Wrangle Hill Elementary School New Castle, DE

Slides:



Advertisements
Similar presentations
“Sustainable Building Systems and Construction For Designers” Chapter 7: Walls.
Advertisements

This is the first slide in the slide show, click each time you would like to go to the next slide. Thank you.
The Millennium Science Complex
Chapter 20 Cladding with Masonry & Concrete
Financial Responsibility Joint Sustainability Initiative.
Optimizing “Big Box” Construction Lauren Hughes Josh Hogan Kevin Hanson Joseph Garrott Rose-Hulman Institute of Technology.
Penn State Hershey Medical Center Children’s Hospital Hershey, Pennsylvania Matthew Vandersall Structural Option AE Senior Thesis Dr. Richard Behr.
The University Sciences Building Northeast, USA Final Presentation Chris Dunlay Structural Option Dr. Boothby.
C AMPUS S QUARE H ARRISBURG, P ENNSYLVANIA A NDREW M ARTIN | C ONSTRUCTION M ANAGEMENT | A PRIL 12, 2010.
Structural Insulated Panel System Chapter 15. Mehta, Scarborough, and Armpriest : Building Construction: Principles, Materials, and Systems © 2008 Pearson.
Kyle Goodyear BAE in Construction Management Pennsylvania State University Senior Thesis Presentation April 12, 2010.
Topic C1 Superstructures - walls
Financial Responsibility. The Concrete Joint Sustainability Initiative is a multi-association effort of the Concrete Industry supply chain to take unified.
2001 Winter Presentation. Site Location Site View.
Structural Systems CM 105. Precast Concrete Framing Offer exceptional strength and resistance to seismic stresses and high degree of fire safety Concrete.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Courtesy of Holbert Apple Associates Georgia Avenue Building Introduction Statistics Gravity System Lateral System Problem Statement & Solution.
THE MITCHELL FRAMING SYSTEM A building system that encourages homeowners to have a direct involvement in driving building growth and expansio n Neal Mitchell.
What is Thermal Bridging? A reduction of the effectiveness of insulation to reduce conductive heat flow through the building envelope otherwise know as.
360 State Street New Haven  CT  Structural | Sabrina Duk | T. Boothby.
The New RLPS Architects Office Building Lancaster, PA Brice Ohl – Mechanical Option Presented on 4/10/13.
Introduction Connected to existing Benton Hall via skywalk Size: 103,154 SF above grade on 4 levels 82,661 SF below grade parking on 3 levels Cost: $23,651,159.
GARY NEWMAN STRUCTURES OPTION ADVISOR: DR. HANAGAN SENIOR THESIS PRESENTATION SPRING 2008.
Kennedy Krieger Institute Outpatient Medical Center Baltimore, Marylan d Katie Sennett Construction Management Dr. Messner Spring 2008.
Council Rock High School South Seth Glinski Construction Management Spring 2003 Thesis.
First Baptist Church of Doylestown Senior Thesis Structural Emphasis James Chester Preliminary Phase II Design.
Charles Miller Construction Option Spring Dr. Riley WestEnd25.
BRYAN DARRIN SENIOR THESIS PRESENTATION MILLENNIUM HALL DREXEL CAMPUS PHILADELPHIA, PA.
Lancaster, PA Courtyard by Marriott Danielle Shetler - Structural Option Senior Thesis - Spring 2005.
Caitlin Ferrell Structural Option Senior Thesis Presentation Spring 2006 The Erie Convention Center and Sheraton Hotel Erie, Pennsylvania Architectural.
The Health Care Center Dauphin County, PA Ken Lorenz Penn State University Architectural Engineering Construction Management April 17, 2007.
Architectural Engineering Construction Management Senior Thesis April 11 th, 2011 Consultant: Dr. Riley Architectural Engineering Spring 2011 – Senior.
Third Avenue NY, New York Michelle L. Mentzer Structural Option.
Robert M. Arnold Building Fred Hutchinson Cancer Research Center
Waynesburg Central High School Waynesburg, Pennsylvania Robert Owen Brennan The Pennsylvania State University Construction Management.
DEREK BAUER CONSTRUCTION MANAGEMENT AE SENIOR THESIS 2008 PENN STATE UNIVERSITY AE SENIOR THESIS PRESENTATION APRIL 15, 2008 OFFICE/RETAIL BUILDING WASHINGTON,
New Middle School Geneva, Il Greg Kemerer AE Senior Thesis 2006 – CM Option.
Swedish American Hospital Heart and Vascular Center Philip Frederick Structural Option AE Senior Thesis 15 April 2008.
Sullivan Trail Junior High Pocono Summit, Pennsylvania Andrew Mellow Goals Background Drawings Site Plan Schedule April 13, 2005.
Andrew Diehl The Pennsylvania State University Architectural Engineering Department Structural Option 5 th Year Senior Thesis Project “The Comparison of.
A Prefabricated Framing and Enclosure System. The Problem.
Jon Hill – Structural OptionSpring 2005 Senior Thesis Structural Analysis and Redesign of Lynde and Harry Bradley School of Technology & Trade Milwaukee,
QuickWalls® strong. fast. simple. *Light Weight *Insulated
Arts & Humanities Instructional Building Noah J. Ashbaugh Construction Management 2006.
Brandon mckee ae senior thesis 2007 construction management penn state university ambridge area high school Ambridge Area High School ambridge, pennsylvania.
Biobehavioral Health Building The Pennsylvania State University Daniel Bodde Structural Option Advisor – Heather Sustersic.
Albany Medical Center Patient Pavilion Albany, Ny Thomas J. Kleinosky – Structural Senior Thesis 2012 | Advisor: Dr. Hanagan.
Bellefonte Area High School Mark Demianovich Construction Management 2007.
Hunter Woron Spring 2012 Structural Professor Parfitt.
Organize Project Team 1 Project is to build Crew Boat facility on Lake Washington Construction Management involves working in teams to meet owner requirements.
K-3 Modular Classrooms Constructed with Cross Laminated Timber REQUEST FOR QUALIFICATIONS FOR Design-Build Services Project No Project No
Building Resource Inc. Sustainable Durable Buildable Cost Effective
BLAKELY  Welcome.
WDMA Technical Conference Chicago, IL 28 June 2016
Harley-Davidson Museum
Pearl Condominiums Philadelphia, PA
The Stuckeman Family Building
UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
Redifer Commons Addition & Renovation Project
BUILDING CONSTRUCTION 1
Graduate Circle Housing Proposal for the Pennsylvania State University
Council Rock High School South
Acterna Headquarters John M Sekel, EIT Germantown, Maryland
Progress Report 11/10/11.
TOWERS CRESCENT BUILDING B Mike Synnott Structural.
Project Background Type of building: Mixed-use residential building
Construction Management Option
Project: 250 West Street, Columbus, Ohio
Minuteman Vocational Technical Regional High School Progress
© OnCourse Learning.
Presentation transcript:

Wrangle Hill Elementary School New Castle, DE Prefabrication: Constructing more efficiently and a Study on its Implications Wrangle Hill Elementary School New Castle, DE Dave Fox Faculty Consultant: Dr. Riley

Project Background Goals CM Research CM Issues Building Envelope Building Enclosure Photovoltaic Conclusions Questions Project Background Goals CM Research Issues Recommendations CM Issues Schedule Cost Building Envelope Heat Transfer Condensation Analysis Photovoltaic Architecture Calculations Conclusions Recommendations Questions

Wrangle Hill Elementary School Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Wrangle Hill Elementary School One Story, 157,000 square feet Shaped like an “X” Four wings are all identical Houses Kindergarten through fifth grade Help meeting increase in students Full time Kindergarten Central Core holds support functions Two Cafeterias, one kitchen 60 classrooms

Architecture and Engineering Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Architecture and Engineering Hand laid masonry façade CMU interior classroom walls Steel stud office walls Structural steel skeleton Standing seam metal roof and flat roof Terrazzo hallway floors Entrances are aluminum storefronts Brick entranceway

The Project Team EDiS Team Project Organization Fast Schedule Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions The Project Team EDiS Team Fast Schedule Experienced team Two superintendents Two Project Managers Project Organization Colonial School District Represented itself Architect designed other schools

Construction and Site Layout Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Construction and Site Layout Constructed four wings first Central Core area followed wings 35 days per wing for masonry $10,000 per day liquidated damages Large site, minimal congestion Material storage must be in rear Job trailers located near entrance to site Loop road used for construction access

Thesis Goals, Efficiency Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Thesis Goals, Efficiency Reduce schedule Construct more efficiently Create a more efficient building Reduce electricity demand

CM Research The Issues Recommendations Project Background Goals CM Issues Building Enclosure Photovoltaic Conclusions Questions CM Research The Issues Recommendations

The Issues Upfront design and construction cost Schedule Impacts Increased design costs Increased cost for design changes later in design Increased cash flow at the beginning of construction Colonial School District expressed issues about obtaining the increased flow due to the school board Quality Prejudices that prefabrication is not high quality All persons interviewed had stated that prefabrication is just as good if not better than in the field “Assembly line” style construction allows for easy quality control Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions The Issues Upfront design and construction cost Schedule Impacts Quality Labor Force Reduced Construction Waste Labor Force Reduced dependence on unionized labor reduces risk of strikes Using prefabrication in highly unionized areas can be very difficult Schedule Impacts Reduced schedule due to decreased on-site construction Panels arrive when needed and immediately get put in place Reduction of on site congestion

Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Recommendations Prefabricator assistance with design from the very beginning Development of draft billing cycle for owners Owners dictating to architects to use prefabrication Owners need to be informed Overcoming prejudices about prefabrication

Prefabrication on Wrangle Hill Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Prefabrication on Wrangle Hill Schedule Cost

Prefabrication on Wrangle Hill Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Prefabrication on Wrangle Hill SlenderWall® Panels to replace exterior masonry work Prefabricated Steel stud wall with brick stamped precast concrete Minimal architectural impacts 5 days to erect the façade of an entire wing vs. 35 days for masonry Steel studs attach to structural steel, yet rest on slab on grade

Schedule Savings 5 days per wing to install façade Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Schedule Savings 5 days per wing to install façade Temporary heating and Conditioning Masonry System – 10/9 Prefab System – 9/5 Overall Schedule Savings 34 days

Cost Implications Cost Increase Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Cost Implications Cost Increase $89,000 Only .28% of project cost Possible reduction of General Contractor fee due to reduced risk

Building Enclosure Heat Transfer Condensation Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Building Enclosure Heat Transfer Condensation

Heat Transfer Analysis Masonry Design Prefabricated Design Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Heat Transfer Analysis R-Value analysis to calculate heat transfer Three Systems Evaluated Masonry System (R-Value 12.8) Prefabricated System (R-Value 16.3) Prefabricated System with Additional Insulation (R-Value 17.8) Additional insulation is used to combat thermal bridging due to the steel studs Without Insulation, the temperature of the steel studs is below interior air dew point in winter Prefabricated Design With Additional Insulation

Condensation Analysis Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Condensation Analysis Vapor resistances for each element Overall flow rate calculated Condensation occurred on the interior face of the additional polystyrene insulation Rate of condensation, .3oz per day in a 28’x 11’ wall. Very minimal as well as the worst condition, it can be assumed this will dry out as the weather changes

Photovoltaic Integration Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Photovoltaic Integration Architectural Impacts Cost Analysis

Architecture Minimal architectural impact Statement in the community Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Architecture Minimal architectural impact Solar panels integrate into standing seam metal roof Statement in the community Students can study the panels Showing community that Colonial School District is working to help the environment

Calculations and Cost PVWatts from NREL used for panel output data Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Calculations and Cost PVWatts from NREL used for panel output data Two different locations analyzed Annual electricity savings Simple payoff period calculation Government grants Additional Research to determine impact in the community

Thesis Goals, Efficiency Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions Thesis Goals, Efficiency Reduce schedule Construct more efficiently Create a more efficient building Reduce electricity demand

CM Research CM Issues Building Enclosure Photovoltaic Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions CM Research Bring prefabricator into design at the beginning to combat upfront design fees and increased cash flow at the beginning of construction CM Issues Schedule benefits with little cost increase Building Enclosure Better performance then masonry wall Additional polystyrene insulation is necessary Photovoltaic Roughly $2,500/year savings Community impact needs further research

Project Background Goals CM Research CM Issues Building Enclosure Photovoltaic Conclusions Questions