2011 CONSTRUCTION PROJECTS
ProjectStatusCost Opinion Letting Schedule Anticipated Construction Schedule Jones Boulevard Improvements 2010Design Complete$3.37MBids due Feb. 16April – December 2011 North Liberty Dubuque Street TrailDesign Complete$850KBids due March 15Unknown - IaDOT will set this Penn Meadows Rain Gardens ParkingBid Complete$370KCompletedApril – June/July Penn Street ImprovementsDesign 90% Complete $1.8MBids due AprilApril - August Golfview Drive ImprovementsDesign Complete$1.34MBids due March+/-April - September 2011 PROJECT INFORMATION
Jones Boulevard Improvements 2010
North Liberty Dubuque Street Trail
North Liberty Dubuque Street Trail - South
North Liberty Dubuque Street Trail - North
Penn Meadows Rain Gardens Parking
Penn Street Improvements
Golfview Drive Improvements