DOE Review May, 2005 Steve Lewis

Slides:



Advertisements
Similar presentations
Steve Lewis XTOD October, 2005 UCRL-PRES LCLS Week/FAC October, 2005 Steve Lewis X-ray Transport, Optics,
Advertisements

1 John Arthur 1 FEH Status CXI Review June 3, 2009 FEH Layout, Status John Arthur – LCLS Expt’l Facilities Div June 3, 2009.
Richard M. Bionta XTOD July 19-21, 2005 UCRL-PRES-xxxxxx X Ray Diagnostics LCLS FAC Meeting Oct. 27, 2005.
John N. Galayda LCLS Facility Advisory November 11, LCLS Update November 11, 2008 Construction Status LCLS Instruments.
Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
John Arthur X-ray June 17, X-ray Overview XTOD current status XES current status Schedule to first experiments.
Steve Lewis Direct Imager 06 Dec EPICS Controls Steve Lewis 07 December 2007 LCLS Direct Imager Final Design Review.
John Arthur Photon Systems April 16, LCLS Photon Systems Status Technical status and accomplishments Response to.
X Ray Transport / Optics / Diagnostics Overview Richard M. Bionta Facility Advisory Committee Meeting April 29, 2004 Richard M. Bionta Facility Advisory.
John Arthur Photon October 18, 2005 LCLS Photon Systems Status John Arthur SLAC.
John Arthur Photon October 27, Photon Systems Overview John Arthur SLAC.
John Arthur X-Ray Optics October 12, 2004 X-Ray Prototype Optics Specifications John Arthur.
John Arthur Photon April 20, 2006 Photon Systems Update John Arthur SLAC Photon Systems Manager.
John Arthur X-Ray Endstation April 29, 2004 X-Ray Endstations Overview John Arthur.
Richard M. Bionta X-Ray Transport, Diagnostic, & Commissioning September 22, 2004 UCRL-PRES Two Problems... LCLS Diagnostics.
Steve Lewis XTOD 4-8 April, 2005 UCRL-PRES LCLS Week 4-8 April, 2005 Steve Lewis X-ray Transport, Optics, and Diagnostics:
Richard M. Bionta XTOD Layout and Diagnostic October 12-13, 2004 UCRL-PRES-XXXXX XTOD Layout and Diagnostic Systems Facility Advisory.
John Arthur X-ray April 20, 2006 X-Ray Beamline and Experiment Layout John Arthur LCLS Photon Systems Manager.
John Arthur Photon October 12, Photon Systems Update John Arthur SLAC 1.
Stefan Moeller XES Plan for FAC Review - April 20, 2006 X-Ray Endstation Systems (XES) Status and Plan for FY06 Stefan Moeller.
John Arthur Photon Systems April 7, 2005 Photon Systems Overview John Arthur.
Steve Lewis XTOD Controls FDR 13 March 2008 XTOD Vacuum Controls Final Design Review Steve Lewis/Keith Kishiyama 13 March 2008.
Lawrence Livermore National Laboratory This work performed under the auspices of the U.S. Department of Energy by Lawrence Livermore National Laboratory.
Donn H. McMahon XTOD Configuration October 24-26, 2005 UCRL-PRES X Ray Transport, Optics, and Diagnostics Overview FAC.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
Steve Lewis Gas Detector 6 December Instrumentation & Controls Steve Lewis Paul Pax Elden Ables 6 December 2006 LCLS Gas Detector.
Steve Lewis Gas Attenuator 11 December Instrumentation & Controls Steve Lewis 11 December 2006 LCLS Gas Attenuator Preliminary.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
LUSI Coordination with LCLS
AIP /02 P Bellomo - QE Magnet Power System Upgrade
Experimental Facilities Planning
EPICS Controls Steve Lewis 13 December 2007
LCLS Ultrafast Science Instruments
LCLS Timing Outline Scope The order of things
LCLS Event System - Software
Magnet PS Controls Hardware Status
LCLS Timing Outline Scope The order of things
Stefan Moeller – XES Manager May 14, 2009
John N. Galayda – Director of LCLS Construction March 30, 2009
Installation of Photon Beam Transport to FEH
Electron Beam Systems ETC and Methodology
X-Ray Endstation Design & Management/Commissioning
X-Ray Transport, Optics, and Diagnostics WBS Alan J
X-Ray Endstations Update
LUSI Controls and Data Systems W.B.S. 1.6
Overview Pre-Beam Checkouts
John Arthur – LCLS Experimental Operations
FEE Diagnostics and Commissioning
NEH - Status Stefan Moeller.
The Transition to User Operations
Coherent X-ray Imaging Instrument WBS 1.3
Conventional Facilities Status
LCLS Personnel Protection System and Beam Containment System
LCLS Week 4-8 April, 2005 Steve Lewis
LTU/Undulator Installation Status
X-ray Correlation Spectroscopy Instrument
DOE Review 7-9 February, 2006 Steve Lewis
Control System Overview Hamid Shoaee LCLS Control System Manager
Photon Systems Breakout Lehman Review July 11, 2007
XTOD Layout and Diagnostic Systems
Linac Coherent Light Source Project Update
X-Ray Endstation Design & Management/Commissioning
LCLS Lehman Review February 7-9, 2005
LCLS XTOD Mechanical and Vacuum Systems; Gas Attenuator
Lehman Review: XTOD Beam Transport
X-Ray Endstation Systems (XES) 2006 Schedule
LCLS Control System Personnel Linac & BC2 Controls progress
LCLS Photon Systems Overview
LUSI Controls and Data Systems W.B.S. 1.6
LCLS Lehman Review February 7-9, 2005
Presentation transcript:

DOE Review 10-12 May, 2005 Steve Lewis X-ray Transport, Optics, and Diagnostics: Controls Status DOE Review 10-12 May, 2005 Steve Lewis

Layout Each hutch is 10 m long FEH NEH FEE Tunnel Experiments: Atomic Physics Front End Enclosure Fast Close Valve Slits Attenuators Shielding Experiments Optics Structual Bio Nano-scale Femtochem FEL Measurements & Experiments: Low Power Imaging High Power Imaging Spectrometer Calorimeter Flipper Mirror Experiments: Optics Warm Dense Matter

Major Effort Areas Getting an accurate count of all devices Naming devices (and extending SLC convention) Aligning XTOD controls devices with LCLS global standards Reviewing cost+schedule Installing EPICS at LLNL

Counting Devices Layout and instrument list has changed since original design Original design was not “EPICS-aware” LCLS-wide standards are (just) now being set All of above are basis for accurate cost+schedule

Will conform to (and extend) SLC conventions Naming Devices Will conform to (and extend) SLC conventions Especially for “SLC-aware” devices Allows uniform notation on spread-sheets, one-line diagrams, as well as EPICS configuration Implicitly forces accurate counting

Safety must be engineered in LCLS Global Standards Safety must be engineered in Commerical products are one way to ensure this (UL, CE, …) Initial Q/A will take place at LLNL for many items

Reviewing Cost+Schedule Possible additions based on quick-look: I/O hardware and cabling costs Approx $200K to be added for master PLCs Configuring+Commissioning Effort Approx 1500 hours to be added for Tunnel Vacuum Licenses (PLC…)

Borrow small VME crate, CPU, EVR and EVG from SLAC EPICS at LLNL Set up a server RH Linux or MacOS X? Keep CVS at SLAC Intellectual property issue? Borrow small VME crate, CPU, EVR and EVG from SLAC Gas Attenuator prototype is first application First use of PLC Will train LLNL staff