Intermittent Resources and Demand Response Integration 2007–2016 Long-Term Reliability Assessment Workshop Bill Bojorquez VP, System Planning August.

Slides:



Advertisements
Similar presentations
1 Regulatory Developments and Impacts Involving Electricity Storage in Texas Elizabeth Drews 31 st USAEE/IAEE North American Conference Austin TX, November.
Advertisements

1 Generation Adequacy Task Force Report to TAC April 7, 2005.
Connection of Wind Farms to Weak AC networks – ERCOT Experience and Challenges Shun-Hsien (Fred) Huang ERCOT System Planning CIGRE WG B4.62 Meeting June.
February 25, 2011 Demand Side Working Group EILS Update Mark Patterson ERCOT, Manager Demand Integration.
ERCOT Emergency Load Response Sam Jones Paul Wattles Steve Krein PUC Demand Response Workshop Sept. 15, 2006.
Enhancing Interruptible Rates Through MISO Demand Response: WIEG Annual Meeting June 19, 2008 Presented by: Kavita Maini, Principal KM Energy Consulting,
The Status Of The Electric Grid In ERCOT The Electric Reliability Council Of Texas Sam R. Jones, P.E. ERCOT – Retired As a retiree of ERCOT this presentation.
North American Electricity Markets APEX Paris, France October 15-16, 2007 Kenneth Laughlin, PJM.
1 The Effects of Integrating Wind Power on Transmission System Planning, Reliability, and Operations Phase 1 Preliminary Overall Reliability Assessment.
ERCOT Public 1 AS Demand Curves for Real-Time Co-optimization of Energy & Ancillary Services.
National Renewable Energy Laboratory Innovation for Our Energy Future * NREL July 5, 2011 Tradeoffs and Synergies between CSP and PV at High Grid Penetration.
Joel Koepke, P.E. ERCOT Operations Support Engineer ERCOT Experiences During Summer 2011.
Intermittent Resources and Demand Response Integration 2007–2016 Long-Term Reliability Assessment Workshop Bill Bojorquez VP, System Planning August 16,
Warren Lasher Director, System Planning October 4, 2014 Our Energy Future.
NASUCA Meeting Integration of Intermittent Renewable Resources Panel Michael McMullen MISO June 10, 2013.
Overview of the North American and Canadian Markets 2008 APEX Conference in Sydney, Australia October 13, 2008 Hung-po Chao Director, Market Strategy and.
Texas Wind Energy American Meteorological Society Summer Community Meeting – Norman Oklahoma Henry Durrwachter, P.E. August 12, 2009.
Demand Response: Keeping the Power Flowing in Southwest Connecticut Presented by: Henry Yoshimura Manager, Demand Response ISO New England September 30,
Demand Response Workshop September 15, Definitions are important Demand response –“Changes in electricity usage by end-use customers from their.
ERCOT Planning WMS 10/20/2010 Target Reserve Margin and Effective Load Carrying Capability of Installed Wind Capacity for the ERCOT System – Methodology.
ERCOT Emergency Interruptible Load Program Kent Saathoff Ken Donohoo Paul Wattles Mark Patterson Steve Krein PUC Demand Response Workshop Oct. 2, 2006.
ERCOT Emergency Interruptible Load Program Paul Wattles Steve Krein WMS Oct. 13, 2006.
Chicago Advanced Energy Demand Response & CSP Evolution Kellen Bollettino Comverge Inc. 10/23/14.
EECP External Communications ERCOT Governmental Relations & Communications COPS June 27, 2006.
1 WMS Report TO TAC January In Brief Two Working Group Reports Two Working Group Reports Two Task Force Reports Two Task Force Reports One PRR.
Demand Response: What It Is and Why It’s Important 2007 APPA National Conference San Antonio, Texas June 26, :00 a.m. to Noon Glenn M. Wilson Director.
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
ERCOT Emergency Interruptible Load Service Customer & Stakeholder Workshops July 2007.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
Long Term Study Transmission Results May 21 st, 2013.
PRR 705 ERCOT Emergency Interruptible Load Service PRS January 22, 2007.
ERCOT Public 1 Project Panel 1 Dan Woodfin Director, System Operations August 15, 2014.
Planning for Texas’ Energy Future Select Committee on Electric Generation Capacity and Environmental Effects Bob Kahn President & CEO February 6, 2008.
Oncor Transmission Service Provider Kenneth A. Donohoo Director – System Planning, Distribution and Transmission Oncor Electric Delivery Co LLC
Operations Update ERCOT Board Meeting March 18, 2003.
Capacity, Demand and Reserves Report Bill Bojorquez May 4, 2007.
Capacity, Demand and Reserves Report Bill Bojorquez Board of Directors Meeting May 16, 2007.
August 24, 2007 ERCOT Regional Planning Group Meeting CREZ Transmission Optimization Study Warren Lasher System Assessment.
Emergency Interruptible Load Service Paul Wattles ROS Subgroup Feb. 7, 2006.
Operations Update Kent Saathoff TAC Meeting March 6, 2003.
SERC Reliability Corporation 1 SERC RELIABILITY CORPORATION MID-AMERICA RELIABILITY CONFERENCE June 21, 2006 COLUMBUS, OHIO.
H.B. “Trip” Doggett President and Chief Executive Officer Review of February 2, 2011 Energy Emergency Alert (EEA) Event Emergency Event Coordination Workshop.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
Energy Emergency Alert (EEA) UPDATE F EBRUARY 8, 2011.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
Renewable Technology Working Group (RTWG) Report to TAC February 4, 2010 Henry Durrwachter.
RPG - 10/12/2007 Competitive Renewable Energy Zones (CREZ) Update Bill Bojorquez Vice President, System Planning.
The Midwest ISO – Platform to Meet Tomorrow’s Challenges Wisconsin Industrial Energy Group August 7, 2008.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Target Reserve Margin (TRM) and Effective Load Carrying Capability (ELCC) of Wind Plants Evaluation - Input and Methodology ERCOT Planning 03/25/2010.
Principal Load Profiling and Modeling
2018 LTSA Workshop August 2017 RPG Meeting Welcome to.
Transmission Planning in ERCOT- Overview
Wind Management at MISO
TAC Report to the ERCOT Board
Appeal of PRS Rejection of NPRR 667
DS3 and Qualifier Trials Update
ERCOT – Southern Cross Transmission ROS/WMS Working Group Assignments
Generation Adequacy Task Force Update to WMS
The New Texas Wholesale/Retail Market
Grid Integration of Intermittent Resources
Opportunities in the Changing Energy System
31st USAEE/IAEE North American Conference
New England Resource Adequacy
Sandip Sharma ERCOT Manager, Operations Planning
Forecasting and Operations CAISO Case
NYS Department of Public Service
Energy Storage System Drivers and Use Cases for Energy Storage Systems
Presentation transcript:

Intermittent Resources and Demand Response Integration 2007–2016 Long-Term Reliability Assessment Workshop Bill Bojorquez VP, System Planning August 16, 2007

NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION (NERC) North American Interconnected Grids NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION (NERC) The ERCOT grid: Covers 75% of Texas land Serves 85% of Texas load 38,000 miles of transmission lines >550 generation units Physical assets are owned by transmission providers and generators, including municipal utilities and cooperatives ERCOT connections to other grids are limited to direct current (DC) ties, which allow control over flow of electricity

Current Wind Development ~3,300MW installed capacity of wind generation in-service ~2,000MW additional wind development with signed interconnection agreements Steady build out has allowed for transmission, modeling and operation integration Additional bulk transmission lines will be required for > ~5000MW from West Texas ~29,000 MW additional wind development in interconnection study process

ERCOT Load 62,339 MW summer peak demand Majority of load is concentrated in eastern half of state Dallas Austin Houston San Antonio

Effective Load Carrying Capability (ELCC) of Wind Process: Run the ERCOT LOLP model with the base set of generating units and a generic thermal generator (550 MW) and determine the expected unserved energy. Remove the generic thermal generator and add new wind generation with detailed profiles until the same expected unserved energy is achieved. The amount of new wind generation will have the same effective load-carrying capability as the 550-MW generic thermal generator Update study every two years Results: 6,300 MW of wind had the same load carrying capacity as 550 MW of thermal generation (i.e., 8.7%). Describe the process for wind.

Increased renewable energy goal 5,880 MW by 2015 10,000 MW by 2025 TX Senate Bill 20 (2005) Increased renewable energy goal 5,880 MW by 2015 10,000 MW by 2025 Set up process for the PUC to designate Competitive Renewable Energy Zones (CREZs) ERCOT contracted AWS Truewind to identify areas with best wind resource potential in Texas AWS identified highest CF 100MW sites and clustered into 25 areas

Potential Wind Resource 12000 Potential Wind Resource 10600 9600 8300 2700 Nearly 100,000 MW above 35% capacity factor (CF) Concentrated in western half of state 4600 2200 6200 6000 2900 7900 6900 4700 Approximate west to east transfer capacity – 3,200MW 3000

New Transmission Required 12000 New Transmission Required 10600 9600 8300 2700 Existing system from west Texas fully subscribed Significant distances and costs associated with adding bulk transmission 4600 2200 200 miles 6200 6000 2900 7900 6900 4700 150 miles 3000

Allowed for incremental 1,000 to 5,000 MW of wind capacity ERCOT Study Results ERCOT’s 2006 study identified new lines and upgrades to allow transfers from CREZ areas Allowed for incremental 1,000 to 5,000 MW of wind capacity In addition to 5,000 MW existing plus planned Goal was to provide options from which the PUC could designate areas and amounts

Draft CREZ PUCT Designations (Scenario 3) 3720 Wind Zone Planned New Wind Capacity (MW) 1, 2 4,560 4 3,720 5, 6 2,890 9,10 5,215 19 2,051 Total 18,436 4 4560 1, 2 5215 2051 9, 10 19 2890 5, 6

Level of wind penetration relative to the size of the interconnection Challenges Level of wind penetration relative to the size of the interconnection Minimum system load dispatch issues (~ 21,000 MW) Ancillary Services to support large wind changes Voltage and transient stability modeling and assessments MW Noon Midnight Completing system reviews for the CREZ designations over the next six months

Next Steps Stage 1 (August): Final order in Docket 33672 on CREZs and “rough” transmission requirements Stage 2 (December/January): Completion of “CREZ Transmission Optimization Study” Stage 3 (December/February): PUC to designate transmission constructors Stage 4 (December ’08/February ’09): CCNs developed and submitted Stage 5 (June ’09/August ’09): CCNs approved Stage 6 (TBD): Completion

Demand Response

Target for reliability: 12.5% Reserve Margins 2000-2012 Percentage difference between projections for peak demand and available generation/resources Target for reliability: 12.5% Over 65,000 MW of new generation is in planning or under consideration, but not all will be built. 12.5%

Interruptible Tariffs in the Regulated World Prior to 2001, 3200 MW of customer load (mostly industrials) provided an emergency interruptible safety net Customers’ year-round electric rates were discounted in exchange for this In May 2000, ERCOT deployed interruptible loads four times during emergency conditions Unseasonably hot weather Generation outages New wave of gas-fired generation had not yet come online ERCOT began full retail competition on January 1, 2002

Interruptible Load in the New (restructured) Market Loads Acting as a Resource: Market-based replacement for interruptible tariffs 1,989 MW currently registered and qualified ERCOT demand forecast is reduced by 1,112 MW of “high confidence” demand response LaaRs can provide ERCOT Ancillary Services (operating reserves) & receive capacity payments regardless of whether they are actually deployed LaaRs provide 50% of ERCOT Spinning Reserve requirement (1,150 MW of 2,300 MW total) Market price: ~$13 per MW per hour Price-responsive demand is significant in ERCOT – but not yet readily reported Additional demand response is obtained on coincident peak periods due to Transmission Tariff incentive

LaaR Participation Growth in LaaR registration in MW

LaaR Deployments LaaRs can be deployed in 4 ways: Automatic trip based on Under Frequency Relay settings Verbal dispatch by ERCOT during EECP event (deployed as block) Verbal dispatch by ERCOT during frequency event reportable to NERC (deployed as block) Verbal dispatch by ERCOT to solve a local congestion issue (location-specific) LaaRs have been deployed four times in the past 16 months: April 17, 2006 Emergency Electric Curtailment Plan (manual) Oct. 3, 2006 frequency event (manual) Dec. 22, 2006 frequency event (UFR & manual) July 2, 2007 frequency event (manual)

Emergency Interruptible Load Service (EILS) Service provided by loads (customers) willing to interrupt during an electric grid emergency in exchange for a payment Last resort prior to firm load shedding (rotating outages) Deployed ONLY in the late stages of a grid emergency Goal is 500 MW to 1,000 MW subscription Minimum subscription not met for spring and summer 2007 New RFP out for fall 2007 ‘Another tool for the operator toolbox’

Deployment During Emergency Operations Event/Action Trigger ADVISORY Physical responsive below 3000 MW ALERT: Start Reliability Must Run units, suspend unit testing, deploy Replacement & Non-spin Reserves Physical responsive below 2500 MW Emergency Electric Curtailment Plan Step 1: Dispatch all generation, issue public media appeal, acquire maximum power thru DC Ties Physical responsive below 2300 MW Step 2: Deploy LaaRs Physical responsive below 1750 MW Step 3: Deploy EILS Resources Maintain frequency at 60 Hz Step 4: Instruct transmission owners to shed firm load Frequency below 59.8 hz ERCOT Operators have flexibility to skip Step 3 if frequency is decaying rapidly. In these cases EILS would be deployed immediately after Step 4 to enable faster recovery.

Consideration on Demand Response (DR) Should DR be considered a firm resource? If so what types of DR Does DR defer transmission investment? ERCOT concluded it should not Summer 2006 MISO experience showed DR may not be useful unless transmission additions are made Does DR stifle development of newer, more efficient, and cleaner generation resources?

Q&A Questions? ON OFF