Material Tour of Boiler - Catastrophic Failures of Boiler Components

Slides:



Advertisements
Similar presentations
Power Plant Engineering
Advertisements

Fired And Unfired Pressure Vessels
Mr.B.L.Prabhu, Safety Officer Boiler Safety Measures.
FOCUS POINTS FOR SITES TO IMPLEMENT TOWARDS BOILER TUBE FAILURES PREVENTION (Actionable points for site based on failure analysis ) SCOPE: BOILER PRESSURE.
East Carolina University Compressed Gas Safety Training Program
MNM Fatal Falling Material Accident Falling Material Accident August 17, 2012 (Florida) August 17, 2012 (Florida) Victim Recovered September 4,
1 Low Conductivity Water (LCW) Connection Training Environmental Energy Technologies Division Safety Topic January 9, 2012.
Material Tour of Boiler - Catastrophic Failures of Boiler Components Presented by George W Galanes, P.E. Metallurgical Consulting Engineer Diamond Technical.
Test to Failure of 3/8-Inch Tube Ferrule Connections in an Effort to Determine the Shear Strength of a Varying Number of Threads Engaged P.O. Box
MATERIALS TESTING.
BMFB 4283 NDT & FAILURE ANALYSIS
Refuge Alternative Examinations, Approvals, and Refits Stakeholder Meeting-MSHA HQ June 27, 2012.
2013 California State Emphasis Program.  During a 4 Crude Unit meeting with regulators Chevron personnel admitted they were “thinking about” clamping.
Gas Transmission Pipelines
1 Oil oxidation impact on Feed pump and turbine performance Presenter: Walter Bischoff.
Stainless Steels Stainless steels are iron base alloys that contain a minimum of approximately 12% Cr, the amount needed to prevent the formation of rust.
ERT 312 SAFETY & LOSS PREVENTION IN BIOPROCESS ACCIDENT INVESTIGATION Prepared by: Miss Hairul Nazirah Abdul Halim.
Learning Objectives  Recognize the need for an investigation  Investigate the scene of the accident  Interview victims & witnesses  Distinguish.
PRESENTED BY ABC TEXAS GULF COAST CHAPTER
Lab 6B -Fracture Toughness and Fracture Toughness-limited Design Big bang for the buck!
Process Hazard Analysis DOW Fire & Explosion Index ChE 258 Chemical Process Safety University of Missouri - Rolla.
Incident Reporting Procedure
ACCIDENT INVESTIGATION. Accident Investigation An Employer should immediately investigate the cause of any accident or other incident that : çresulted.
Introduction to Equipment
Process Safety Management
FSRUG Presentation – January 2014 Tennessee Valley Authority Browns Ferry Nuclear Plant Unit 3 Reactor Feed Water (FW) Clean Up Piping Break.
1. Objectives  Describe the responsibilities and procedures for reporting and investigating ◦ incidents / near-miss incidents ◦ spills, releases, ◦ injuries,
Part 3.3 Production Safety. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Understand safety.
FAILURE ANALYSIS Sources of failure - - Sources of failure - - Material Related Failures. Deficiency in Design. Service Related Failures. Environmental.
High strength materials are being increasingly used in designing critical components to save weight or meet difficult service conditions. Unfortunately.
STRUCTURES Outcome 3 Gary Plimer 2008 MUSSELBURGH GRAMMAR SCHOOL.
EXAMPLE FEP REPORT – Flow Erosion Assessment Program Investigation Report – May 2009 EIMAGING POWER GENERATION.
Explosion An explosion is a rapid expansion of gases resulting in a rapid moving pressure or shock wave. The expansion can be mechanical or it can be.
Destructive Examination & Testing 2 Destructive Examination Destructive Examination renders the weld or material unfit for further service.
Significant Potential Incident Unauthorized Weld on Pressurized Water Line Timmins, Ontario, Canada October 17, 2011.
3.4.3 Student Book © 2004 Propane Education & Research CouncilPage Bulk Plant Emergency Shutdown Equipment and Periodic Examination Methods One.
MECHANICAL TESTING.
Welding Inspection and Metallurgy
1 Full document available on EDMS Metallurgical qualification of AISI 316L TIG welded tubes Summery - Richard French.
06/01/20161 Benny Hoff TÜV NORD Sweden AB AFS 2002:1 Use of pressure equipment.
3.1.8 Student Book © 2004 Propane Education & Research CouncilPage Identifying Procedures for Conducting Container Vapor Flaring Operations Before.
This presentation is for illustrative and general educational purposes only and is not intended to substitute for the official MSHA Investigation Report.
IAEA International Atomic Energy Agency AGEING MANAGEMENT ASSESSMENT Module 9 Session 9 Resource document: AMAT Guidelines, Reference document for Ageing.
Teknologi Pusat Data 12 Data Center Site Infrastructure Tier Standard: Topology Ida Nurhaida, ST., MT. FASILKOM Teknik Informatika.
SAFETY TALK BP AMOCO - TEXAS CITY OPERATIONS DATE: 19 APRIL 1999 LOCATION: OSP, F-301ARV.
EFFECTIVE ACCIDENT/INCIDENT INVESTIGATION 15 FEBRUARY 2013 PHILIPPINE ASSOCIATION OF SAFETY ENGINEERS -QATAR- -QATAR- COMMITTEE ON SAFETY EDUCATION 2013.
Accident analysis One-hour training.
Version 1.0, May 2015 BASIC PROFESSIONAL TRAINING COURSE Module XX Regulatory control Case Study This material was prepared by the IAEA and co-funded by.
Process Safety Advisory on Boiler Incidents
Coating Defects and Failures
Incident Reporting And Investigation Program
NERC Published Lessons Learned
CASE STUDY ON BOILER ACCIDENT
Compressor Safety Practices
F-101 CATALYSTS TUBE WELD JOINT FAILURE
THE PROCESS OF CRACK INITIATION AND ITS PROPAGATION
Teknologi Las Kapal Destructive Testing.
관상동맥(Coronary artery )
ACCIDENT INVESTIGATION PRESENTATION
One Will Die: The John Martin Story Applying Action Based Safety
East Carolina University Compressed Gas Safety Training Program
Incident Reporting And Investigation Program
MATERIALS TESTING. Why are metals tested ? Ensure quality Test properties Prevent failure in use Make informed choices in using materials Factor of Safety.
Power Plant Engineering. Boilers Boilers Boiler is an apparatus to produce steam. Thermal energy released by combustion of fuel is used to make steam.
1/18/2019 6:28 AM C h a p t e r 8 Failure Dr. Mohammad Abuhaiba, PE.
Rajan Bhandari Senior Lecturer
LOP Flare Pilot Outage Shell Martinez Refinery 7/6/18
BASIC PROFESSIONAL TRAINING COURSE Module XX Regulatory control Case Study Version 1.0, May 2015 This material was prepared by the IAEA and.
Boiler Room LOG Sheets: Interpreting the Records
Gas Transmission Pipelines
Presentation transcript:

Material Tour of Boiler - Catastrophic Failures of Boiler Components Presented by George W Galanes, P.E. Metallurgical Consulting Engineer Diamond Technical Services, Inc

Introduction Discuss two rather important and recent failures of high temperature and high pressure boiler components Both failures were catastrophic and resulted in loss of equipment One failure caused injury to plant personnel What happened?

Primary Superheater Link Pipe Ruptures

Typical Boiler Layout Pri SH Inlet Feeder Pipes (30 total) (136 sweeps) 6.625 “ O.D. x 0.935 “ minimum wall thickness of SA335 P1 material (carbon – moly steel). Design pressure is 4,180 psig and 830 deg. F.

History Repeats….. ▪ 1982: - 5” long tight through wall crack found during hydro during forced outage - Boat sample analyzed by internal lab: “contained many sulfide inclusions”, no Charpy testing completed, no graphitization, inconclusive failure mechanism. - Repaired: grind / re-weld. ▪ 1990: - Through wall crack found during hydro during a forced outage. - No metallurgical analysis completed ▪ 2004: - Through wall crack / on-line leak - Replaced elbow with upgraded P22 material during a scheduled 11 day outage. ▪ 2009: - Multiple elbow failure event during unit shut-down. - Metallurgical Analysis performed however results did not detect grain boundary graphitization because of unfamiliarity with the damage mechanism. ▪ 2011: - Single elbow failure of a previously repaired elbow during steady state conditions. - Detailed seq. of events on subsequent slides.

What happened on that day Sequence Of Events: Thursday 2/10/11, Primary Superheater inlet pipe ruptured @ 7:37 a.m. (during normal AM load increase (5 mw/min) at 606 mwg) INJURIES Two Plant employees and one contractor employee were air lifted to a burn center All with 2nd degree burns; released following day. Two Plant employees taken by ambulance to regional Medical Center Both released same day. One employee treated for dust inhalation (Released same day)

Type of Rupture

Teamwork A root cause analysis (RCA) team was assembled. Team members consisted of operations personnel, plant personnel, and outside consultants to ensure a methodical review of events and known process for establishing causal factors. In addition, fracture mechanics and boiler flow modeling were used to assist in RCA. Outside entity was the lead in conducting the RCA to ensure independent technical oversight. The failed sweep was sent to a metallurgical laboratory for comprehensive metallurgical analysis; Chemical Analysis Tensile testing Hardness Testing Impact testing Metallographic examination

Look Closely It was determined that the cause of failure in the primary superheater (PSH) inlet sweep was a damage mechanism confirmed to be grain boundary graphitization.

What Happened…. This type of damage mechanism is time dependent, meaning as the Grade P1 remained in elevated temperature service, the pipe would exhibit continued significant loss in toughness and ultimately fail catastrophically (no leak before break) in service. The failure initiated and propagated from the OD surface of the bend extrados. This location would have been exposed to the highest forming strains. Bulk hardness testing confirmed the extrados as having the highest hardness( approximately 200 HV in comparison to straight sections at 165 HV). Loss of toughness and significantly reduced elongation values were confirmed in the formed sweeps versus straight sections of Grade P1 piping based on extensive mechanical property testing.

Summary Grain boundary graphitization was confined to formed bends did not appear to have been thermally treated after forming. Because the grain boundary graphitization damage mechanism is not well understood or reported in literature it was more difficult to quantify severity of damage in comparison to the more traditional form of graphitization damage (graphite nodules). Fortunately, after extensive sampling of sweeps and straight pipe sections of known Grade P1 PSH pipe material, there was no grain boundary graphitization observed in straight sections of Grade P1 pipe because these pipe spools contained no residual forming strains.

Prevention………….. Based on the findings from the Unit PSH sweeps, a review was was performed to determine the extent of Grade P1 pipe material installed in this boiler and in a second boiler (sister unit). Carbon steel piping was also sampled as a precaution. No grain boundary graphitization damage was detected for carbon steel piping. In addition, a search of Grade P1 material was expanded to include the remaining coal-fired units for this client. No other Grade P1 piping was installed in the boiler proper. After careful review of metallurgical test results for sampled Grade P1 pipe material locations in both boilers, it was recommended to replace the original Grade P1 sweeps with SA 335 Grade P22 material and monitor the remaining P1 piping until full replacement using SA 335 Grade P22.

Failure #2 Warm-Up Line for an HRSG during start-up

Warm-Up Line Failure Investigation Activities Associated with Root Cause Analysis and metallurgical failure analysis; Mapping of the failed warm-up line Removal and preservation of failed segments Engineering Review of operating information Engineering Review of the design basis of the warm-up line Selection of a metallurgical lab to perform laboratory analysis in support of the failure investigation.

Failed Warm-up Line

More Pictures…

And more pictures..

Warm-up Line ID Surface

View of the ID pipe surface

Local thinning from corrosion

Results Failure of the warm-up line internal wastage that weakened the pipe resulting in catastrophic rupture in service at multiple locations within the line. The internal wastage corrosion from either stagnant or pooled condensate during off-line conditions from exposure to air atmosphere. There was no evidence of internal erosion or erosion/corrosion that contributed to the failure.

RCA Causal Factors Reverted control logic for the 12” Fischer regulating valve that exposed the weakened line to internal operating pressure near main steam pressure conditions. However, it is important to note that if the warm-up line did not sustain internal corrosion it would have safely accommodated main steam internal pressure based on original design (ASME B31.3).   Lack of urgency in reviewing the previous pipe inspection results from February, 2011. The pipe inspection results indicated excessive local wall thinning that if given proper review would have resulted in immediate corrective actions – repair or replace of severely thinned pipe sections prior to return to service. The need to have a sufficient number of drains to ensure proper drainage of this warm-up line to prevent stagnant or pooling of condensate when the line is valved out.

Prevention Corrective Actions Develop inspection plans for the warm-up line and other high energy steam lines. The inspection program results should be reviewed independently of site personnel to ensure no gaps or missed opportunities for corrective actions. Survey the replacement warm-up line and other lines that are used on an infrequent basis to determine the need for drains or drain pots to avoid having similar internal corrosion problems.

Questions?