7E: Tower test plans GLAST Large Area Telescope: Tracker Subsystem

Slides:



Advertisements
Similar presentations
Tracker Subsystem1 GLAST LAT Project FM8/14 PSR, Oct. 5, 2005 GLAST LAT Tracker Towers 8/14 Pre-Ship Review INFN-Pisa.
Advertisements

GLAST LAT ProjectMarch 24, 2003 HPS Tracker Peer Review, WBS Section 2-D 1 GLAST Large Area Telescope: Tracker Subsystem WBS Structural.
GLAST LAT ProjectPeer Review, March 24-25, D 1 Gamma-ray Large Area Space Telescope 7D: Tray test plans GLAST Large Area Telescope: GLAST Large Area.
GLAST LAT Project Gamma-ray Large Area Space Telescope Status of the EM Thermal Tests GLAST Large Area Telescope: GLAST Large Area Telescope: Tracker Subsystem.
GLAST LAT ProjectGSFC, October 2003 LAT-PR-0XXXX 1 Gamma-ray Large Area Space Telescope Status of the EM Vib Tests GLAST Large Area Telescope: GLAST Large.
GLAST LAT ProjectMarch 24, A Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS A: Tracker Test Plan Overview.
GLAST LAT ProjectMonthly Review, September 1, Tracker SubsystemR. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S August Status Meeting.
GLAST LAT ProjectOctober 14, 2002 Tracker, WBS GLAST Large Area Telescope: Tracker Subsystem WBS Engineering Meeting Tracker Engineering-Model.
Tracker Subsystem1 GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 GLAST LAT Tracker Tower7/9 Pre-Ship Review INFN-Pisa.
Tracker Subsystem1 GLAST LAT Project FM4/5 PSR, May 31, 2005 GLAST LAT Tracker Tower-4/5 Pre-Ship Review INFN-Pisa.
GLAST LAT Project4 April 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
Page 1 GLAST LAT ProjectAugust 30, 2004 GLAST Large Area Telescope: LAT Accelerometer and Thermal Instrumentation Review Presented by Leonard Lee John.
GLAST LAT ProjectPeer Review, March 24-25, E2 1 Gamma-ray Large Area Space Telescope 7E2: EM test plans GLAST Large Area Telescope: GLAST Large Area.
FNAL Meeting, July 2006 Basti, Bedeschi, Raffaelli, INFN-Pisa 1 ILC cryomodule mechanical work at INFN-Pisa  Ongoing work  Near term future  Manpower.
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 6.0 Subsystem Verif. Test Plan 1 GLAST Large Area.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
GLAST LAT ProjectMarch 24, D Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS D: Composite Panel Fabrication.
Tracker Production Overview Readout Cables UCSC, SLAC (Parlex) SSD Procurement, Testing SLAC,Japan, Italy (HPK) Electronics Fabrication, burn-in, & Test.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW Boom PER 30 June RBSP EFW Spin Plane Booms Greg Dalton Space Sciences.
LAT-PR Section 55-1 GLAST LAT ProjectMechanical Design Integration Peer Review, March 2003 Mechanical Design Integration Peer Review, March 2003.
GLAST LAT ProjectMarch 24, A Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS A: Engineering Model Tower.
C osmic R Ay T elescope for the E ffects of R adiation CRaTER Pre-Environmental Review (I-PER) Environmental Test Planing Bob Goeke September 10-11, 2008.
GLAST LAT ProjectMarch 24, G Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS G: Tower module assembly A.
GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 8 of 12 Thermal Vacuum Test 1 GLAST Large Area Telescope LAT Pre-Shipment Review.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
THEMIS IDPU PDR I&T REQUIREMENTS- 1 UCB, October 16, 2003 I&T REQUIREMENTS Ellen Taylor University of California - Berkeley.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
LAT Design Integration and Analysis1 GLAST LAT Project24 May 2005 LAT Monthly Status Review 24 May 2005 Design Integration and Analysis LAT Monthly Status.
GLAST LAT ProjectMarch 24, A Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS A: Parts and Materials Procurement.
LAT MPSRLAT Structural Analysis-1 GLAST LAT ProjectNov-04 Structural Analysis: Completed Tasks LAT System Level –LAT Environmental TIM Support A success.
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 11 of 12 Thermal Vacuum Test 1 GLAST Large Area Telescope LAT Pre-Shipment Review.
GLAST Large Area Telescope:
EMI/EMC GLAST Large Area Telescope LAT Pre-Shipment Review
Solar Probe Plus FIELDS V1234 Mechanical Pre-Ship Review May 26, 2017
Solar Probe Plus FIELDS V1234 Mechanical Pre-Ship Review May 26, 2017
Gayle K. Martin November 14, 2016
General overview Place : Institue of Space Astrophysic (IAS, Orsay)
GLAST Large Area Telescope:
Optical Blocking Filter and Dust-proof Film for HXMT
CRaTER Pre-Environmental Review (I-PER) Engineering Requirements/Design Updates Bob Goeke September 10-11, 2007.
GLAST Large Area Telescope:
Mechanical Integration
THEMIS INSTRUMENT SUITE
FIELDS SCM Thermal iPER
LAT Requirements Verification in TVAC
GLAST Large Area Telescope:
GLAST LAT System Engineering
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope
GLAST Large Area Telescope: Cost/Schedule Review September 1, 2005
Integration and Test Organization Chart
Thermal Performance of the GLAST LAT Tracker
Thermal Vacuum Test: Plans and Procedures
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Integration and Test Organization Chart
GLAST Large Area Telescope:
The encapsulation problem of the LAT heavy trays
GLAST Large Area Telescope:
GLAST Large Area Telescope
GLAST Large Area Telescope:
GLAST LAT System Engineering
Introduction and Overview
GLAST Large Area Telescope:
Presentation transcript:

7E: Tower test plans GLAST Large Area Telescope: Tracker Subsystem Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Tracker Subsystem 7E: Tower test plans Nicola Mazziotta University and INFN Bari - Italy mazziotta@ba.infn.it

Outline Overview Tower vib plan Tower thermal plan Test schedule Summary Reference LAT Documents: LAT-MD-00408, LAT Instrument Performance Verification Plan LAT-SS-00788, LAT Environmental Specification LAT-TD-01005, Thermal Test Results on Thick Converter Mock-up Trays LAT-TD-01249, Thermal Test Results for Pre-Engineering Model Trays LAT-PS-01584, LAT Tracker Tray SSD Ladder Panel Assembly Procedure LAT-TD-00155, Tower Vibration Test Plan LAT-TD-01840, Tower Thermal Test Plan

Tower matrix Item Quantity High freq sine Sweep 20-2000 Hz Random Vibration White noise Low freq sine Sweep 5-50 Hz Functional Thermal Vacuum Test site Tower A (Qual) 1 X,Y,Z axis Qual  Italy Tower B (Spare) Acc 1-16 Towers (Flight) 16

Qual test flow (LAT-MD-408)

Acc test flow (LAT-MD-408)

Low frequency sine sweep Tower vib levels Low frequency sine sweep White Noise Frequency (Hz) ASD WN Level(g2/Hz) Overall grms Duration (min) 20 ÷ 2000 10-4 0.45 1 Random vibration Frequency (Hz) ASD Acceptance Level (g2/Hz) ASD Qualification 20 0.01 0.02 20-50 +5.9 dB/oct 50-800 0.06 0.12 800-2000 -5.9 dB/oct 2000 Overall 8.7 grms 12.3 grms Duration 1 min/axis 2 min/axis High frequency sine sweep Frequency range 20  2000 Hz Sweep rate 2 oct/min Target Amplitude 0.5 g0-pk

Tower vib set up Accelerometers set up (TBR): 3 axial on the shaker table (control accelerometer) 3 axial on the center of the bottom tray lower surface 3 axial on the center of the top tray upper surface 3 axial accelerometer +X sidewall center of the thermal boss tray number 12; 3 axial accelerometer +Y sidewall near the center of the tray number 10; 3 axial accelerometer +Y sidewall center of the thermal boss of the tray number 1; 3 axial accelerometer +Y sidewall center of the thermal boss of the tray number 19; 3 axial accelerometer -X sidewall center of the thermal boss of the tray number 10; 3 axial accelerometer -Y sidewall near the center of the tray number 10, on the center plane;

Tower A vib sequence For each axis Step Description Test Level LPT 1 LPT 1 Mounting 2 Fixture calibration High frequency sine sweep 0.5 g0-pk 3 Normal mode search 4 Pre-random vibration White noise 0.45 grms 5 Random vibration -6 dB Qual 6 Post/Pre-random vibration 7 -3 dB Qual 8 9 0 dB Qual 10 Post-random vibration 11 Normal mode check 12 13 Low frequency test Low frequency sine sweep Qual 14 Dismounting 15 16 Test completion

B&Flight Towers vib sequence For each axis Step Description Test Level LPT 1 Mounting 2 Fixture calibration High frequency sine sweep 0.5 g 0-pk 3 Normal mode search 0.5 g0-pk 4 Pre-random vibration White noise 0.45 grms 5 Random vibration -6 dB Acc 6 Post/Pre-random vibration 7 -3 dB Acc 8 9 0 dB Acc 10 Post-random vibration 11 Normal mode check 12 Dismounting 13 14 Test completion

Tower A thermal levels 8 Cycles Thermal-Vacuum cycling/Qual level Ranges -30°C  50°C # of cycles 8 (12) Temp. rate 20°C/hr Pressure 10-5 Torr Duration @ extreme 12 hr Total Duration 256 (384) hr + stabilization @ T room 8 Cycles (Tab. 2 LAT-MD-408)

B&Flight Towers thermal levels Thermal-Vacuum cycling/Acc level Ranges -20°C  35°C # of cycles 4 Temp. rate 20°C/hr Pressure 10-5 Torr Duration @ extreme 4 hr Total Duration 54 hr + stabilization @ T room

Tower covered with a thermal blanket during T-V cycles. Tower thermal set up Tower covered with a thermal blanket during T-V cycles. The tower has a large number of thermocouples in the read out cables that can be acquired by using the TKR DAQ system. Additional thermocouples (TBR): +Y sidewall center of the thermal boss of the tray number 1; +X sidewall center of the of the tray number 1, on the center plane; +Y sidewall center of the thermal boss of the tray number 19; +X sidewall center of the of the tray number 19, on the center plane; -X sidewall center of the thermal boss of the tray number 10; -Y sidewall near the center of the tray number 10, on the center plane The temperature control point for the cold part of the cycle will be the coldest thermocouple, while the control point for the hot part of the cycle will be the hottest one.

Tower thermal sequence Step Description Level CPT 1 (Strain gauges and) Thermocouple set up 2 Chamber set up 3 (Strain gauges calibration) 4 Thermal vacuum cycles  CPT/LPT Qualification/Acceptance CPT/LPT 5 Dismounting 6 7 Test completion

Summary Work in progress: Number of thermal qualification cycles LPT definition CPT definition Use of strain gauges for T-V test ???