzing the impact of batching on the system performance and designing optimized batching policies Understanding the relative advantages and disadvantages of the various “push” and “pull”-based production systems

The G/G/1 model M1 TH B M2 Mm Modeling Assumptions: Part release rate = Target throughput rate = TH Infinite Buffering Capacity m identical servers Server mean processing time = te St. deviation of processing time = e Coefficient of variation (CV) of processing time: ce = e / te Coefficient of variation of inter-arrival times = ca

Performance measures for the G/G/1 station B TH M2 Mm Server utilization: Expected cycle time in the buffer: (Kingman’s approx.) Expected cycle time in the station: Average WIP in the buffer: (by Little’s law) Average WIP in the station: Squared CV of the inter-departure times:

Some Important Remarks The entire analysis of the previous slide is an approximation, since it derives from the provided approximation for CTq. The provided formula for CTq is exact for the M/M/m and M/G/1 stations. The station operation will be stable only if u = TH te / m < 1.0, i.e., only if the effective workload released into the station per unit of time is less than the available processing time of the station. Otherwise WIPq, CTq and CT will grow infinitely large. Notice that the requirement u < 1.0 is also suggested by the provided expression for CTq since only then CTq takes finite positive values. The expression for CTq comprises three factors, each depending respectively upon (i) the variability of the processing and inter-arrival times, as expressed by the corresponding SCV’s, (ii) the server utilization, and (iii) the mean processing time. An increase of any of these factors results in an increase of CTq, and also of CT, WIPq and WIP. Assuming a non-zero mean processing time, CTq=0.0 only if ca2= ce2=0.0; these are essentially the conditions of a paced / synchronous production line. The SCV of the inter-departure times can be approximated as a linear function of the SCVs of the inter-arrival and processing times. Furthermore, for u1.0, cd2 depends primarily on ce2, while for u0, cd2 depends primarily on ca2.

Analyzing an entire Production Line TH Key observations: A target production rate TH is achievable only if each station satisfies the stability requirement u < 1.0. For a stable system, the average production rate of every station will be equal to TH. For every pair of stations, the inter-departure times of the first constitute the inter-arrival times of the second. Then, the entire line can be evaluated on a station by station basis, working from the first station to the last, and using the equations for the basic G/G/1 model.

Modeling the impact of operational detractors Effective processing time = time that the part occupies the server Effective processing time = Actual processing time + any additional non-processing time Actual or otherwise natural processing time typically presents fairly low variability ( SCV < 1.0). Non-processing time is due to detractors like machine breakdowns, setups, operator unavailability, lack of consumables, etc. Detractors are distinguished to preemptive and non-preemptive. Each of these categories requires a different analytical treatment. Preemptive detractors are outages that take place during the actual processing of the part. Typical examples are machine breakdowns, lack of consumables, operator unavailability, etc. Non-preemptive detractors are activities that may take place between the processing of two consecutive parts. Typical examples are setups, preventive maintenance, operator breaks, etc. We want to determine the mean, variance and SCV of the effective processing time from the corresponding attributes of the natural processing time and some additional attributes characterizing the behavior of the various detractors.

Modeling the impact of preemptive detractors X = random variable modeling the natural processing time, following a general distribution. to = E[X]; o2=Var[X]; co=o / to . T = random variable modeling the effective processing time = where Ui = random variable modeling the duration of the i-th outage, following a general distribution, and N = random variable modeling the number of outages during a the processing of a single part. mr=E[Ui]; r2=Var[Ui]; cr = r / mr Time between outages is exponentially distributed with mean mf. Availability A = mf / (mf+mr) = percentage of time the system is up. Then, te = E[T] = to / A or equivalently re = 1/te = A (1/to) = A ro

Breakdown Example Data: Injection molding machine has: 15 second stroke (to = 15 sec) 1 second standard deviation (o = 1 sec) 8 hour mean time to failure (mf = 28800 sec) 1 hour repair time (mr = 3600 sec) Natural variability co = 1/15 = 0.067 (which is very low)

Example Continued Effective variability: Which is very high!

Example Continued Suppose through a preventive maintenance program, we can reduce mf to 8 min and mr to 1 min (the same as before) Which is low!

Modeling the impact of non-preemptive detractors X = random variable modeling the natural processing time, following a general distribution. to = E[X]; o2=Var[X]; co=o / to . NS = average number of parts processed between two consecutive setups It is also assumed that the number of parts between two consecutive setups follows a geometric distribution, which when combined with the previous bullet, it implies that probability for a setup after any given job = 1/ NS. Z = random variable modeling the duration of a setup tS = E[Z]; S2 = Var[Z] S = random variable modeling the setup time experienced by any given job = T = random variable modeling the effective processing time = X+S Then, E[S] = tS / NS ; Var[S] = (S2 / NS) + tS2((NS-1) / NS2); te = E[T] = to+tS / NS ; ;

Setup Example Data: Fast, inflexible machine – 2 hr setup every 10 jobs to = 1 hr Ns = 10 jobs/setup ts = 2 hrs re = 1/te = 1/(1+2/10) = 0.8333 jobs/hr Slower, flexible machine (with no setups!) to = 1.2 hr re = 1/to = 1/(1.2) = 0.8333 jobs/hr So with traditional analysis, there is no difference!

Example Continued Slower, flexible machine – no setups: to = 1.2 hr re = 1/to = 1/(1.2) = 0.8333 jobs/hr ce2 = co2 = 0.25 Conclusion: Flexibility reduces variability

Example Continued Considering mean and variability: Fast, inflexible machine – 2 hr setup every 10 jobs to = 1 hr and ts = 2 hr co2=0.0625 Ns = 10 jobs/setup te = 1+2/10 = 1.2 hrs re = 1/te = 1/(1+2/10) = 0.8333 jobs/hr re = 1/to = 1/(1.2) = 0.8333 jobs/hr e2 = 0.4475 ce2 = 0.31

Example Continued Consider a third machine that is the same as the previous machine with setups, but with shorter, more frequent setups: Ns = 5 jobs/setup ts = 1 hr Analysis: Conclusion: Shorter, more frequent setups induce less variability

Example: Employing the presented results for line diagnostics B M2 to1 =19 min co12=0.25 mf1=48 hrs mr1=8 hrs MTTR ~ expon. to2 =22 min co22=1.0 mf2=3.3 hrs mr2=10 min Ca2=1.0 20 parts Desired throughput is TH = 2.4 jobs / hr but practical experience has shown that it is not attainable by this line. We need to understand why this is not possible.

Diagnostics example continued: Capacity analysis based on mean values

Diagnostics example continued: An analysis based on the G/G/1 model i.e., the long outages of M1, combined with the inadequate capacity of the interconnecting buffer, starve the bottleneck!

Example: Designing an asynchronous prod. line Design of a new 4-station assembly line for circuit board assembly. The four consecutive stations and the currently considered “technology options” for them (each option defines the processing rate in pieces per hour, the CV of the processing time, and the cost per unit in thousands of dollars). The above data correspond to the effective processing times. Each station can employ only one technology option. The maximum production rate to be supported by the line is 1000 panels / day. The desired average cycle time through the line is one day. One day is equivalent to one 8-hour shift. Workpieces will go through the line in totes of 50 panels each, which will be released into the line at a constant rate determined by the target production rate. Design task: Identify a line configuration that meets the above requirements while minimizing the equipment cost. Also, estimate the expected WIP at every station, when the line is operated at maximum production rate.

A baseline design: Meeting the desired prod. rate with a low cost

Reducing the line cycle time by adding capacity to Station 2

Adding capacity at Station 1, the new bottleneck

An alternative option: Employ less variable machines at Station 1 This option is dominated by the previous one since it presents a higher CT and also a higher deployment cost. However, final selection(s) must be assessed and validated through simulation.

Analyzing CONWIP-based flowlines with single-machine stations as Closed Queueing Networks (CQNs) Mean Value Analysis - the key underlying ideas: A CONWIP-based flow line with single-machine stations and its WIP level set to W, can be modeled by a closed queueing network (CQN) with general processing distributions, W jobs in it, and the following structure: II. In a CQN with W jobs and exponential processing times, the expected number of jobs observed at the various stations by a job arriving at some station Sj, is equal to the expected number of jobs observed at any random time at the same stations when the system is operated with W-1 jobs in it. III. Assuming that this effect applies in an approximate sense for more general distributions of the processing times, we proceed to develop an algorithm that will compute the performance measures of interest iteratively, for various W levels, starting with W=0.  M1  M2  Mn

Notation n = number of stations te(j) = mean effective processing time at station j ce2(j) = SCV for effective processing time at station j TH(W) = the line throughput when operated with WIP level W CT(W) = expected job cycle time through the line CTj(W) = expected job cycle time at station j when the WIP level is W WIPj(W) = expected WIP level at station j when the WIP level is W uj(W) = utilization of the server at station j when the WIP level is W

Deriving the algorithm iteration CTj(W) = E[remaining processing time for the job at the server of Sj] + (E[number of jobs at station Sj]-E[number of jobs in service])te(j) + te(j) But E[remaining processing time for the job at the server of Sj] = Prob(Server of Sj busy)E[remaining process time | busy] = uj(W-1)E[remaining process time | busy]  (b) E[number of jobs at station Sj]  WIPj(W-1) E[number of jobs in service]  uj(W-1) (d) uj(W-1) = TH(W-1) te(j)

Deriving the algorithm iteration (cont.) Combining the results of the previous slide: But then, Obviously, for W=0, CT(0) =TH(0) = WIPj(0) = 0 Furthermore, application of the above formulae for W=1 gives: (from Little’s law)

Bounding the line throughput: Upper bounds For W, TH(W)rbminj{1/te(j)}, the bottleneck rate of the line. rb can also be achieved with finite WIP in a deterministic setting, i.e., in a line with ce(j) = 0, j, and synchronized with pace tb=1/rb. However, by Little’s law, a line with raw process time To, in order to produce at rate rb, will need a WIP level of Wo=rbTo; this WIP level is known as critical WIP. An interpretation of Wo is given by the following formula: i.e., Wo is the level of WIP that we must maintain in the system in order to maintain the bottleneck utilization at 100%. Otherwise, the bottleneck will starve. If W<Wo, then in a deterministic setting we can pace the jobs through the system in such a way that CT=To. Hence, the maximal line throughput will be

Example: Attaining the throughput upper bound with balanced, deterministically paced line W=Wo=rbTo=5 W=6 W=4 t1 t2 t3 t4 t5 = 1.0 TH=rb=1 CT=To=5 CT=To+tb=6 TH=W/CT =4/5

Bounding the line throughput: Lower bounds (under global non-idleness) Clearly, 1/To is a lower bound to TH(W) under global non-idleness, since this is the rate of a line with only one job in it, and therefore, no parallelism. This bound is also achievable under any other finite WIP level W, by a non-idling policy that moves all W jobs as a single batch from station to station. Indeed, for that policy

Example: Attaining the throughput lower bound through batching = = = = 2.0 T = 0 T = 6 T = 12 T = 18 T = 24 TH = W / (W To) = 3 / 24= 1 / 8

The W-TH(W) space TH(W) W Ideal Operational Point rb 1/To 1/To 1 Wo=rbTo W

The W-CT(W) Space To Wo 1 CT(W) W 1/rb Ideal Operational Point The depicted curves are induced from those depicted in the W-TH(W) space, through Little’s law. In particular, upper bounds in the W-TH(W) space provide lower bounds in the W-CT(W) space, and vice versa, as follows:

Practical System Performance The “ideal” performance is attained in an optimized, deterministic setting. this performance is typically compromised by the variability that is inherent in the system operations; the impact of the applied control policies (e.g., the batching policy that defines the lower bounds for the system throughput - Notice, however, that these policies might be justified from some broader considerations). A “benchmark” case: Maximizing the variability inherent in the system operation Single-machine stations Exponential processing times Balanced line, i.e., te(j) = t, j Key feature: All feasible states for this line are equiprobable. Mean Value Analysis (exact, since processing times are exponential): Remarks: As expected, TH(1) = rb/Wo =1/To and TH() = rb. A performance that is worse than that of the “benchmark” case is a strong indication of mismanagement / bad practice.

Effective Mechanisms for Improving the System Performance The problem: Given a line operating at a desired throughput rate, TH, what are some possible mechanisms to reduce the expected cycle time through the line, CT (and through Little’s law, the line WIP, W) ? The key idea: We need to “pull” the curve describing the line performance in the W-TH(W) space to the left. (i) Increase rb (by adding capacity or making more effective use of the existing capacity at the line bottleneck(s)) TH(W) W Wo 1 TH 1/To rb rb’ 1/To’ Wo’ W’

Effective Mechanisms for Improving the System Performance (cont.) (ii) Add capacity to some non-bottleneck station(s) (this addition essentially enables the better catering to the bottleneck needs, but it can help only to a limited extent) TH(W) rb=rb’ TH 1/To’ 1/To’ 1/To 1/To W 1 Wo’ W’ Wo W (iii) Reduce the inherent variability at the different stations; the corresponding reduction of the station CVs will “pull” the performance curve in the W-TH(W) space closer to the curve characterizing the upper bound. (iv) Increase the line flexibility, which essentially enables the better utilization of the bottleneck capacity (and takes us back to item (i) above).

Demonstrating the “inertia” of CONWIP lines Problem: Consider a CONWIP line operated at 80% of its bottleneck rate. Furthermore, the performance of the line compares favorably to that of the “benchmark” case, and W>>Wo so that CTW/rb. Compute the relative increase W/W that will increase the line throughput to 85% of its bottleneck rate. Solution: Let W=W’-W=xW. Then, i.e., the necessary increase is almost 42% of the original WIP!

Batching Batching implies the physical or logical grouping of a number of parts processed through (different segments of) the system. Possible reasons for batching: High set up times and costs => need for serial process batching to control the capacity losses Processes that require a large production volume in order to maintain a high utilization (e.g., fermentors, furnaces, etc.) => need for parallel process batching An excessive and/or costly material handling activity => need for move or transfer batching From the vantage of the processing taking place at the different stations, batching is an additional source of variability in the inter-arrival and/or processing times, and therefore, a source of delays. Hence, a pertinent batch size must be large enough to maintain feasibility of the production requirements and/or help control the target operational costs but not too large so that it incurs unnecessary part delays and/or inventory holding costs

Example: Optimizing Parallel Batches through a queueing-theoretic approach Model Parameters: k: (parallel) batch size B: maximum batch size ra: arrival rate (parts/hr) ca: CV of inter-arrival times t: batch processing time (hrs) ce: CV for effective batch processing time Then CT = WTBT + CTq+t From the above, Remark: Notice that CT as u1 but also as u0 !

Determining an “optimal” batch size Let um  rat . Then u = um / k  k = um / u . Substituting this expression for k in the expression for CT, we get: and we get Recognizing that , we set where To minimize CT, it suffices to minimize y(u). This can be achieved as follows: and which further implies that Remark: If ce2  0, the term  in the original expression for u* will significant. In that case, we can set and obtain u* and k* as before.

Some implications of the derived results Minimum feasible batch size may be greater than one If process times are long enough and batch capacity large enough, cycle time will be minimized with a batch size greater than one Eventually cycle time grows proportionally with batch size Without wait-for-batch time, cycle time decreases in batch size CT Batch Size

Parallel Batching Example Parameters k = batch size (10) te = time to process a batch (90) ce2 = SCV for batch (1) ra = arrival rate for parts (0.05) ca2 = SCV of batch arrivals (1.0)

Determining the minimum batch size Time to process batch: te = 90 Arrival of batches: ra/k = 0.005 Utilization: u = (ra/k)(te) = 0.45 For stability: u < 1 implies

Estimating the delays experienced at the batch station Average wait-for-batch time: Average queue time at station: Total cycle time: WTBT+CTq+te = 220.5

Serial Batching Example: Single processing station Parameters k = batch size (10) to = time to process a singe part (1) ts = time to perform a setup (5) ce2 = SCV for batch (parts + setup) (0.5) ra = arrival rate for parts (0.4) ca2 = SCV of batch arrivals (1.0)

Determining a minimum batch size Time for batch: te = ts + kto = 15 Arrival of batches: ra/k = 0.04 Utilization: u = (ra/k)(ts+kto) = 0.6 For stability: u < 1 implies

Estimating the experienced delays Average queue time at station: Average cycle time depends on move batch size Move batch = process batch (non-split) Move batch = 1 (split)

Serial Batching Effect Minimum feasible batch size may be greater than one If setup times are long enough, cycle time will be minimized with a batch size greater than one Eventually cycle time grows proportionally with batch size No-Splitting Lot Splitting CT Batch Size

Move Batches Cycle times over a segment of a routing are roughly proportional to the move batch sizes used over that segment. For 2 machines in series:

Move Batching Effect Cycle time increases proportionally with the move batch size Low arrival rates cause long “wait for batch” times Inflation term does not depend on CV Batching delay is essentially separate from variability delay Congestion from batching is more bad control than variation

On the relative advantages of “push” and “pull”-based production systems The WIP cap employed by “pull” systems provides a feedback mechanism for reacting to operational disruptions and prevents congestion. The avoidance of congestion further facilitates more flexible and responsive decision making in reaction to arising contingencies. Another benefit from avoiding congestion is that the WIP necessary to elicit a certain throughput, TH, from a “pull” system is typically lower than the WIP accumulated in this system when it is operated in a “push” mode and with the feeding rate equal to TH. WIP as a control variable is more easily measurable than throughput. The performance attained by a “pull” system is robust to the selection of the WIP level. However, this robustness also implies that the production rate of a “pull” system cannot be easily controlled through WIP cap adjustments, which further implies that effective deployment of “pull” systems necessitates non-volatile demand profiles (and raises the issue of active demand management). CONWIP systems can achieve higher throughput than their KANBAN-based counterparts because they provide the aforementioned advantages of “pull”-based operation while eliminating the negative impact of (internal) blocking that is inherent in the KANBAN mechanism.

Suggested Readings Hopp & Spearman, Factory Physics, 2nd ed., Irwin-McGraw Hill, 2001 Cachon and Terwiesch, Matching Supply with Demand: An Introduction to Operations Management, Irwin-McGraw Hill, 2006 Buzacott and Shanthikumar, Stochastic Models of Manufacturing Systems, Prentice Hall, 1993 Viswanadham and Narahari, Performance Modeling of Automated Manufacturing Systems, Prentice Hall, 1992