Security of Payment and Adjudication in Hong Kong

Slides:



Advertisements
Similar presentations
A GIA is a contract between a surety company and a contractor (or subcontractor)/principal. A GIA is a standard, typical document in the construction.
Advertisements

Presented by: Fouad Al-Malazi ID No.: Managing Construction Contracts By Robert D. Gilbreath Chapter 1 CONSTRUCTION CONTRACTS: Roles and Relationships.
The First-tier Tribunal (Property Chamber) Nicholas Kissen Thomas Frith Islington Leaseholders Association 12 th June 2013.
10 th Adjudication Update Seminar ADJUDICATION FOLLOWING THE LATHAM REVIEW Graham Watts Chief Executive Construction Industry Council Chairman,
Security of Payment workshop Andrew Robertson Important Disclaimer: The material contained in this publication is comment of a general nature only and.
COMMENCEMENT OF ARBITRATION PROFESSOR JOSEPH MBADUGHA.
Cost Effective Dispute Resolution Alana Dowley Legal Services Director Contract Intelligence Pty Ltd.
East Anglia Branch Annual Seminar Downing College, Cambridge 14 June 2013 The Man* in the Middle *The masculine gender shall include the feminine.
WIPO ARBITRATION AND MEDIATION CENTER 1 Ignacio de Castro WIPO Arbitration and Mediation Center February, 2008 Arbitration of Intellectual.
Reform of Arbitration Law The New Arbitration Ordinance (Chapter 609) # Frank Poon Solicitor General (Acting) Department of Justice Hong Kong SAR.
Time for a new standard - AS General Conditions of Contract
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT 20. Claim, Disputes and Arbitration [Construction Contract Administration]
LOGO October The Employer FIDIC 1999 dasdas Supervisor: Dr.Kamalain shaath Done by: Mahmoud Abu Kmail Construction Contract Administration ENGC.
Workers Compensation Commission Sian Leathem Registrar 29 September 2008.
By Aidan, Lochie, Curtis. WORKPLACE DISPUTES  Negotiation: Is a method of compromising disputes within a workplace. This easygoing approach usually.
The Building and Construction Industry Security of Payment Act 2002 (Vic) made simple Western Suburbs Law Association Tuesday 4 June 2013 Michael Heaton.
LAW for Business and Personal Use © 2012 Cengage Learning. All Rights Reserved. May not be scanned, copied or duplicated, or posted to a publicly accessible.
Copyright © 2005 Pearson Education Canada Inc. Business Law in Canada, 7/e, Chapter 2 Business Law in Canada, 7/e Chapter 2 The Resolution of Disputes.
Local Assessment of Code of Conduct Complaints. 2 Background  On 08 May 2008 – the local assessment of Code of Conduct complaints was implemented due.
Planning appeals Peter Ford Head of Development Management Planning Committee Training – 30 th July 2015.
Procedural Safeguards. Purpose Guarantee parents both an opportunity for meaningful input into all decisions affecting their child’s education and the.
Certificate for Introduction to Securities & Investment (Cert.ISI) Unit 1 Lesson 59:  Breaches, complaints and compensation  The difference between a.
General Condition THE EMPLOYER Construction Law Supervised By : Dr. Kamalain Shaath Prepared By : Eng. Fawzy El.farra.
HN2100 Collective Agreement Administration With Paul Tilley Unit 7 Collective Agreement Clauses – Part 2.
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
The UNCITRAL Model Law on International Commercial Arbitration: 25 Years 4 June 2010 “The Influence of the UNCITRAL Model Law in Hong Kong and China”
Kevin Kelly Government Construction Projects & Capital Spend Conference 2016 Wednesday 11th May 2016 Royal Marine Hotel, Dun Laoghaire, Co. Dublin.
HOW TO PROTECT YOUR INTEREST IN A SALE CONTRACT Focus on what you “get” when you sign!
What is the court’s expectation of doctors? British Medical Association 17 November 2006.
ARBITRATION ACT. Challenge of arbitrator The appointment of an arbitrator may be challenged on the issues of – (i) impartiality, – (ii) independence,
Building Capacity of SMEs for Participation in Public Procurement Draft Presentation for Training of Trainers June 2014.
CCA Adjudication Cashflow, or fair dispute resolution, or both? Opportunities for Improvement in the Act and adjudication procedure Peter Degerholm AMINZ.
Charles University – Law Faculty October 2012 © Peter Kolker 2012 Class III
Rialto Adjudications Level 46, 525 Collins Street MELBOURNE VIC 3000 Phone: Fax: Web:
SMEs and private enforcement of competition law Rachel Burgess Ph:
Pre-action Procedure for Financial Cases
SURAT CHAPTER OF WIRC OF ICAI
Dispute Resolution Between ICT Service Providers in Saudi Arabia
Administration of a FIDIC Contract - Project Control
Resolving IP Disputes outside the Courts through WIPO ADR
Civil Tort Law Trial Procedure Civil Remedies (Tort Action)
What Small and Emerging Contractors Need to Know Understanding Dispute Resolution Options in the Construction Industry © Copyright 2017 NASBP.
Content of Tender Dossier Instructions to Tenderers
EPA CONTRACT TEMPLATE Overview
Gordon L. Jaynes A DAM GOOD THING Gordon L. Jaynes Copyright 2008.
The Role of Experts in Construction Arbitration
Civil Pre-Trial Procedures
Court Procedures for Negligence Cases
EPA SUBCONTRACT TEMPLATE Overview September 2017
Civil Pre-Trial Procedures
Extension of time and how it is granted to a contractor (Referencing JCT 2005)
What Small and Emerging Contractors Need to Know Understanding General Agreements of Indemnity © Copyright 2017 NASBP.
BRIEFING TO THE SELECT COMMITTEE ON SECURITY AND JUSTICE ON THE INTERNATIONAL ARBITRATION ,BILL, 2017 [B10B-2017] 1 NOVEMBER 2017.
ARBITRATION AWARD.
Chapter 4 Contractual Rights and Obligations
SIMAD UNIVERSITY Keyd abdirahman salaad.
Insurance Dispute Resolution in Thailand
ALTERNATIVE MEANS OF DISPUTE RESOLUTION
Chapter 11.
Function of the International Court of Justice (ICJ):
Complaints Investigation Presenter: Ms H Phetoane Senior Investigator :HealthCare Cases Prepared for OHSC Consultative Workshops.
Trial before court of session
Complaints Investigation Presenter: Ms H Phetoane Senior Investigator :HealthCare Cases Prepared for OHSC Consultative Workshops.
Complaints Investigation Presenter: Ms H Phetoane Senior Investigator :HealthCare Cases Prepared for OHSC Consultative Workshops.
Complaints Investigation Presenter: Ms H Phetoane Senior Investigator :HealthCare Cases Prepared for OHSC Consultative Workshops.
Dennis Li - HKCIC Lecturer
Complaints Investigation Presenter: Ms H Phetoane Senior Investigator :HealthCare Cases Prepared for OHSC Consultative Workshops.
Construction Contract Administration
ALTERNATIVE MEANS OF DISPUTE RESOLUTION
Public Protector South Africa Deputy Public Protector of South Africa
Presentation transcript:

Security of Payment and Adjudication in Hong Kong Vincent Liu, Partner

Agenda Objective of SOP legislation Scope of Proposed SOP Legislation Unenforceability of Pay when Paid Provisions Payment Terms Statutory Payment Claim System Statutory Adjudication Process Enforcement and review

Introduction In 2012, the HK Govt established a working group of 14 industry stakeholders to evaluate the options for SOP legislation in HK On 1 June 2015, consultation paper was issued by the working group setting out key aspects of the proposed legislation Interested parties are invited to give comments by 31 August 2015 Proposed legislation hybrid between UK SOP legislation and Australian SOP legislation

Objective of SOP legislation To ensure timely cash flow for contractors and subcontractors by way of periodic payments An industry wide survey in 2011 reported that 45% of main contractors and 57% of subcontractors had serious delays in payments To introduce a fast track dispute resolution process to ensure problems are resolved quickly during a project Current culture in the construction industry is to leave contractual claims e.g. EOT and major claims until the final account

Scope of Proposed SOP Legislation When does the Proposed SOP Legislation Apply? Apply to contracts related to construction activities carried out in Hong Kong regardless of: the nationalities of the parties; or the prescribed governing law Apply to all contracts for construction activities entered into by the HK Government Apply to private sector contracts for new building works where the original contract value is more than HK$5,000,000 (does not apply to refurbishments) If main contract subject to legislation, then it will apply to all lower tier subcontracts

Scope of Proposed SOP Legislation (cont) Apply to provision of professional services, and supply of materials or plant in relation to construction activities carried out in HK Apply to oral and partly oral contracts However, some debate whether only apply to written contracts as per Singaporean and Malaysian SOP legislation

Scope of Proposed SOP Legislation (cont) When doesn't the Proposed SOP Legislation Apply? Employment contracts Insurance contracts Guarantee contracts Loan contracts Investment contracts Accounting services Financial services (other than cost control and QS type services) Legal services Public relations services

Protections provided by Proposed SOP Legislation Prohibited Clauses "Pay when Paid" clauses and clauses of similar effect will be unenforceable under the proposed legislation Standard position taken in security of payment legislation in England and Australia Payment Terms/Payment Intervals Parties are free to agree on payment intervals for progress payments provided that No more than 60 days for interim payments; and No more than 120 days for final payments Defaults to 60 and 120 days respectively Consistent with the legislation enacted in New South Wales, Western Australia and Singapore

Statutory payment claim procedure Progress claims could be made purely on contractual basis In addition or alternatively, payment can be claimed by the statutory payment claims under Proposed SOP Legislation Statutory payment claim procedure is intended to operate in parallel to contractual payment procedures Contractors will not be able to claim any more than they could under the Contract – eg conditions precedents to payment, requirements for provision of particulars apply

Statutory payment claim procedure (cont) Who can issue Statutory Payment Claims? Both claimant and respondent are entitled to claim progress payments by way of statutory payment claims Contents of Statutory Payment Claims SOP Legislation will set out minimum criteria to be met in terms of the content of payments claims including: Details of amount claimed Relevant work carried out Basis of calculation etc Query whether compliance with prescribed requirements determines jurisdiction of adjudicator NSW, adjudicator found to lack jurisdiction when the requisite footer not included in a payment claim

Statutory payment claim procedure (cont) How to respond to a Statutory Payment Claim? Respondent must serve his payment response within 30 days of a payment claim Respondent to identify: Amount of payment claim accepted as due Disputed amounts and grounds of dispute Any amounts intended to be set off against amounts due and the basis of set off

Statutory payment claim procedure (cont) Failure to respond to a Statutory Payment Claim If the respondent ignores a payment claim, then: Will not automatically liable to pay the full amount of payment claim; but Will not be able to raise any set off or counterclaims during an adjudication In other words, the respondent could only raise liability and quantum defences in subsequent adjudication But not able to raise set off or counterclaims Statutory payment claim procedure is essentially the start of the adjudication process and provides respondents with notice of a forthcoming adjudication – one means of avoiding ambushes of the respondent

Implied Payment Provisions If no payment provisions in a Contract, then following terms are implied: Parties entitled to make payment claims at monthly intervals Payment due calculated based on value of work provided and valuation based on any contract price or market rates prevailing at the time the contract was entered into Respondent to serve payment response within 30 days Payment Period will be 60 days for interim payments and 120 days for final payments

Statutory adjudication Procedure Adjudication Process - Intention of the Proposed SOP Legislation Operates in parallel to other legal and contractual remedies The purpose of the adjudication process is to provide a provisional determination and on account payments to keep the cash flow moving in a project Even after determination, parties to a dispute are still entitled to proceed to mediation, arbitration or litigation for final resolution of the dispute

Statutory adjudication Procedure (cont') Who can apply for adjudication? Both parties will be able to refer disputes to adjudications More liberal than NSW and Singaporean legislation where respondents cannot commence adjudications

Statutory adjudication Procedure (cont') What disputes could be adjudicated? Payment disputes Set off / deductions Extensions of Time No jurisdiction to determine: Quantum meruit Breach of contract damages claims Proper Interpretation of the Contract

Statutory adjudication Procedure (cont') Adjudication Application Adjudication must be commenced within 28 days of: non-payment of the amount admitted as due in a payment response; rejection of all or part of a payment claim; failure to serve a payment response; or a time dispute arising Proposed legislation does not make clear when a time dispute arises = disputes concerning jurisdiction

Statutory adjudication Procedure (cont') Adjudication Application Adjudications commenced by service of notice of adjudication must set out: brief details of the parties the nature of the dispute the redress sought Query – whether adjudicator would lack jurisdiction if adjudication notice served out of time eg WA legislation The claiming party must serve submissions together with all supporting evidence relied upon on or before the appointment of the adjudicator Need to anticipate all arguments – may not get another chance

Statutory adjudication Procedure (cont') Appointment of Adjudicator An adjudicator is then either: appointed by agreement; or by nomination by an agreed or default nominating body (i.e. HKIAC) within 5 working days Nominating body could be agreed by the parties under the Contract

Statutory adjudication Procedure (cont') Responding to Adjudication Applications Respondent must respond with his own submissions and supporting evidence within 20 working days Possibility of extensions by the adjudicator – contrast Australian legislation where no extensions possible

Statutory adjudication Procedure (cont') The adjudicator is required to reach and publish his decision within 20 working days Extendable by the adjudicator up to 55 working days Could extend more than 55 working days if the parties agree The adjudicator is entitled to resign if he considers that it is not possible to decide the dispute fairly in the time available

Statutory adjudication Procedure (cont') An adjudicator: Is not bound by rules of evidence Can conduct the adjudication in such manner as he thinks fit Require further submissions and evidence from either party Call meetings with the parties Inspect relevant matters Set deadlines Issue procedural directions Provided adjudication is concluded within 55 working days from the date of appointment or any agreed extension Consultation Document suggests that adjudicators should decide matters on documents only

Statutory adjudication Procedure (cont') Adjudicators should take a fair and robust approach to arrive at their decision as soon as possible Consultation Document suggested that adjudicators do not need to have formal hearings with sworn witnesses and cross examination by lawyers Each party will bear its own costs – no need for adjudicator to determine cost liability Adjudicator's fees and expenses can be awarded to one party or the other depending on the result

Statutory adjudication Procedure (cont') Addressing Ambush The proposed legislation seeks to address ambush concerns by providing: an adjudicator with discretion to extend the deadline for serving an adjudication response an adjudicator may disregard any submissions or evidence not made in the notice of adjudication which should reasonably have been made earlier But claiming party will always have a strategic advantage as: he could simply withhold making his payment claims; and the paying party will still have to respond within the limited timescale of the adjudication

Adjudication Applications and Responses Practical Tips Check all arguments, set off and counter-claims raised in payment response Could seek a direction from adjudicator to provide further submissions but discretionary Recycling of claims? Be brief and concise in submissions – try not to be overly technical Good contract administration will help preparation of submissions by: Keeping daily site records of what work was done Taking photographic evidence at relevant times Obtaining statutory declarations on work and quality Obtaining independent assessment of work likely to be disputed

Effect of Adjudication Decisions Adjudication decisions are binding on the parties even if arbitration or legal proceeding have been commenced Payments made under adjudication decisions are on account/provisional – keep the cash flow going Arbitrator or Court would in making award or judgment allow for any amount paid under an adjudication determination

Enforcement and Review Suspension for Non-Payment The proposed legislation introduces a right for parties to: suspend all or part of the works; or reduce their rate of progress after giving written notice (2-10 days) in the event of non- payment of a sum determined in an adjudicator's decision or non-payment of an amount admitted as due in a payment response Contractor who suspends or slows down progress for non- payment will have rights to an EOT and to reasonable costs and expenses in respect of delay or disruption

Enforcement and Review (cont') Enforcement of Adjudication Decisions Adjudicator's decision will be enforceable in the same way as judgments of the Court without set off or deduction This means no new set off or deduction against the decision Review of Adjudication Decisions Responding parties only have a short period within which to lodge any challenge as to validity No ability to appeal or challenge the merits of adjudicator's decisions Could only challenge validity from the procedural perspective eg breach of natural justice, jurisdictional error Consultation paper – only in very clear cases will a challenge succeed on these grounds

Questions Email: vincent.liu@hfw.com Direct Line: +852 3983 7682

Lawyers for international commerce hfw.com