USDA - RURAL DEVELOPMENT

Slides:



Advertisements
Similar presentations
Project Estimates There are two types of estimates 1Partial Payment Estimate 2Final Payment Estimate.
Advertisements

Section 12 Under Construction. Your role as the owner What to expect at the preconstruction meeting Dos and Dont during construction How to handle change.
FAA Project - Bidding Phase FAA Recommends.. Consider how you would like to bid the project early on in the design. Due to possible budget constraints.
Metro Muncipal Agreement Program
Office of Purchasing and Contracts Research Funded Procurement Outreach Training Level III Procurements $50,000 and Above.
Construction Contracting
Roles & Responsibilities in Construction Management
Change Order Missouri Local Programs How to Complete a Change Order & Get it Approved.
VENDED PROGRAMS SFSP FY 05. What is a Food Service Management Company? Any organization (including commercial for profit companies, schools, or private.
New York City Department of Education Charter Matching – Facilities Upgrades/ Capital Improvements – FY 2014.
DISTRICT FIVE CONSTRUCTION CONTRACT ADMINISTRATION UPDATE TRAINING Submission of Working Schedule Specification SP A.
Chapter 15 Closing the Bid. Objectives Upon completion of this chapter, you will be able to: –Describe the estimate summary process –Describe items that.
M.A. Young and Company 1 This is a slide show Just click your mouse button on the bar to the right each time you want to move to the next slide. Use your.
DREDGING YOUR DOCKS 2013 Supported by: USACE Galveston District U. S. Coast Guard Sabine Neches Navigation District.
Chapter 12 Estimate Summaries and Bids. Bid Summaries The format of the summary depends for what the estimate is to be used. –Ordering materials –Calculating.
Contamination Cleanup Grant Program Implementation Workshop.
Page 1 No Sleight of Hand! Getting & Managing Grants Presented By Bethany Wolbrecht-Dunn, City of Shoreline.
With the Genesee County Road Commission By Fred Peivandi, P.E. And Ken Johnson, P.E. Local Road Funding.
CONSTRUCTION ADMINISTRATION Preconstruction Operations Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
14.21 Contract Closeout Procedure Update Notice of Completion, Release of Retention and Punchlist Resolution December 8, 2005.
Marcy Mealy Procurement Specialist CDBG Program
State Aid (SALT) prepares the Federal Agreements and the Amendments for  Force Account (FA)  Right of Way (ROW)  Preliminary Engineering (PE)  Construction.
Community Facility Loans/Grants Architect Flow Chart Owner has need for project. RD Area Office is contacted. RD visits project site and discusses project.
For West Virginia Department of Education DISCLAIMER This PowerPoint presentation serves only as a snapshot of purchasing regulations. Please visit the.
Project Close Out CTC-470.
Consolidated Equipment Financing Program (CEFP) Department of Financial Services Bureau of Accounting.
Conditions of the Contract for Construction
Washington University Medical Center Campus Renewal Project MANDATORY BILLING MEETING JUNE 12, 2015 Presented by:
Work Plan Development Steve Robinson Highway Utility Engineer, INDOT June 11, 2015.
Construction: Legal Issues. Legal Issues In the Bidding Process Timing of various activities has legal implications. During the bidding process: –A bid.
COMPLIANCE WITH GRANT IMPLEMENTATION PROCEDURES TxDot Grant Fund Project.
FHA 203K IS ONE LOAN FOR A PURCHASE OR REFINANCE, THAT ALSO FINANCES HOME IMPROVEMENTS. WHILE THE FHA 203K HAS MANY ADVANTAGES, ITS PRIMARY BENEFIT IS.
IDM Chapter 104 Utility Coordination Joe Gundersen Senior Utility Engineer, INDOT August 21, 2014.
The Tax Credit Process (Once credit has been awarded) Reservation and Carryover Gross Rent Floor Election Form Commitment 10% Certification Quarterly Progress.
Completing the State Aid Payment Request (SAPR). Tips Each spring check on the State Aid Finance web page for the current version of the State Aid Pay.
October 30, 2007 TSP Pre-Planning Meeting & Information.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
Measurement and Payment. Construction Progress Payments –Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed.
Genesee County Road Commission Fred Peivandi, P.E. County Highway Engineer MTPA July 15, 2011 TIP Project Administration.
CONSTRUCTION CONTRACTS DOCUEMENTS
MARCH 9, 2006 Boating Safety and Enforcement Grant Program Regulations Stakeholder Workshop Proposed Conceptual Regulations Department of Boating and Waterways.
Contract Training Class I
CONSTRUCTION ADMINISTRATION Measurement and Payment Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
Project Closeout Module #14 Prepared by Dr. Randy R. Rapp July 2005.
Managing Construction Chapter 16. Contractor Projects are overseen by a contractor who owns and operates a construction company. Projects are overseen.
San Marino Unified School District Contracts Presentation Presented by: Wesley Lee, Budget Analyst October 28, 2015.
1 CONTRACTING. 2 WHAT IS CONTRACTING ? CONTRACTING IS BASICALLY AN AGREEMENT BETWEEN TWO PARTIES, ONE CALLED THE CONTRACTING PARTY AND THE OTHER THE CONTRACTED.
Office of Procurement Services.  Vendor Application Website: 
Measurement and Payment
Sponsored Project Administration Fall 2012 CERTIFICATION PROGRAM Sponsored Project Lifecycle Introduction Overview Creating a Project Budget Compliance.
Introduction to Procurement for Public Housing Authorities Sealed Bids Unit 5.
Subcontractors and Suppliers Procedures for Receipt of Payment.
Emilio Pucillo Director, Division of Engineering Services, HHS Peyton Kuhlthau Acting Director, Division of Facilities & Loans, HHS.
Contract Compliance Training. Department Personnel Office of the General Counsel (OGC) Mario K. Castillo General Counsel John Guest Deputy General Counsel.
Presented by: Brienne Berscheid Assistant Vice President & Construction Escrow Underwriter Construction Escrow Documentation Requirements.
Heritage Trust Fund Grant Orientation Session. HTF Staff and Contact Information Katrina Ringler Grants Manager ext. 215
EQUIPMENT CONTRACT RUS FORM 395
Contract Compliance Training
CONTRACT ADMINISTRATION
Administration of a FIDIC Contract - Project Control
Construction Oversight
Managing Construction Projects
Safety Responsibilities
Contract Compliance Training
Overview of Stakeholders and Key Roles
Designers’ Manual Overview and Chapter Contents
Completing the State Aid Payment Request
Administrator of Construction Todd Wilson Senior Project Manager
Residential Placement Application 2011
Directed Change Constructive Change
Presentation transcript:

USDA - RURAL DEVELOPMENT USDA Rural Development NYS Engineers Training 6/14/2012 USDA - RURAL DEVELOPMENT Construction Bid, Contracts, Meetings, Change Orders, Closeout By Marcy A. Newman, PE, State Engineer

RURAL DEVELOPMENT REGULATIONS website http://www.rurdev.usda.gov/home.html

State Engineer’s Role in Construction Management Agency’s technical representative Approves and signs most paperwork Inspection (for RD purposes only) Makes sure documentation is done

State Engineer’s Role in Construction Management Why do we even do it? Protect the interest of the taxpayer Protect the interest of the Owner / borrower Aren’t we already paying someone for this?

Components Review bid and contracts Pre-construction meeting Monthly construction meetings Change orders Payments to contractor and engineer Inspections Pre-final, final and warranty inspections

Post-Bid/Pre-Award Submittal Bid Tabulation Engineer’s Recommendation for Award Contractor signed RD- Form 400-6 , AD-1048, and RD Instruction 1940-Q Exhibit A-1 As-bid Form E (budget form) RD MUST concur on bid BEFORE award

Post-Bid/Pre-Award Submittal Bid tab has all prices for all items for all contractors Look for “way out” prices; do these cause a concern? Engineer’s recommendation: after bid, defines which alternatives are being recommended, has total for each contract

Post-Bid/Pre-Award Submittal Are the 3 RD forms signed (not printed) RD 400-6 – Are both sides provided Form E – All as-bid prices agree with bids and recommendation Sufficient budget

Post-Bid/Pre-Award Submittal If everything is in order, RD will issue a letter to the Engineer, copy for Owner and Area Specialist, concurring on bid and authorizing award of contract

Post-Award/Pre-Construction Submittal Owner’s Board's resolution of award Notice of Award Executed agreement for each contract Contractor’s Certificate of Insurance Contractor’s executed Performance and Payment Bonds EJCDC C-610 (2010) and EJCDC C-615 (2010)

Post-Award/Pre-Construction Submittal Certificate of Owner's Attorney Resident Construction Inspector’s Resume Regulatory Agency Approval(s), Permits NYSDEC confirmation of SWPPP NOI RD State Engineer MUST concur on contract(s) prior to preconstruction meeting

Post-Award/Pre-Construction Submittal Board resolution dated AFTER RD bid concurrence Notice of Award dated AFTER resolution Contract dated AFTER Notice of Award date Bonds dated AFTER date of contract

Post-Award/Pre-Construction Submittal Bonds MUST be on 2010 forms Check contract dollar and word amounts Power of attorney complete / correct Original signatures Dates correct No modifications

Post-Award/Pre-Construction Submittal Read the RD contract document review letter to find out what to submit One copy of most things to Area Specialist and one copy to State Engineer RD doesn’t need all the copies of the contracts RD DOES need all copies of the GC-A

Post-Award/Pre-Construction Submittal If everything is in order, RD will issue a letter to the Engineer, copy for Owner and Area Specialist, concurring on contract(s) and authorizing coordination with Area Specialist to schedule preconstruction meeting Area Specialist has final say for precon

Pre-construction Meeting Led by Engineer Area Specialist and RD Inspector must attend Owner, Engineer, Contractor’s Rep (with signing authority) must attend Recommend Regulatory Agency & Utility companies also attend Sign in sheet for all attendees to sign

Pre-construction Meeting Engineer prepares and distributes minutes to all attendees and interested parties RD’s agenda to be read/discussed; may be merged with Engineer’s agenda Clearly describe expectations for project – timelines, payments, change orders, etc.

Pre-construction Meeting Minutes must document discussions and verbal agreements Notice to Proceed may not be issued until after pre-construction meeting and Area Specialist has all necessary paperwork

Monthly Progress Meetings Led by Engineer Attended by RD representative, Owner, Engineer, and contractor Updated progress schedule from contractor

USDA Rural Development NYS Engineers Training 6/14/2012 Payment Estimates If any payment is being requested, the following MUST be submitted as one package: FORM E Budget Sheet Tabulation sheets for each section of Form E All administrative and technical invoices Contractor’s partial pay application Engineer’s monthly report or meeting minutes (submitted within 5 days of meeting) By Marcy A. Newman, PE, State Engineer

Payment Estimates Submit no more frequently than monthly Submit six copies, all with original signatures First page must be on EJCDC C-620 (2010) Backup pages may be on Contractor’s or Engineer’s form as long as it’s in the same format

Payment Estimates Everything on the pay estimate form MUST be filled out Change orders NOT yet approved by RD shall NOT be reflected on the pay estimate Stored materials must have paid invoices (or invoices first month, paid invoices second month) and insurance form for those materials

Contract Change Orders Submit six copies, all with original signatures, to State Engineer or RD Construction Control Inspector (CCI) Provide a draft copy of the front sheet to the Area Specialist and RD CCI at the same time First page must be on EJCDC C-941 (2007) Everything on the change order form MUST be filled out

Change Orders Area Specialist State Engineer or CCI Confirms availability of funds State Engineer or CCI Reviews technical aspects Adequate documentation Verifies within scope Approves / Disapproves

Contract Change Orders Include ALL supporting information (labor and equipment hours, quantities, invoices/quotes for material prices, drawings/maps) Include justification (if Regulatory requirement, provide copy of letter) Engineer is responsible to provide copies of pay estimates and change orders to fiscal advisors

Contract Change Orders Recommend sending an electronic copy to RD before the change order is finalized / signed to verify its eligibility, completeness, etc.

Contract Change Orders ALL CHANGE ORDERS MUST BE APPROVED BY RD STATE ENGINEER OR CCI BEFORE CHANGE ORDER WORK MAY START AND BEFORE CHANGE ORDER MAY BE REFLECTED ON THE PAY ESTIMATE, NO EXCEPTIONS.

Contract Change Orders Final over/under change order is to zero out all quantities, including previous change order work. Final quantities must equal actual quantities installed. Final contract amount must equal work to date.

Inspection Services What to do/expect What not to do/expect

Roles of the Inspector Observe & report Know the contract Document Safety

Know the contract Know it inside and out Technical Timelines Requirements Approved Submittals Timelines Responsibilities Authorities Designated representatives

Observe Inspector is there whenever the contractor is working (unless part-time inspection has been approved by the Owner AND RD) Inspector is aware of what is going on Inspector is knowledgeable in type of construction Testing of materials

Report Daily logs Distribute to all interested parties Signature Who, what, when, where, how many, time Distribute to all interested parties Who How often Signature

Document Write everything down in an approved format Pictures, pictures, pictures!

Safety The Contractor is usually responsible for safety; check contract requirements Inspector should let appropriate people (Contractor and Owner) know immediately of safety concerns or violations

What RD Will Not Do Will not direct the contractor anything Will not act as Engineer Will not act as Owner

Costs of Inspection $50 - $100 per hour ($8K-$18K per month) 4-7% of estimated construction cost If contractor goes beyond allowed time, pays for additional inspection costs Budget enough money up front – should not use contingency funds

Common Problems to Avoid Inspector not on site Inspector and/or Owner directs contractor Inspector and/or Owner makes deals with contractor Owner / Engineer does not respond in a timely manner

Inspections – Substantial Completion Critical players Owner Consulting Engineer/Resident Inspector Contractor Funding agencies Regulatory agencies Discuss all conditions of construction and project closeout

Certificate of Substantial Completion Certificate of Substantial Completion (CSC) MUST be submitted within a reasonable time from date of substantial completion. CSC is effective on date shown, regardless of when signed. Area Specialist needs a copy with original signatures; State Engineer / CCI can receive it electronically

Inspections – Final Complete all project closeout items before acceptance If contractor not responsive, after giving notice owner should complete work with funds retained and send any remaining moneys to contractor Critical players Owner, Engineer/Resident Inspector, Contractor, Rural Development State Engineer or CCI

Contract Closeout Documents USDA Rural Development NYS Engineers Training 6/14/2012 Contract Closeout Documents Certificate of Substantial Completion Prefinal / final inspections with Owner, Engineer, Contractor, and RD Final over/under change order Contractor Release of Liens (AIA G706 and G706A Contractor Consent of Surety (AIA G707) By Marcy A. Newman, PE, State Engineer

Contract Closeout Documents Engineer’s certification to Regulatory Agency Regulatory Agency’s Approval Letter Engineer’s certification that construction is compliant with all NYS codes Warranty information (Area Specialist needs just a copy of the transmittal from these being sent to the Owner)

Contract Closeout Documents Owner’s Board’s resolution accepting project as complete and authorizing final payment Contractor’s final payment application Final Form E

Use of Remaining Funds Once all construction contracts are done (or nearly so), Owner/Engineer may submit a request for using remaining funds (if any) Eligible items are those necessary for operating, maintaining, and protecting the facilities, DISCUSSED IN THE PER

Use of Remaining Funds RD State Engineer must approve request for eligibility Once approved, Owner/Engineer must obtain three written quotes for each item Quotes and final cost estimate must be approved by RD

Warranty Inspection 11 months after substantial completion Owner, Engineer, and Contractor should attend RD State Engineer or CCI must attend Good idea to talk to operator Any concerns are to be addressed in writing to the contractor

Liquidated Damages Not a penalty Should be enforced uniformly Carefully consider amounts Interest Engineering/Inspection Administrative costs Other costs

Contractor Default Follow contract terms & notice requirements Check state laws that may apply Allow surety reasonable time to respond Notify state licensing agency and Treasury Department if surety is unresponsive Keep Owner’s attorney informed and verify that proper procedures are followed

Questions?