V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

Slides:



Advertisements
Similar presentations
LHC UPS Systems and Configurations: Changes during the LS1 V. Chareyre / EN-EL LHC Beam Operation Committee 11 February 2014 EDMS No /02/2014.
Advertisements

Electrical Distribution: How to Ensure Safe Powering and High Availability for LHC Machine Protection Systems? V. Chareyre / EN-EL Machine Protection Panel.
MEF - Machines & Experimental Facilities Technical Stop #4 29 th August - 2 nd September 2011 Summary Julie Coupard Schedule and Coordination LHC-TS4 -
Tomasz Ladzinski GS/ASE. LASS Annual Maintenance & Tests General Principles Each winter shutdown preventive maintenance of EIS takes place. It is followed.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
How to achieve higher redundancy of the UPS for QPS ? -The lack of redundancy concerns the supply lines from UPS to consumer but equally parts of the UPS.
Chamonix Risks due to UPS malfunctioning Impact on the Superconducting Circuit Protection System Hugues Thiesen Acknowledgments:K. Dahlerup-Petersen,
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
Training LHC Powering R. Denz Quench Protection System R. Denz AT-MEL.
AT-MEL-PM, R. Denz, CERN, CH-1211 Geneva 23 1 QPS system and its risks  Principal risks  General remarks  Quench heater circuits  Quench detection.
Beam Interlock System MPP Internal ReviewB. Puccio17-18 th June 2010.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
LS1 Review P.Charrue. Audio/Video infrastructure LS1 saw the replacement of BI and RF analog to digital video transport Was organised in close collaboration.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
Review of Sector th of February Tunnel Access During Powering Tests Hugues Thiesen, AB-PO.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
MPP Workshop Status of Powering Interlocks I. Romera on behalf of MPE-MS MPP Workshop, 12 June 2015, I. Romera (TE-MPE)1.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
Machine Protection Review, Markus Zerlauth, 12 th April Magnet powering system and beam dump requests Markus Zerlauth, AB-CO-IN.
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Hardware Commissioning Review, R. Denz, 12-May Superconducting circuits: what remains to be done during hardware commissioning R. Denz AT-MEL-PM.
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
Magnet activities in SPS during EYETS
Matters arising RADWG - 3 July 2009
YETS & LS2 Works EN-EL / Power distribution
The TV Beam Observation system - BTV
Technical Services: Unavailability Root Causes, Strategy and Limitations Data and presentation in collaboration with Ronan LEDRU and Luigi SERIO.
Beam Interlock System SPS CIBU Connection Review
PSB Lock Out Test, Follow-Up AP. Bernardes-/EN-STI, K
EYETS Works EN-EL [ FC excluded ]
YETS & LS2 Works EN-El on LHC / Power distribution
R. Denz, A. Gomez Alonso, AT-MEL-PM
Powering LHC magnets version 30/3/2007.
Acknowledgements: H.Milcent, R.Denz, R.Schmidt, M.Zerlauth
TE-MPE LS1 review Vision from EN-EL(CF)
LINAC4 50 MeV phase BIS STATUS
LV Safe Powering from UPS to Clients
Powering the LHC Magnets
J. Uythoven for the MPE-MI & MS Teams
1v0.
MPE main activities planned for LS2
TI8/WIC Incident & UJ87/UA87 Radiation Levels & Analysis
Powering from short circuit tests up to nominal
YETS & LS2 Works EN-EL / Power distribution
Beam dump on LHC beams dumped on 08:20:04 by SIS, following a failing BLM HV check in IR7.
Commissioning and Testing the LHC Beam Interlock System
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Monday 11/07: Recovery Plenty of accesses.
Thursday 09:30 VdM scan for CMS, standard ADT gain.
TEST PLANS for HL LHC IT STRING
Power cut 18kV cable for EMD404/E9 is heating
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Collimator Control (SEUs & R2E Outlook)
Machine Protection Xu Hongliang.
M. Zerlauth, I. Romera 0v1.
Machine Protection System Commissioning plans
Will We Ever Get The Green Light For Beam Operation?
Beam Interlocks for Detectors and Movable Devices
Brief report of the hardware commissioning activities
Commissioning of the LHC superconducting magnets systems: Why an LHC Hardware Commissioning? Specificity and complexity of this machine Roberto Saban.
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Review of hardware commissioning
Presentation transcript:

V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth (Re-)validation tests of UPS powering post LS1 Acknowledgements: V.Chareyre, H.Thiesen, M.Zerlauth 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth Motivation Machine Protection Systems depend on UPS power to maintain protection and diagnostics function during power outages and perturbations UPS power was reconfigured after 2008 incident to guarantee truly redundant powering (F3/F4 lines in tunnel for e.g. QPS, additional power from other IP side in even points,…) Separation came with degradation of availability and maintainability LS1 campaign used by EN/EL to consolidate situation and restore dependable powering -> MPP presentation V.Chareyre May 2013 Changes require re-validation and allow for identification of potential errors/short-comings in design (QPS powering F3/F4, LBDS powering, BIS CIBUs…) 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

Why to test redundant powering? Verify that single protecting systems have redundant power supplies, i.e. they are supplied by true independent power distribution lines Verify that redundant systems are powered from the correct power path Verify that machine protection is still fully operational even if a complete distribution line is lost (although protected by UPS) Identify interdependencies between systems! Verify that magnet powering is stopped in degraded powering conditions (as the PIC may not be triggered by the UPS systems!) Verify the impact on other users (not having redundant systems nor redundant powering). They are or will be interested by this test! Always mentioned but never done! -> Some incidents in run 1, following a lot of consolidation works during LS1, so it’s high time to do it! 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

Overview of the UPS Network for the LHC Example in one even LHC point: 2 UPS parallel-redundant systems in UA (left), US and UA (right) 64 UPS systems for powering the LHC machine systems (RE alcoves, LHC even points (US and UA zones), LHC odd point)s UPS network for all users requesting safe powering! QPS (quench protection systems) Beam interlock systems Beam Loss Monitors Cryo, Vac, WorldFip, Star-points Backup time defined by the QPS systems: 10 min, strict minimum for continuing protecting the magnets after a fast power abort (energy extraction time constant) Example in one alcove (RE): 2 UPS parallel-redundant systems Courtesy V.Chareyre 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

New UPS Configuration in the alcoves and Odd Points 3rd UPS (UPS backup) powering the bypass of both UPS F3 and UPS F4 = Stand-by redundancy ‘Natural’ redundancy No communication bus between the 3 UPS systems Distribution Unchanged Output UPS power protected Courtesy V.Chareyre 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

UPS Configuration in UA and US zones UPS configuration not changed UPS system replacement one-to-one In case of failure of one UPS system in a redundant UPS configuration: Stop of the faulty UPS system Automatic transfer of the full load to the remaining UPS system F3 and F4 distribution lines fully protected Output UPS power protected Courtesy V.Chareyre 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

Résultats des tests HC-AUG (2008-2009) EN-EL, HCC Team et Hugues Thiesen 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth Objective Annual AUG tests were used to verify that equipment powered with ‘secure’ power (UPS, Diesel,…) is behaving properly during power cuts Systems concerned Safety systems ACESS, ODH et Fire detection, RadMon et Ramses Machine protection QPS, QHPS, 13kA-EE, 600A-EE PIC, WIC, BIC Power Converters Cryo Vide Beams RF, Beam Instrumentation, Beam Transfert and Beam Dump Infrastructure CV EL TI Star Point Excluded systems Expériences Courtesy H.Thiesen 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth Sequence of tests AUG tests organised / point and concerned The point under test (surface and underground), The two adjacent sectors, roughly ½ arc on each side Interruption of normal AC supply until complete cut of network supplies After 10 minutes the UPS systems were stopped According to client system Non-secured network clients affected by initial cuts Systems powered by UPS affected by UPS cut Systems on secure network do not see any interruption T I 2 8 S P n j e c t i o B a m d u p Point 5 Point 4 Point 2 Point 3 Point 6 Point 7 Point 1 Point 8 Courtesy H.Thiesen 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth Test results No major problem observed, however a number of small but important problems revealed Machien Protection Systems QPS, QHPS, 13kAEE et 600A-EE Rack QPS of MQ.15R5 not on UPS 4 cells in the arc23 (2R) found linked to mains instead to UPS Certain WorldFIP repeater not connected on UPS (lost comunication) … PIC, WIC et BIC Communication problem in point 5 (Star Point?), Inversion of UPS/AUG signals in point 1, Power Converters EIS convertes not on secure network => access problem after end of UPS autonomy Beam Instrumentation Pb with 3 crates BLM in SR2, Beam transfer (pts 2, 4, 6 et 8) Tests not significant as equipment condemnd… Courtesy H.Thiesen 11 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

Proposal for test procedure post LS1 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

How to test redundant UPS powering The IT star-point rack (powered by the UPS F3) is transferred to a temporary power supply The switchboard (EOD F4) downstream the UPS F4 is switched off MP users verify that: Their equipment remain powered by the F3 distribution line And/or their redundant equipment A are still powered while equipment B are switched off Then the switchboard (EOD F4) is powered again The switchboard (EOD F3) downstream the UPS F3 is switched off Their equipment remain powered by the F4 distribution line And/or their redundant equipment B are still powered while equipment A are switched off The other users (without redundant powering) can only see and note the impact! Optional in UA63/67: Cut 2nd time EOD F4 to verify LBDS functionality Then the switchboard (EOD F3) downstream the UPS F3 is powered again The IT star-point rack is transferred back to its initial power supply coming from the UPS F3 Notes: ‘Backup UPS’ in the alcoves and odd points No operation on the UPS systems PIC not triggered! 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

What needs to be tested – REs / odd points New configuration with 3 UPS systems and 2 redundant power paths F3/F4: Each RE alcove  x 16 Each odd LHC point  x 4 Each even LHC point -> x4 Test procedure to be applied 24 times Tbd if surface UPS should be tested as well Each RE covers ½ arc, impact from half-cell 11 up to 34 Each LHC odd point covers from half-cell 10L up to 10R Each LHC even point covers from half-cell 10L up to 10R 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth When to test? Obviously when all systems are present and connected, but impact on operation systems (cryogenics, vacuum,..) is still minor Proposal: After the already scheduled AUG tests (during initial cool-down of sectors) For each RE alcove /LHC odd point: 1/2 day to perform the test For each LHC even point: 1 day Perform tests together with planned AUG tests before/early into cool-down 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth UPS test planning in 2014 Tests to take place at end of AUG tests to profit from synergies ½ -1 day of additional test time / zone Type Test Mid April: IR6 (LBDS dry-run?!) End April: IR7 Early May: IR8 Mid June: IR1 End June: IR2 & IR3 End July: IR4 & IR5 Organistion: I.Romera (MPE), H.Thiesen (EPC), V.Chareyre (EL), M.Solfaroli & M.Pojer (HWC) 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth Conclusion Revalidation strongly recommended following consolidation and run 1 experience -> Should also surface UPS be considered? No major problems expected, will however reveal numerous small but important non-conformities which require correction before restarting the machine Use synergies with (already scheduled) AUG tests to minimize impact Requires additional ½ day for odd points and 1 day for even points (conservative) Only clients on UPS networks affected, normal network will remain powered Due to ‘early’ timing tests might however not be fully significant for some equipment types (equipment condemned during shut-down,…) Next steps Finalize survey for impact/requirements from all relevant users Integration into in official LHC planning (following presentation in LSC before end of the year) Prepare and circulate procedure describing test and required preparation (early 2014) 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth End 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth

Questions to client systems Do you have any concerns for the safety/availability of your equipment during the tests (Cryo, Vac) Will the test at proposed time allow to validate redundant powering, i.e. will remote diagnostic be available? Do you have any additional request wrt to ‘standard procedure’ (cut sequentially F3/F4) Do you have any additional request for network configuration prior to test (e.g. powering of diagnostic racks,..)? Do you have any equipment in the LHC surface buildings racks?! Pleas name a contact person representing your team during the test 11/14/2018 V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth