Electric Power Generation ECE 4501 Electric Power Generation
BOSWELL ENERGY CTR Minnesota Power’s Primay Generation Ceneter (an Allete Company!) Unit 1, 70 megawatts, operational in 1958. Unit 2, 70 megawatts, operational in 1960. Unit 3, 350 megawatts, operational in 1973. Unit 4, 535 megawatts, operational in 1980.
Boswell from the Air
Power Station
Boiler
Steam Turbine/Generator
Turbine
Synchronous Generator
Stator – Liquid Cooled Windings
Step-Up Transformer
Transmission Line
Substation
Inside the Butler Building
Metal Enclosed Switchgear