Tom’s Creek Foot-Bridge Final Exercise Tom’s Creek Foot-Bridge
Instructions Scenario: Previous PO started PW but then rotated out You have, scenario information, draft PW, FIRM, and photos As a class we will show photos next
Taken by applicant morning following storm near high water Taken by applicant morning following storm near high water. April 2, 2003
Overview of bridge from downstream.
Marker found on bridge
Bridge pier (upstream view) Bridge pier (upstream view). Applicant already has replaced stone in boxed area. Debris still in channel.
Washed out area downstream of bridge abutment.
Utilities on upstream side of bridge.
Assignment Determine appropriate mitigation measure Obtain mitigation costs from instructors Revise PW as needed Complete Special Considerations Questions Prepare Hazard Mitigation Proposal.
Class Summary 406 Regulations & Policies General Principles Hazards - Forces Involved - Mitigation Cost Effectiveness Other Considerations Document Preparation
Technical Feasibility Other Considerations Cost-Effectiveness Technical Feasibility Eligible Project