Silicon Strip Tracker MPR November 2004 CMS TRACKER COLLABORATION

Slides:



Advertisements
Similar presentations
L. Greiner 1HFT PXL LBNL F2F – March 14, 2012 STAR HFT The STAR-PXL sensor and electronics Progress report for F2F.
Advertisements

Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
US CMS Silicon Tracker : Schedule J. Incandela University of California Santa Barbara US CMS Silicon Tracker Project Manager Fermilab PMG April 9, 2004.
1 Long Term Module Testing-Anthony AffolderTPO, December 11, 2003 Current Module LT Testing Capability Only Vienna Boxes Available  10 slots at each site.
The LHCb Inner Tracker Marc-Olivier Bettler SPS annual meeting Zürich 21 February 2007.
US CMS Silicon Tracker – PAC Meeting – FNAL - Nov 3, Incandela 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Joe Incandela Fermilab Level.
US Module and Rod Production Overview and Plan For the US CMS Tracker Group.
Slide 1 Anthony Affolder US Silicon Meeting, March 9, 2004 Equipment Status ARCS equipment status à Single module and 4 hybrid DAQ equipment status à Vienna.
US Tracker Group Status Sep. 1, 2005 J. Incandela For the US CMS Tracker Group.
Slide 1Rod Production presented by Jim Lamb (UCSB)April 9, 2004 Rod Production Rod Production, April , presented by Jim Lamb (UCSB)
Status of the Tracker DB System Tk week april 03 D. Contardo Developments Applications.
Brenna Flaugher Oct. 31 th CDF Meeting1 RunIIb Silicon Project Successful Lehman Review Sept Workshop at LBL 10/23-10/25: Wednesday-Thursday  hybrids.
The Finnish CMS Collaboration Helsinki Institute of Physics S. Czellar, A. Heikkinen, J. Härkönen, V. Karimäki, H. Katajisto,R. Kinnunen,T. Lampén, K.
US CMS DOE/NSF Review: May 8-10, Endcap Alignment Dick Loveless DOE/NSF Review 9 May 2001.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
1 TEC pilot run status Goal : test TEC module production rate capabilities - 15 R6 modules assembled on Brussels Gantry and bonded in Aachen I - 15 R7.
Status Brussels GANTRY Ê Assembly of R3 modules (36 modules) 4 precision of the modules 4 problems with DataBase (not adapted for single sensor modules)
CMS TRACKER STATUS REPORT Dimitri PandoulasCMS Week
DOE/NSF Review of the U.S. ATLAS Construction Project June 3-4, 2002 WBS 1.1 Silicon Subsystem Abe Seiden UC Santa Cruz.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
Roberto Tenchini CMS FB December 2004 CMS Tracker The Tracker Cost Review - November 2004.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Guido_Tonelli / CMS_TSC / 5 February Time stability of ST sensors The problem The sensors re-measuring campaign Failure analysis Conclusions.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
The CMS detector as compared to ATLAS CMS Detector Description –Inner detector and comparison with ATLAS –EM detector and comparison with ATLAS –Calorimetric.
CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)
Tevatron II: the world’s highest energy collider What’s new?  Data will be collected from 5 to 15 fb -1 at  s=1.96 TeV  Instantaneous luminosity will.
D0 Status: 01/14-01/28 u Integrated luminosity s delivered luminosity –week of 01/ pb-1 –week of 01/ pb-1 –luminosity to tape: 40% s major.
TOB meeting, TOB meeting 20 September 2005, Antti Onnela: TOB mechanical integration status and plans n TST-TOB-TIB integration exercise n.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
Local Supports to IDR Discussion ATLAS Upgrade Week November 2014.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
The CMS Silicon Strip Tracker Carlo Civinini INFN-Firenze On behalf of the CMS Tracker Collaboration Sixth International "Hiroshima" Symposium on the Development.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
PH/DT2 Scientific Tea PH-DT2 Scientific Tea, 29 April 2005 : The CMS Tracker - Mechanical Aspects Antti Onnela, PH-DT2: 1. CMS Tracker and.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
Juan Valls - LECC03 Amsterdam 1 Recent System Test Results from the CMS TOB Detector  Introduction  ROD System Test Setup  ROD Electrical and Optical.
CMS-UK Oversight Committee 17/11/06 D.J.A. Cockerill - RAL 1 The CMS Electromagnetic Calorimeter UK Responsibilities Procurement and testing of VPTs Design.
Single-Phase ProtoDUNE Construction Planning Jim Stewart LBNC January 11, 2016.
SVD Status Markus Friedl (HEPHY Vienna) SVD-PXD Göttingen, 25 September 2012.
EC: 7 DISK concept Preliminary considerations
CMS Phase 2 Tracker R&D R. Lipton 2/27/2014
Jim Fast Pacific Northwest National Laboratory
Alignment of the CMS Tracker
Test Beam Request for the Semi-Digital Hadronic Calorimeter
Update on the SVD construction
Internal review of IR2 LEP cryostats (WP11/WP5) Close out session
Renovation of the 45-year old PS magnets
ProtoDUNE SP DAQ assumptions, interfaces & constraints
2S module geometry updates Module positioning concepts
Rod adaptors for module tests Module positioning studies
Ideas and Plans on Tracker Module Mechanics Developments
System Tests at Lyon From Aachen: ICB for front petal side A, disks 4-6, rings 4 and 6 From CERN: CCU25 Tests (M. Ageron): FEC ring and I2C addressing.
Status Brussels GANTRY
Tracker Outer Barrel Silicon
FNAL Production Experience
Results from module testing
Front End Driver (FED) Crates and Racks +Tracker PSU racks
US Module Testing Progress Report
Current Module LT Testing Capability
Operations/Failure Analysis
TIB contribution for the X5 - May 2003 Test Beam
US Module Testing Progress Report
Status of Bonding R1N, R1S, R3 of TEC University of Hamburg
Equipment Status ARCS equipment status DAQ equipment status
Hardware needs (ARCS) Current ARCS capabilities at both sites should be able to keep up with production assuming software changes Automatic I-V curves,
Presentation transcript:

Silicon Strip Tracker MPR November 2004 CMS TRACKER COLLABORATION Gigi Rolandi CMS Tracker Project Manager on behalf of the CMS TRACKER COLLABORATION November 2004 MPR 04 Gigi Rolandi

SST Layout Support tube with Thermal Screen Outer Barrel --TOB- Inner Barrel & Disks –TIB & TID - End Caps –TEC 1&2- 2,4 m Support tube with Thermal Screen TID 2x (408 modules on 3 disks) TIB 2724 modules integrated on 16 shells TOB 5200 modules integrated on 688 rods TEC 2x ( 3200 modules integrated on 144 petals) November 2004 MPR 04 Gigi Rolandi

Achievements (1) The CMS concept for large rate silicon module production was demonstrated. We built more than 2000 final modules (out of 15000). High production rates were sustained in all centers during production or in trials of the production runs. Modules are tested using centrally produced hardware and common and calibrated procedures. We built and distributed large number of custom made cheap test stations. All information about production and testing is stored in a very efficient database used daily for production monitoring. The quality of the modules is very high. We have a well maintained DAQ system (in X-DAQ) able to read large number of modules and we have prototypes of the final electronics integrated in the system. They are currently used for test beams and integration. Dire quanti metri quadri e/o quante volte babar… November 2004 MPR 04 Gigi Rolandi

Achievements (2) We tested large scale prototypes on test beams using final DAQ (X-DAQ) and electronics. The FE electronics and the readout system were validated on the first 25 ns beam (2001 ???). Optoelectronics, FED, FEC and Power Supplies on schedule And very important for the integration: We completed the procurement of all large CF parts for the supporting structures and many of them have been already assembled. We produced a very large number of mock-ups that have been used for many integration studies (cabling…) and installation trials November 2004 MPR 04 Gigi Rolandi

“Recent” problems and solutions (1) Quality of Thick silicon sensors Bulk of the production shifted to HPK . All sensors have been ordered Quality of the FE Hybrids Also due to lack of quality control at the firm (that has eventually changed ownership). Improved quality control at the firm and in CMS. Quality of kapton Production redone but not on critical path due to other delays Quality of TOB rods board assembly Changed firm not on critical path due to other delays November 2004 MPR 04 Gigi Rolandi

“Recent” problems and solutions (2) Quality of the TEC petal manifold Solved only recently and near to the critical path for petal assembly Clearance TIB+TOB / TEC interface Changed layout of TIB-TID cables on the flange Construction tolerances of the alignment prisms Changed the design of the alignment link to muon system November 2004 MPR 04 Gigi Rolandi

Sequence for Construction November 2004 MPR 04 Gigi Rolandi

Support Tube and Thermal Screen sequence for construction Construction of the support tube Construction of the thermal screen Integration of the thermal screen in the support tube November 2004 MPR 04 Gigi Rolandi

TOB sequence for construction Construction of the TOB modules Construction of the rods Integration of modules on the rods Construction of the TOB structure and insertion in the support tube Integration of the rods in the TOB structure/support cylinder November 2004 MPR 04 Gigi Rolandi

TIB/TID– sequence for construction Construction of the TIB modules Construction of the shells Integration of the TIB modules on the shells Construction of the TID modules Construction of the of the disks Integration of the TID modules on the disks Assembly of 8/16 shells to form ½ TIB Assembly of 3 disks to form 1 TID Integration of ½ TIB and 1 TID Installation in the TOB Integration in the support tube } 2x November 2004 MPR 04 Gigi Rolandi

TEC sequence for construction Construction of the TEC modules Construction of the petals Integration of modules on the petals Construction of 2 x TEC structures Integration of the petals in the TEC structures 2x Installation of the TEC structure in the support cylinder November 2004 MPR 04 Gigi Rolandi

The next 7 (hidden) slides show the managerial structure of the project and the share of the responsibilities. You have them in the file and I will show them on request The Tracker Steering Committee has weekly meetings for executive decisions and monitors the advancement of the project including weekly reports from the module production centers November 2004 MPR 04 Gigi Rolandi

OVERWIEV OF THE PRODUCTION November 2004 MPR 04 Gigi Rolandi

Overview of Support tube and thermal screen production Hardware is in hand Assembly and tests will be finished by February 2005 November 2004 MPR 04 Gigi Rolandi

Overview of module construction Sensors are delivered to the gantries after QC steps Frames are delivered to the gantries Hybrids and pitch adapters are delivered to CERN Hybrids and PA are assembled at CERN Hybrids and PA are bonded ½ at CERN and ½ in US Assembled hybrids are delivered to the gantries Modules are assembled and delivered to the bonding centers Modules are bonded Modules are tested November 2004 MPR 04 Gigi Rolandi

Parts delivery In the following transparencies I will discuss schedule. The main assumption is that the delivery of FE Hybrids and Thick Sensors follows the agreed delivery schedules. We recently agreed with Cicorel a delivery schedule We ordered recently to HPK the last lot of 4900 sensors. November 2004 MPR 04 Gigi Rolandi

FE Hybrid delivery schedule Weeks in 2005 November 2004 MPR 04 Gigi Rolandi

Thick Sensors delivery schedule November 2004 MPR 04 Gigi Rolandi

Can we build modules at high rate, essentially following hybrids delivery? November 2004 MPR 04 Gigi Rolandi

Rate of Hybrid and PA Assembly at CERN Sustained rate in 2004 with less manpower : 350 assembly/week Availability of parts: pitch adapters are in hand – hybrids follow the schedule November 2004 MPR 04 Gigi Rolandi

TIB and TOB Module construction TIB : max rate of delivery of assembled hybrids is 80% of the available assembly rate in Italy as sustained in 2004 . During 2004 we built a large TOB and TEC module construction capacity in US. TOB : max rate of TOB hybrid delivery is 90% of the sustainable rate in US and 70% of the peak rate in US Availability of parts: Assembled hybrids follow the schedule other parts in hand November 2004 MPR 04 Gigi Rolandi

TEC Module construction A substantial part of TEC modules will be built in US. The Available module assembly rate depends on the capacity that is free after TOB production. During the first production phase (Jan 05- Aug 05) we have enough spare capacity. In the last 4 months the available capacity for module assembly just matches the rate of assembled hybrids, introducing a delay in the assembly of the last TEC module. November 2004 MPR 04 Gigi Rolandi

Why we believe we can sustain large module production rates ? We validated the CMS concept for module production in many ways We produced more than 2000 modules TIB & TEC and we sustained large rates when hybrids were not limiting the production We produced large number of modules on the other gantries and we sustained high rates for periods of at least 1 week. We studied in detail the procedures and we have taken measure to make it robust During 2004 we have invested large resources to augment the module production capacity in USA, that serves both TOB and TEC The numbers that we quote are robust and based on thorough studies and direct experience November 2004 MPR 04 Gigi Rolandi

Can we integrate the subdetectors in time ? November 2004 MPR 04 Gigi Rolandi

Overview of TOB integration See talk Construction of the rods TOB rods mechanics is assembled in Finland and delivered to CERN TOB rods are integrated with electronics at CERN and delivered to US Modules are built in US and integrated on rods. Rods are tested and delivered to CERN Rods are accepted Mechanical structure is built and inserted in the support tube Group of rods (8-22) are integrated in the structure, cabled and tested November 2004 MPR 04 Gigi Rolandi

Overview of TOB production November 2004 MPR 04 Gigi Rolandi

Overview of TOB production November 2004 MPR 04 Gigi Rolandi

TOB critical path Since the available assembly rate of modules and of rods is larger than that of assembled hybrids, The delivery of the assembled hybrids gives the critical path Once we are integrating on the structure we could do more with more manpower and is the integration rate that gives the critical path November 2004 MPR 04 Gigi Rolandi

Overview of TIB-TID production November 2004 MPR 04 Gigi Rolandi

TIB-TID critical path 1) Delays in the delivery of the major components needed for the integration (mostly the TID) 1a)TID (modules, mother cables, DOM for the D1/D2/D3FWD) modules 04/04/05 mother cables 28/02/05 DOM 25/02/05 1b) TID rings and disks 25/03/05 2) Delays in the commissioning of the TIB/TID assembly tool and of the burn-in procedure. 2a)TIB/TID assembly tool 24/01/05 2b) Burn/in procedure 22/02/05 November 2004 MPR 04 Gigi Rolandi

Overview of TEC integration See talk Construction of the petals Petal mechanics + motherboards are built in Aachen and delivered to the 7 Petal Integration Centers (PIC) Modules are built in several centers and delivered to PIC Petals are integrated with electronics and with modules, tested and delivered to the two integration centers Two mechanical structures are assembled and integrated with cables and ribbons ready to receive the petals TEC+ is integrated Aachen and shipped to CERN TEC- is (partially) integrated in Lyon and shipped to CERN November 2004 MPR 04 Gigi Rolandi

Overview of TEC production November 2004 MPR 04 Gigi Rolandi

Overview of TEC production November 2004 MPR 04 Gigi Rolandi

TEC Critical Path As explained already before, the critical path is given by the hybrid delivery at the beginning of the production and by the module construction capacity at the end of the delivery The petal production rate is ok and – in the present model – limited to lower rate near the end due to availability of modules of a given flavor. To be checked if can be optimized The foreseen integration rate is comfortable for TEC+ and less for TEC-. To be seen if one can advance the start petal integration on TEC-. November 2004 MPR 04 Gigi Rolandi

Do we learn from the past ? November 2004 MPR 04 Gigi Rolandi

Time evolution of the Tracker schedule Here I say that 1)the time allotted for final integration did not change in the years 2)the time allotted to module construction has diminished and the module construction rate increased. 3) I said previously this is justified by the experienced gained with the first 15% of the production and with the large investment we made in US to upgrade the module production capacity November 2004 MPR 04 Gigi Rolandi

Module production rates Essentially this transparency is to justify why we have today lower rates than at the AR04. Here I say that at AR04 we did not know yet the hybrid schedule, so I essentially used the max rates in the three subdetectors. Actually what copes with the hybrid rates (but from TEC at end of production) is indicated in the column NOW. What we need globally is just below of what we have (as already discussed before) TOB and TEC production are nested see slide 29 Test capabilities increased accordingly to the production rates November 2004 MPR 04 Gigi Rolandi

Risks in the schedule (1) Delivery of FE hybrids and their quality No contingency against another failure. Improved QC Delivery of Sensors Present schedule has small contingency: last TEC sensor arrives 2 months before last TEC assembled hybrid Discuss with HPK November 2004 MPR 04 Gigi Rolandi

Risks in the schedule (2) Major failure of a Gantry We have a maintenance policy and we know from experience that we have been able to repair the rare failures we had in ~ 2 weeks. If we need to replace one of the gantries with the back-up gantry ( very unlikely event) it will take two months. Failure of a bonding machine Less impact due to the larger redundancy Increase the number of spare parts Stock of modules in the 7 petal assembly centers Problems with uniform module delivery Concentrate resources in fewer centers if needed November 2004 MPR 04 Gigi Rolandi

Simple analysis of the schedule (1) After we agreed with Cicorel on a schedule for the delivery of the FE Hybrids we propagated it through the construction process. At the same time we had a critical look to the integration procedures. We identified two main changes in the procedure that create contingency. Delivery of partially integrated TEC- at CERN. This saves the time needed for testing TEC- after the transport. Nested integration sequence: TOB+ , TIB+, TOB- (in parallel), TIB-. This allows a sequential integration of TIB+ and TIB- and we can profit of the experience in integrating TIB+ when integrating TIB-. November 2004 MPR 04 Gigi Rolandi

Integration schedule November 2004 MPR 04 Gigi Rolandi

Simple analysis of the schedule (2) TEC+ and TEC- are integrated independently and independently of TOB and TIB-TID. They can be inserted in the Tracker at the last moment. The delivery of the Tracker is driven by two largely independent paths TOB and TIB/TID integration that is correlated with the delivery of TOB modules TEC- integration that is correlated with the end of the delivery of TEC modules Ariella will present the details of the integration schedule in the next talk. It foresees the delivery of the Tracker to CMS by September 2006 November 2004 MPR 04 Gigi Rolandi

Contingency in the schedule We have assumed an Hybrid delivery rate that is 10% lower than what agreed with the company. TOB-TIB Line (TOB+ , TOB- , TIB-) Module delivery follows hybrid delivery: contingency in the assembly rate (20%) . The delivery of the last TOB rod has a float of 3 months The delivery of TIB- has a large float The integration has internal contingencies. In parallel one can use extended shifts during the integration time. Hard limit is the delivery of the last TOB rod that has a float of 3 months wrt the end of the TOB integration Once TOB- is integrated TIB- takes 64 working days for integration November 2004 MPR 04 Gigi Rolandi

Contingency in the schedule TIB+ and TEC+ lines are not critical TEC- line Contingency in the module assembly rate (20%) may be used to accelerate the delivery of the last TEC module/petal The delivery of the last petal has a float of 2 months After the integration of the last petal, the schedule has 20 days of contingencies and 20 days of cold test. November 2004 MPR 04 Gigi Rolandi

Availability of Manpower for construction During 2004 large manpower for hybrid assembly and for module has been “idle” waiting for parts to mount. ( ~ 100 people) The delays induced by the technical problems on the hybrids and on the sensors have caused a large loss of money on the exploitation budget of the European institutes and on the CMS budget of the US institutes All institutes are committed to provide the manpower for the Tracker construction in the coming years. In the next month we will make a survey in the institutes to evaluate the resources needed to create contingency by increasing manpower on critical tasks. November 2004 MPR 04 Gigi Rolandi

Conclusions The project has accumulated very important delays due to technical problems in the FE hybrids and in the Thick Sensors The problems with the Thick Sensors have been solved The production of the FE hybrid has restarted after a thorough review of the project. We have taken measures to minimize the impact of these delays on CMS We are confident that if the part delivery continues as foreseen we can deliver with contingency the Tracker to CMS by fall 2006. November 2004 MPR 04 Gigi Rolandi