SOUTHERN FRINGE DEVELOPMENTS –CONSTRUCTION MANAGEMENT STRATEGY JUNE 2011 Outline /Full Planning Permissions –provisions 1. Strategic Construction Environmental.

Slides:



Advertisements
Similar presentations
PLANNING AND COMPULSORY PURCHASE ACT 2004 by Alun Alesbury Three Years On 9 th March 2007.
Advertisements

March 2010 Plenary Session Slides for Governance Review IEEE 802 Presentation Submission Template (Rev. 9) Document Number: ec EC Date Submitted:
Metro Muncipal Agreement Program
Mayor and Council Public Hearing February 15, 2011 David Umling, City Planner.
DEL-71 Project at the US 36/SR37 Interchange Round Table Meeting Ferzan M. Ahmed, P.E.- District 6 Deputy Director Steve Fellenger, P.E. – Project Manager.
1100 CORNWALL INFO HANDOUT Bellingham Public Development Authority 1.
DustScan Ltd Planning Consent for Mineral Works Oliver Puddle 25 September 2013.
Providing affordable housing in the Southern Fringe John Cross Chief Executive bpha Southern Fringe Community Forum 18 th January 2012.
Project Update – MERC Waste Handling Agreement Recycling Agreement Purchase & Sale Agreement Municipal Officers Meeting November 19, 2013 City Hall, Council.
Building pride in Cumbria Do not use fonts other than Arial for your presentations The Cumbria Local Sites Partnership and NI 197 Richard Newman Environmental.
HR Essentials: Employment Contracts Presented by Kristin Ramsey Associate Director.
TurnKey Project Management Services Capabilities Briefing.
VNY Part 150 and Part 161: Status Update Presentation to the Board of Airport Commissioners February 1, 2010.
ALO Planning & Assurance Requirements
Lunenburg County Public Hearing January 29, 2013 Conditional Use Permit Lunenburg County Landfill Tracy Gee, County Administrator Frank F. Rennie, IV,
Lander Streets and Utilities 2015 Public Meeting No. 2 McDougall & Cliff Project Area.
Dillon and Christina Project Area Lander Streets and Utilities 2015 Public Meeting No. 2.
INSPECTION PENRICE ANGASTON QUARRY OPERATION Thursday 19 February 2009.
Japanese Experiences in Urbanization & Urban Planning System in Japan JICA Expert Kenichi WAKAMATSU 23 Aug.2001 Jakarta.
LIGHT RAIL PERMITTING ADVISORY COMMITTEE COMMITTEE MEETING Dec. 17, 2014|3:00PM -5:00PM | ROOM 1E-113.
On-Call Signal Contract Options for Discussion March 13, 2015 Cape Cod Joint Transportation Committee.
Equitas Academy Charter School Conditional Use Permit Review.
BUILDING SCHOOLS FOR THE FUTURE. Purpose of presentation Strategic Business Case – content and status Outline Business Case – progress report.
A Project Update for Trumpington Residents’ Association Great Kneighton.
PELLET PLANT LAY DOWN TRAFFIC MANAGEMENT POLICY COMMUNICATION.
OVERVIEW AND SCRUTINY COMMITTEE SCRUTINY OF 20MPH SPEED LIMITS Rupert Thacker Team Leader – Forward Planning and Rail Liaison.
Contractor Management and ISO 14001:2004
1 Municipal Ports Training Seminar: Board Governance Issues Prepared for DfT by Fisher Associates June 2007.
John Zammit-Haber National Grid
Report Tile Training & Management Assistance Branch UNITED STATES OFFICE OF PERSONNEL MANAGEMENT Project Kick-Off Meeting for with Project Manager Name,
Jilin Provincial Transport Scientific Research Institute & PEECE Pty Ltd Environmental Management Plans Presented by Phil Hawley & Steve O’Rourke P E E.
Development Contributions Planning Agreements Environmental Planning and Assessment Act 1979 Part 4, Division 6, Subdivision 2 lindsaytaylorlawyers Level.
Old Policy – which no one ever seem to have heard of.
THE SOUTH WESTERN RAILWAY Twickenham Station Platform Improvements 29 th January Twickenham Stadium.
Odour Code of Practice – An Update Martin Key Presentation to Scottish Noise and Nuisance Conference, 6 October 2006.
Health and Safety Policy
Synopsis EIA Purpose of EIA Origin Key Elements NGO Participation Content Analysis 1.
Scottish Experience in Procurement and EIA of Roads EIA and Early Market Involvement IAIA 2007.
TERRAMIN AUSTRALIA Limited Angas Zinc Project. Angas Zinc Project: traffic Raised as a concern through Stakeholder consultation process Dominant source.
Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009.
Briefing Session Temporary Traffic Arrangement at Campus Circuit For Site Formation Works at Area 39.
April 9, 2011 Mike Wieszchowski, P.E., PTOE Professional Traffic Operations Engineer Road Use Planning Guidelines to Protect Your Roadways.
Gulana Hajiyeva Environmental Specialist World Bank Moscow Safeguards Training, May 30 – June 1, 2012.
Construction Management Two 2014 Setting up Site Presenter Tony Bosnich Feb 2014.
The new VicSmart process and provisions. What is VicSmart? VicSmart is a fast planning permit process A decision is expected to be made in 10 days All.
Planning schemes Statutory documents under s.20(2) of LUPAA –outline policies and objectives –regulate or prohibit use or development of land –reserve.
Locally Administered Federal-Aid Project Initiation Workshop Prospectus Part 3 and NEPA Requirements Presenter: Howard Postovit; ODOT Region 5 Region Environmental.
Responding to Wind Farm Applications Ian Aikman Major Applications, Review & Enforcement Manager Scottish Borders Council.
UNIVERSITY OF DAR ES SALAAM t Selection and Employment of Consultants Negotiations with Consultants; Monitoring Performance of Consultants; Resolving Disputes.
PARCA Demonstration Data Information Flow Diagram Footnote:- No set timescales – timescales will be agreed by the Project Team Phase 0 Phase 1 Phase 2.
Corby North Eastern Sustainable Urban Extension. Corby North Eastern SUE Comprises 1.Priors Hall (Bela Partnership) 2.Weldon Park (Charles Church/Persimmon.
Introduction to Planning Sarah Platts. A plan-led system Two parts of planning: policy making and determination of planning applications; The planning.
Wellingborough SUE’s Julie Thomas Head of Planning and Local Development.
AES HUNTINGTON BEACH ENERGY PROJECT
Expenditure Authorization (EA) Training Scaling the Hurdles of EAs: Strategies and Solutions March 5, 2015.
Contestability in Connections Contestability Working Group Meeting NIE/SONI Joint Presentation 9 September
Desk Based Preconstruction – Planning
Health and Safety Policy
Administration of a FIDIC Contract - Project Control
Administration of a FIDIC Contract - Commencement Date to + 28 Days -
Cambourne to Cambridge Better Bus Journeys
Waste Planning Case Studies Exeter Energy from Waste Facility
Western Orbital Local Liaison Forum 11TH September 2017.
Meriden Estate Redevelopment
West Gate Tunnel – Air quality expert evidence
Work Hours: Monday – Saturday, 5:00 a.m. – 3:30 p.m.
Western Orbital: M11 J11 Park and Ride Provision
10 DAY PUBLIC NOTICE: Water Main
GCP Transport Update Meeting for: M11 J11 Park & Ride Engagement Group
Western Orbital.
Presentation transcript:

SOUTHERN FRINGE DEVELOPMENTS –CONSTRUCTION MANAGEMENT STRATEGY JUNE 2011 Outline /Full Planning Permissions –provisions 1. Strategic Construction Environmental Management Plans/Construction Management Plans (SCMP/CMP) and Detailed Construction Method Statements (DCMS) These have to include information on: Contractors access arrangements for vehicles, plant and personnel including location of construction traffic routes to and from the site; details of their signing, monitoring and enforcement measures. Details of haul routes within the site. Details of parking, turning, leading and unloading areas within the site and contractors compound details. Delivery times for construction purposes.

Dust management and wheel washing measures Noise and vibration method, monitoring and recording statements. Details of odour control systems. Maximum noise mitigation levels for construction equipment, plant and vehicles/maximum vibration levels Site lighting. Screening and hoarding details. (this list highlights the key elements but is not comprehensive).

Coordination/Liaison/Complaints Importantly they also have to include: Liaison, consultation and publicity arrangements, including dedicated points of contact. Complaints procedure, including complaints response procedures. Membership of the Considerate Contractors Scheme. The DCMS also has to include: consideration of sensitive receptors and prior notice and agreement procedures for works outside agreed limits.

2. Other relevant conditions: Hours of operation (Trumpington Meadows outline only) : No development or construction activity shall take place before 7.30am on weekdays and 8.00am on Saturdays nor after 6pm on weekdays and 1pm on Saturdays nor at any other time on Sundays or Bank Holidays, unless otherwise agreed in writing by the Local Planning Authority. Demolition, Construction Noise and Vibration Impact report (Clay Farm)

Status of the key individual Southern Fringe developments Trumpington Meadows outline CMP –condition 30 –required to be submitted prior to commencement of development (approved 30 March 2011) Hours of operation –condition 34 Clay Farm outline SCMP –condition 58 –to be submitted prior to commencement of development (approved for spine road only 23/11/2010. Main document still under consideration by City Council). DCMS – condition 59 - to be submitted prior to commencement of any reserved matters. Demolition, Construction Noise etc Impact Report – condition 60 -to be submitted prior to commencement of any reserved matters. Glebe Farm full permission SCMP –condition 35 –as above (approved 18/02/2011) DCMS –condition 36 – to be submitted prior to commencement of development of any phase (Phases 1-7 approved 18/02/2011). Amended documents expected shortly.

Contact details: See separate handout