CMBG Performance Indicator Working Group Lloyd Hancock, CMBG Steering Committee November 12, 2018 Cleveland 2005
CM PI Working Group Beth Kernes Krause, Cooper Station Keith Reinsmith, Susquehanna NPP Rai Osborne, SONGS Peter Davidson & Hans Braul, Bruce NPP David Weber, Columbia Station Gary Scarfo, Fermi Plant Lloyd Hancock, Facilitator November 12, 2018 Cleveland 2005
CM PI Working Group Charter Requested at 2004 CMBG Conducted Numerous Conference Calls and emails Picked 5 “Easy” Indicators Developed Consensus Definitions Collected Data November 12, 2018 Cleveland 2005
CM Simplified Process Model
CM PI Working Group PIs Selected Temp Mods (quantity & age) Mod Package Closure Times Critical Document (FCI) Backlog Avoidable Field Changes for Mods % of CM CRs to Total CRs November 12, 2018 Cleveland 2005
CM PI Working Group Lessons Learned Terminology Difficult to Agree On Collecting Data Very Time Consuming if Reporting System(s) not set up Entire Exercise Was Learning Experience November 12, 2018 Cleveland 2005