PROGRESS REPORT As of September 22, 2011
I.Project StatusProject Status II.S-CurveS-Curve III.Revised Construction ScheduleRevised Construction Schedule IV.Manpower ProfileManpower Profile V.Monthly ReportMonthly Report VI.Progress Photos: – Earthworks Earthworks – Barge Pier Construction Barge Pier Construction – Seawall Construction Seawall Construction
* Based on approved Construction Schedule version September 1, SCHEDULEPLANNEDACTUALVARIANCE ORIGINAL64.38%29.16%-35.22% REVISED*18.47%29.16%10.69% (Original) Time Elapsed / Duration (Days): 169 / 306 = 55.23% (Revised) Time Elapsed / Duration (Days): 169 / 334 = 50.90%
ACTUAL, 3.79% (as of June 23, 2011)
BLUE SHEET COVERING THE BACKFILL MATERIALS STOCKPILING OF STONES SCREENING OF EXCAVATED MATERIALS
INSTALLED WIREMESH AND INITIAL SHOTCRETING OF WEATHERED SLOPE SURFACE COMPACTION FDT OF COMPACTED AREA
GEOTEXTILE LINER INSTALLATION DREDGING WORKS GEOTEXTILE LINER INSTALLATION AND STONE LAYING GEOTEXTILE LINER INSTALLATION
DREDGING FOR SEAWALL GEOTEXTILE LINER INSTALLATION STONES FILLING ( KG)
2-TON CONCRETE ARMOR INSTALLATION STONES FILLING ( KG)
2-TON CONCRETE ARMOR INSTALLATION HAULING OF PRE-CAST RC WALL
INSTALLATION OF PRE-CAST RC WALL LEAN CONCRETE POURING SURFACE PREPARATION PRIOR TO LEAN CONCRETE POURING INSTALLATION OF PRE-CAST RC WALL
CONSTRUCTION OF SEAWALL GAP CONCRETE CYLINDER SAMPLING CONSTRUCTION SEAWALL SEGMENT CONSTRUCTION OF SEAWALL GAP