Essex County Transportation Services Department Essex County Highways 2014 Construction Program Peter Bziuk P. Eng. Manager Construction Services
Essex County Highways 2014 Construction Program Highlights –$25,018,00 expenditure level –Includes approx. $2,100,000 from 2013 –Rehabilitation Program –Capacity Improvement Program –CWATS Implementation
Rehabilitation Program 28 Planned Projects –5 Bridges ( 2 Construction, 3 Engineering) –6 Culverts ( 3 Construction, 3 Engineering ) –12 Roads –5 Maintenance
Capacity Improvement Program County is continuing a multi year capacity improvement program for the network County funding is being utilized, Senior level funding is being pursued 12 Planned Projects for 2014 –6 Construction, 6 Engineering
Essex County Highways Bridge Projects ($880,000) –2 - Structure Rehabilitations: CR Belle River CR Big Creek –3 - Engineering for 2015 construction: CR Big Creek CR Silver Creek CR Sucker Creek
Essex County Highways Culvert / Drainage ( $1,274,000 ) –CR Orton Drain culvert replacement –CR Ruscom River culvert replacement –CR Sullivan Creek culvert replacement –3 - Culvert Engineering projects for 2015 CR Lebo Creek CR 6-7 Sideroad Drain CR Gzowski Drain
Essex County Highways Road Projects ($4,147,000) –Recycling/Resurfacing: CR 8/ CR 11 - Tecumseh/Essex/Amherstburg CR 8/9 – LaSalle/Tecumseh/Amherstburg CR 9 - Amherstburg – 0.8 km CR 2 - Lakeshore – 2.9 km CR 7 - LaSalle – 3.5 km CR 13 - Essex – 2.2 km CR 14 - Leamington – 3.6 km CR 20 - Leamington – 0.9 km CR 23 - Essex – 1.4 km CR 25 - Lakeshore – 2.5 km CR 27 - Lakeshore – 2.3 km CR 34 – Kingsville/Leamington – 5.3 km
Essex County Highways Pavement Preservation ( $571,000 ) –Route and Seal – various locations –Surface Treatment – CR km –Micro Surfacing – CR50 – 6.8 km Bridge / Culvert Preservation ($405,000) –Various deck and expansion joint repairs –Various guiderail repairs / upgrades Estimated Quantities –26,790 tonnes of Hot Mix Asphalt –110,120 sm. of Pavement Recycling –18,400 tonnes of Granular A
Essex County Highways Capacity Projects ( $6,000,000) –CR 23/46 – Intersection Improvements – LS –CR 22 Phase 5 - Contract B – LS –CR 19/22 Improvements - Engineering –Various Connecting Link projects with Towns CR 22 – Lakeshore CR 6 – LaSalle CR 20 – Leamington
Essex County Highways EAs / Engineering in Process: –CR 19 / CR 22 Prelim. Design –CR 42 EA, City limit to CR 25 –Lauzon Parkway Extension – MTO/CoW /CoE –Active Transportation System ($52M) Annual $1,300,000
Essex County Highways Thank you for your interest, Thank you for your support in delivering our annual programs, Looking forward to working safely through the 2014 construction season.