Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE.

Slides:



Advertisements
Similar presentations
Our Turn To Change The Future! Buckeye Locals 2009 Building Project Spring 2009.
Advertisements

Jeopardy Q 1 Q 6 Q 11 Q 16 Q 21 Q 2 Q 7 Q 12 Q 17 Q 22 Q 3 Q 8 Q 13
Jeopardy Q 1 Q 6 Q 11 Q 16 Q 21 Q 2 Q 7 Q 12 Q 17 Q 22 Q 3 Q 8 Q 13
Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.
Aubrey Green Community Meeting Issues and Opportunities Vandalism Safety Community Image Community Opportunities and Renewal Who is here and Why PW - Parks.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District July 21, 2008 BUILDING TOMORROW TODAY 1.
East Parking Garage Project (Executive Leadership Council) January 31, 2011.
Fullerton College Bond Fund Projects Update Fullerton College Athletics Project Scope Overview Schedule Parking.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 20, 2009 EDUCATE ENGAGE EMPOWER 1.
Module Reading Plans and Elevations
MULTIPLE PROFESSIONAL REVIEWS DOCUMENT SOLUTIONS Architectural and engineering review identifies building code and accessibility repairs needed. ($750,000.
MARPLE NEWTOWN SCHOOL DISTRICT FACILITIES. Maintenance & Small Projects Planned for Summer 2007 New carpet at Worralls office New fencing at Worralls.
Recent Bond Accomplishments. Bordeaux Elementary Remodel.
August 2008 WATCH YOUR STEP! CONSTRUCTION PROJECTS UNDERWAY!
Draft FMP Priorities For Discussion Facilities Committee 3/5/13.
June 8, 2011 Irvine Unified School District. What is a Modernization? Eligibility Permanent buildings - 25 years old Portable buildings - 20 years old.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 18, 2011 EDUCATE ENGAGE EMPOWER 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District November 1, 2007 BUILDING TOMORROW TODAY Cordoba Corporation.
O X Click on Number next to person for a question.
Update on FCPS Construction/Renovation Projects April 2009.
April 14, 2009 Los Angeles Valley College Prop J Master Plan Town Hall Presentation.
25 seconds left…...
Bond Program Planning Imperatives Study Session October 12, 2004.
Marin Community College District CIP Briefing – Citizen’s Oversight Committee September 13, 2005.
We will resume in: 25 Minutes.
Design Review Planning to date Project scope summary
1 Unit 1 Kinematics Chapter 1 Day
O X Click on Number next to person for a question.
BOND PROGRAM UPDATE Long Beach Community College District Citizens’ Oversight Committee Meeting October 11, 2004.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District October 2008 EDUCATE  ENGAGE  EMPOWER 1.
BOND PROGRAM UPDATE Building Tomorrow Today Long Beach Community College District Citizens’ Oversight Meeting October 9, 2006.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District January 31, 2011 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Program Long Beach City College District November 2006.
Current Project Update October 25th 2012 Good Evening!!!
Greenbush School Maintenance Calendar. JULY Week 1 ❏ Check clock systems ❏ Fertilize athletic fields ❏ Drag and roll baseball/softball fields ❏ Clean.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District October 19, 2009 EDUCATE  ENGAGE  EMPOWER 1.
LOCAL ASSISTANCE 5 – YEAR PLAN Facilities Department Mark Thissell.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District July 20, 2009 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District August 8, 2011 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District January 25, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District October 25, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 25, 2012 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District September 2, 2008 BUILDING  TOMORROW  TODAY 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District April 14, 2010 EDUCATE  ENGAGE  EMPOWER 1.
BOND PROGRAM UPDATE Building Tomorrow Today Long Beach Community College District The Long Beach Rotary Flex Day,March 28, 2007 Flex Day, March 28, 2007.
BOND PROGRAM UPDATE Long Beach Community College District Board of Trustees Meeting July 13, 2004.
Bond Construction Update Citizens’ Oversight Committee Long Beach Community College District January 28, 2008 BUILDING  TOMORROW  TODAY Cordoba Corporation.
BOND PROGRAM UPDATE Long Beach Community College District Citizens’ Oversight Committee Meeting July 12, 2004.
Bond Construction Program Long Beach City College District March 2007.
Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District Septmeber 24, 2009 EDUCATE  ENGAGE.
Torrance Unified School District Bond Measure Y Bond Measure Z Quarterly Construction Update September 30, 2009.
Paradise Valley Community College CLC Update Jacalyn A Askin, Vice President of Administrative Services May 8, 2009.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District September 1,
Bond Construction Update Facilities Advisory Committee Long Beach Community College District November 17, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District October 24, 2011 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District January 23, 2012 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District April 6, 2011 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District July 26, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District September 14, 2011 EDUCATE  ENGAGE  EMPOWER 1.
MODERNIZATIONS MEASURE G OVERSIGHT COMMITTEE September 8, 2015.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District March 3, 2010 EDUCATE  ENGAGE  EMPOWER 1.
2006 Facilities Master Plan Update Cañada College
Facilities Update November 17, 2017
MIRACOSTA COMMUNITY COLLEGE DISTRICT
Facilities Modernization Program
College Council Meeting September 7, 2018
Recent Bond Accomplishments
Presentation transcript:

Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE EMPOWER 1

Agenda Completed Construction Projects PCC Learning Resource Center LAC Central Plant Current & Upcoming Construction Projects LAC South Quad Complex LAC Learning Resource Center LAC Building A, Student Services Retrofit LAC Math Technology Building LAC Parking Structure LAC Infrastructure Improvements – Phase 3 PCC Central Plant PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Academic Building) PCC Building C Retrofit District Wide Building Needs Assessment Projects Toilet Improvement Projects Quick-Start Projects ADA Projects Lighting Projects Classroom Improvement Projects Recently Completed Facilities Improvements Important Ongoing Initiatives Planned Phasing of Future Projects Q & A 2

Completed Construction Projects Construction Complete Modern Facility with Computer Lab and Multimedia Stand alone Data Center. Provides District IT redundancy Bridge to building E Design elements move towards energy efficiencies Ribbon cutting held 9/17/08 PCC Learning Resource Center – Measure E

Completed Construction Projects Central Plant equipment, Public Safety, & Field House for Athletics Final FF&E installation underway Plant ready for operation and awaiting completion of LRC & SQC Construction Complete Anticipated startup 12/05/08 LAC Central Plant – Measure E

Current and Upcoming Construction Projects Construction approx. 89% Complete Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive office Multipurpose room State of the art Board Room Substantial completion anticipated 1/09 South Quad Complex – Measure E

Current and Upcoming Construction Projects Construction 91% Complete Adds 10,000 ASF to existing building Substantial Completion Anticipated January 2009 LAC/Learning Resource Center – Measure E

Current and Upcoming Construction Projects Design Development to be submitted this month Adds 4,000 ASF to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction 7/09 LAC Building A – Student Services Retrofit Measure E

Current and Upcoming Construction Projects Completed Schematic Design (June 2008) Currently in Design Development phase Will house Math and Culinary Arts instructional program as well as Reprographics Estimated start of construction 2011 LAC Math Technology Building – Measure E

Current and Upcoming Construction Projects Planning initiated for approximately 900 Vehicles To be procured under Design Build Delivery method To be located Southeast corner of Lot J adjacent to the Verizon building Photovoltaic Electrical Generation Array on top level of structure Anticipated start of construction 2009 LAC Parking Structure – Measure E Proposed Parking Structure Loc. Proposed Math Technology Bldg. Lot J Verizon Bldg.

Current and Upcoming Construction Projects LAC Infrastructure Improvements – Phase 3 Measure E 2008 Planning underway with engineers Completes chilled water lines to North side of campus Includes other major utility upgrades; Reclaimed Water, Domestic Water, Data, etc. Existing building HVAC systems to be upgraded in synch with infrastructure improvements Coordinated with modernization and quick start projects 10

Current and Upcoming Construction Projects Houses Central Plant equipment and Maintenance and Operations facility Construction Approximately 99% Complete Currently provides chilled water to the PCC LRC PCC Central Plant – Measure E

Current and Upcoming Construction Projects Modern facility houses Welding Department and other trade programs Construction is 45% complete Replaces existing antiquated structures New Northern face of the campus Completion anticipated summer 2009 PCC Industrial Technology Center Phase 1 Measure E

Current and Upcoming Construction Projects 90% construction documents submitted Swing space planning completed 9/2008, construction of swing space starts Spring 2009 Anticipated start of MDAB construction Summer 2009 To be completed in two phases PCC MDAB (Multi-Disciplinary Academic Building) Measure E

Current and Upcoming Construction Projects To be designed by Hill Partnership Architects Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices Swing space to be located on PCC Campus (TBD) To be completed concurrently with MDAB project Anticipated start of construction Spring 2010 PCC Building C Retrofit - Measure E

Current and Upcoming Construction Projects Toilet Improvement Projects Quick-Start Projects ADA Projects District Wide Building Needs Assessment Project Measure E

Current and Upcoming Construction Projects Lighting Projects Classroom Improvement Projects District Wide Building Needs Assessment Projects Measure E

Recently Completed Facilities Improvements 17 Replaced existing boilers, pumps, expansion tanks and common flue with new equipment via helicopter lift. A newly upgraded design reflecting a mechanical engineered system was installed improving the efficiency of the boilers. Completed 10/2008 Building B and E Boiler Replacement

Recently Completed Facilities Improvements 18 Additional Facilities Improvements LAC upgrades: Veterans Stadium scoreboard and PA system upgrade Building K upgrades – Exterior door paint, room 111 floor refinishing PCC upgrades: Building AA – Built wall for information desk, installed carpet, and power upgrades Building BB – Carpet and window blind installation Building CC – Installed fans in gym Building DD – Carpet and window blind installation Building EE – Window blind installation Building MM – Exterior paint, replaced doors and awnings, re- glazed windows, and replaced fascia boards

Important Ongoing Initiatives Master Landscape Project District Wide Energy Efficiency Improvements Electronic Marquee Signage Wayfaring and Building Signage Campus Lighting Improvements 19 LBCCD Coming Advancements

Planned Phasing of Future Projects 20 Currently Planned Schedule Parking Structure – Design/Build concept Anticipate awarding bid Spring 2009 Moving Warehouse from PCC to Alteon Building at LAC – TBD Moving LAC Building A into Swing Space – Spring 2009 Install portables at PCC for Swing Space – Spring 2009 LAC/PCC Building Needs Assessment Projects Bathroom Improvement Projects Quick-Start Projects Lighting Projects Classroom Improvement Projects Infrastructure Projects Submit FPP for M/N Project at LAC and MM Project at PCC and submit IPP for P Building at LAC Finalize Master Landscaping and Signage plans Marquee signage anticipated to be installed March 2009

Planned Phasing of Future Projects Begin construction of Building A at LAC Anticipating July 2009 start Begin construction of Buildings CC, DD, and EE at PCC Anticipating July/August 2009 start Begin Schematic Design for Buildings C and F at LAC Submit plans to DSA no later than March 2010 Begin Master Landscaping and Signage Initiatives Continue District Wide Energy Efficiency Improvements Phase IIA Lighting Upgrades, HVAC Upgrades, Control upgrades, Pool Cover, Roof replacement, etc Phase IIB Upcoming advancements include connecting current buildings to Central Plant infrastructure Currently Planned Schedule

Planned Phasing of Future Projects Anticipated Construction completion of Building A at LAC – January 2011 Submit plans to DSA for Math/Technology Building at LAC Move Buildings C and F programs into Swing Space (M/N Building) and begin construction – Spring 2011 Construction completion of Buildings CC, DD and EE at PCC Begin construction of Buildings AA and BB at PCC Anticipating January/February 2011 start Currently Planned Schedule

Planned Phasing of Future Projects Begin construction of Math/Technology Building at LAC Submit plans to DSA for M/N Building at LAC Anticipated Construction completion of Buildings C and F at LAC – December 2012 Anticipated Construction completion of Math/Technology Building at LAC – December 2012 Begin construction of Buildings M/N at LAC – January 2013 Anticipated Construction completion of Buildings AA and BB at PCC – June 2013 Currently Planned Schedule

QUESTIONS & ANSWERS EDUCATE ENGAGE EMPOWER 24