Practical experience of the Russian VVER design organization in the use of PSA for verification of compliance with single and double failure criteria.

Slides:



Advertisements
Similar presentations
Generic Pressurized Water Reactor (PWR): Safety Systems Overview
Advertisements

FRENCH PWR’S ULTIMATE HEAT SINKS THREATENED BY THEIR ENVIRONMENT
RISK INFORMED APPROACHES FOR PLANT LIFE MANAGEMENT: REGULATORY AND INDUSTRY PERSPECTIVES Björn Wahlström.
Issues Associated with the Development of Severe Accident Management Guidelines for CANDU Reactors Keith Dinnie Director, Risk Management Nuclear Safety.
Student Book © 2004 Propane Education & Research CouncilPage Performing Pressure Tests on Gas Distribution Lines Gas personnel must understand.
RELIABILITY IN A HIERARCHICAL MANAGEMENT. 1 LITERATURE REVIEW & METHODS THE RESULTS OF THE PRESENTATION CONTENT 2 3 INTRODUCTION AND OBJECTIVE.
MODULE “PROJECT MANAGEMENT AND CONTROL” EMERGENCY PLANNING SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP , Programme “Leonardo.
Overview of Incident at Fukushima Daiich Nuclear Power Station (1F) (Informal personal observations) April 2011.
Framatome ANP IP-EUROTRANS Meeting WP 1.5 Progress in safety approach development TEE, March Sophie EHSTER.
EUROTRANS - Helium cooled EFIT Probabilistic assessment of different DHR designs Karlsruhe, November Sophie EHSTER, Laurent VINCON.
AREVA NP EUROTRANS WP1.5 Technical Meeting Task – ETD Safety approach Safety approach for EFIT: Deliverable 1.21 Stockholm, May Sophie.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.5/2 Design Geoff Vaughan University of Central Lancashire,
Fukushima Incident Preliminary Analysis, Consequences and Safety Status of Indian NPPs Part-1 Dr. S.K.Jain Chairman & Managing Director NPCIL & BHAVINI.
FRANKLIN engineering group, inc. Start-up Shutdown Malfunction Plan Development and Implementation Duncan F. Kimbro
ACADs (08-006) Covered Keywords Containment Isolation, actuation logic, Description Supporting Material
FAULT TREE ANALYSIS (FTA). QUANTITATIVE RISK ANALYSIS Some of the commonly used quantitative risk assessment methods are; 1.Fault tree analysis (FTA)
> AREVA NP GmbH NRPP-G, AREVA NP All rights are reserved, see liability notice.
,Yalta,17-th Symposium of AER1 IMPACT OF CHANGED FUEL PERFORMANCES ON SAFETY BARRIER EFFECTIVENESS AT NORMAL OPERATION OF NPP WITH VVER A.V.
1 PED: equivalent overall level of safety PED Annex 1, clause 7: The following provision apply as a general rule. However, where they are not applied,
Fukushima Daiichi Nuclear Plant Event Summary and FPL/DAEC Actions.
Long-term loss of all AC power supply sources for Belene NPP November 1, 2015 Reliability, Safety and Management Engineering and Software Development Services.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.5/1 Design Geoff Vaughan University of Central Lancashire,
TACIS Project: R8.01/98 – TRANSLATION, EDITING AND DIFFUSION OF DOCUMENTS (Result Dissemination) Probabilistic Safety Analysis Technology (PSA) TACIS R3.1/91.
March 11, 2011 to Present. Presentation Overview Reactor Design and FeaturesChronology of EventsCurrent Status of Each ReactorRecovery Actions Kashiwazaki-Kariwa.
International Atomic Energy Agency 1 Grid, Industrial involvement and procurement Akira OMOTO DIR, NENP.
Regional Meeting on Applications of the Code of Conduct on Safety of Research Reactors Lisbon, Portugal, 2-6 November 2015 Diakov Oleksii, Institute for.
IAEA Training Course on Safety Assessment of NPPs to Assist Decision Making System Analysis Workshop Information IAEA Workshop City, Country XX - XX Month,
Risk-informed On-Line Maintenance at Cofrentes NPP IAEA Training Course on Safety Assessment of NPPs to Assist Decision Making Workshop Information IAEA.
IAEA Training Course on Safety Assessment of NPPs to Assist Decision Making Workshop Information IAEA Workshop Defence in Depth Safety Culture Lecturer.
Erman Taşkın. Information security aspects of business continuity management Objective: To counteract interruptions to business activities and to protect.
Safety Assessment of General Design Aspects of NPPs (Part 2) IAEA Training Course on Safety Assessment of NPPs to Assist Decision Making Workshop Information.
Teknologi Pusat Data 12 Data Center Site Infrastructure Tier Standard: Topology Ida Nurhaida, ST., MT. FASILKOM Teknik Informatika.
Low Power and Shutdown PSA IAEA Training Course on Safety Assessment of NPPs to Assist Decision Making Workshop Information IAEA Workshop City, Country.
Initiating Event Analysis IAEA Training Course on Safety Assessment of NPPs to Assist Decision Making Workshop Information IAEA Workshop City, Country.
IAEA Training Course on Safety Assessment of NPPs to Assist Decision Making Diablo Canyon NPP Maintenance Rule Program Workshop Information IAEA Workshop.
MEHB 513 Introduction on nuclear technology assignment GROUP MEMBERS:ID: SEEH CHONG CHIN ME YEE QIAN WAHME TING DING PINGME LIM JIA YINGME
Process Safety Management Soft Skills Programme Nexus Alliance Ltd.
Nuclear Battery Battery.  Reactor –Core Metallic fuel core (U-10%Zr) –Reactivity control Movable reflectors –Shutdown system Shutdown rod and reflectors.
Workshop on Risk informed decision making on nuclear power plant safety January 2011 SNRC, Kyiv, Ukraine Benefits and limitations of RIDM by Géza.
Version 1.0, May 2015 BASIC PROFESSIONAL TRAINING COURSE Module VIII Integrated risk informed decision making Case Studies This material was prepared by.
Version 1.0, May 2015 SHORT COURSE BASIC PROFESSIONAL TRAINING COURSE Module V Safety classification of structures, systems and components This material.
Version 1.0, July 2015 BASIC PROFESSIONAL TRAINING COURSE Module VII Probabilistic Safety Assessment Case Studies This material was prepared by the IAEA.
World Health Organization
BASIC PROFESSIONAL TRAINING COURSE Module V Safety classification of structures, systems and components Case Studies Version 1.0, May 2015.
Liquid LVs propellant consumption control terminal system
Saint- Petersburg State University of Aerospace Instrumentation
DCPP Performance Based on NRC Performance Indicators
Approaches and measures aimed at ensuring safety, preventing severe accidents in new RF NPP designs Gutsalov N.A. 10/03/2016.
Approach to Practical Elimination in Finland
Complementarity of deterministic and probabilistic approaches
Diversity analysis for advanced reactor design
BASIC PROFESSIONAL TRAINING COURSE Module III Basic principles of nuclear safety Case Studies Version 1.0, May 2015 This material was prepared.
International Topical Conferences on Nuclear Safety, IAEA, June 6-9, 2017, Vienna Analyses of DEC Events in the Czech Republic and their Implementation.
leaks thru rupture sticks open closed
NRC Event Number – Event Date
Federal Environmental, Industrial and Nuclear Supervision Service
BASIC PROFESSIONAL TRAINING COURSE Module V Safety classification of structures, systems and components Version 1.0, May 2015 This material was.
Session Name: Lessons Learned from Mega Projects
Severe accident management at Paks NPP
Summary of the Earthquake and Situation of the Kashiwazaki-Kariwa NPP
IAEA International Conference on Topical Issues in Nuclear Installation Safety, 6-9 June, 2017 Investigation of performance of Passive heat removal system.
BASIC PROFESSIONAL TRAINING COURSE Module VII Probabilistic Safety Assessment Case Studies Version 1.0, July 2015 This material was prepared.
BASIC PROFESSIONAL TRAINING COURSE Module VI Deterministic safety assessment Version 1.0, May 2015 This material was prepared by the IAEA and.
Version 1.0, May 2015 SHORT COURSE
RSFs & categorisation 20 May, 2019.
Approaches and measures aimed at ensuring safety, preventing severe accidents in new RF NPP designs Gutsalov N.A. 10/03/2016.
THE ROLE OF PASSIVE SYSTEMS IN ENHANCING SAFETY AND PREVENTING ACCIDENTS IN ADVANCED REACTORS Moustafa Aziz Nuclear and Radiological Regulatory Authority.
Mikael Olsson Control Engineer
New Regulatory Requirements in Japan
HSE Requirements for Pipeline Operations GROUP HSE GROUPE (CR-GR-HSE-414) EXECUTIVE SUMMARY This rule defines the minimum HSE requirements related to the.
Presentation transcript:

Practical experience of the Russian VVER design organization in the use of PSA for verification of compliance with single and double failure criteria A.Lyubarskiy, V.Morozov JSC “Atomenergoproekt” Russian Federation, Moscow Email: Lyubarskiy_AV@aep.ru I.Kuzmina, Consultant Russian Federation, Moscow Email: irina.kuzmina@yahoo.com

INRODUCTION JSC “Atomenergoproekt”, Moscow, is a design organization that is part of the integrated group of companies of the “Atomstroyexport” (ASE). The first unit with NPP-2006M (“generation 3+” design) of JSC “Atomenergoproekt” is already operating at Novovoronezh NPP (NVNPP-2) A number of other units are at various stages of construction in Russia, Turkey and Bangladesh The design provides an enhanced level of safety and efficiency through the use of innovative design solutions, namely, the combination of two-trains active safety systems (in some cases with additional redundancy of active elements within each train) The design provides a two-train structure with regard to connections of active elements with support systems (power supply, control, information representation). Passive systems, along with active safety systems, participate in performing all basic safety functions providing a time window sufficient to connect additional facilities used in the design basis accidents. Nevertheless, taking into account the two-train structure of active safety systems, including emergency power supply systems, the justification for fulfilling a number of safety criteria requires additional consideration. It is necessary to take into account not only the states with the operation of the unit at power, but also the shutdown states of the unit, in which part of the safety systems can be disabled or can be taken out of service for scheduled maintenance In particular, it is required to justify compliance with the single failure criterion (SFC), as well as the "N+2 failures" criterion Which in fact is an extension of SFC

DIAGRAM OF THE EMERGENCY CORE COOLING SYSTEM (ECCS) OF NVNPP-2 Example of a two-train system with internal redundancy

FORMULATION OF THE FAILURE CRITERIA (in accordance with EUR(D) [1]) Single failure criterion (SFC) : "Safety under design conditions is ensured if, with each postulated individual IE, all basic safety functions are guaranteed to be performed by a complex of safety systems, taking into account an IE-independent single failure in any part of this system complex and in any design conditions in which it’s work is required”. Moreover, in addition to the postulated single failure, the following is considered (see 2.1.3.4A [1]): Non-detected failures Failures, which are the consequential failures of the postulated single failure Failures caused by the IE (e.g. loss of the train of the ECCS system with leakage of the primary circuit in the injection line of equivalent diameters > 1/3 of the pipe diameter) According to 2.1.3.4F [1], failures of passive components may not be considered for SFC if they are designed, manufactured and assembled in accordance with the specified high quality requirements (e.g. pipelines, heat exchangers, tires, etc.) "N + 2 failure" criterion: "Since in the normal operation mode, preventive maintenance of certain equipment performing safety functions may be provided, in each individual case, the concept N + 2 (Unavailability due to maintenance plus SFC) in accordance with the minimum number of N redundant elements required for the function being performed and the design conditions under which this function may be required." At the same time, since this criterion refers to complex sequences exceeding the SFC conditions, its fulfilment can be demonstrated on the basis of a realistic (non-conservative) approach to safety analysis. Note that for AES-2006M, N = 1 (one element is needed for performing safety function)

ASSESSMENT OF COMPLIANCE WITH THE FAILURE CRITERIA The assessment of the design compliance with criteria requires an analysis of the detailed list of postulated initiating events Of all dependencies between structures, systems and components The analysis should consider a huge number of combinations of failures and repair states of equipment and should take into account all explicit and implicit dependencies potentially leading to inability to perform critical safety functions The probabilistic safety assessment (PSA) is an effective tool, which allows the most complete and justified confirmation of the fulfilment of the above criteria

SIMPLIFIED FORMULATION OF THE FAILURE CRITERIA SFC requires that for all design basis postulated initiating events there will be no single failure of the equipment or operator error that can lead to the core damage With this All failures dependent upon IE are considered Check valves failures are considered Passive components and components with reliability equivalent or better than passive components may not be considered Mobile equipment is not credited «N+2 failures» criterion requires that SFC is satisfied with account for equipment under planned maintenance For NVEAS-2 design «N+2 failures» criterion is satisfied if : For at-power operation: planned maintenance is not allowed and SFC is satisfied At shutdown, when planned maintenance is performed: SFC is satisfied even with account for unavailability of the equipment under maintenance

SFC – DETERMINISTIC ASSESSMENT OF THE DESIGN (1) Emergency shutdown of the reactor is carried out by an emergency protection system Designed with appropriate backup in the initiating and executive parts. Residual heat removal is carried out by active safety systems (SS) consisting of two redundant independent trains All active components check valves inside each train are reserved (with the exception of diesel generators (DGs)). The localization function is performed by the passive component (primary containment) and the active ventilation system of the inter-enclosure space (2 trains) => failures of which cannot be induced by the design basis accidents. A two-train sprinkler system removes heat and reduce pressure in the containment, and also helps to limit the release of radioactive products beyond the contaminant boundaries=> failures of this system cannot be induced by the design basis accidents With deenergizing and failure of one DG, another DG remains in operation (there are no failures dependent on the design basic accidents) SFC does not apply to passive components reactor vessel and steam generator, refuelling pool, primary and secondary containment, pipelines in the safety trains

SFC – DETERMINISTIC ASSESSMENT OF THE DESIGN (2) In operating states with opened reactor (before combining the volumes of the reactor shaft and the refuelling pool to carry out the refuelling), there are two trains of the emergency and planned cooling system (EPCS) In each train, the active parts are reserved. Scheduled maintenance (SM) of safety systems trains is not allowed in these states. During refuelling, when the volumes of the reactor and the refuelling pool are combined and scheduled maintenance on a safety system train is allowed, operator has sufficient time to connect alternative systems to compensate water losses. Conclusion => structure of safety systems (SS) of NVAES-2 design satisfies SFC

Illustration to Justification of Compliance with SFC (for ECCS) On the diagram the leak location, dependent failure and independent failure leading to complete failure of 1 ECCS train Equipment ineffective due to single failure Leal location Dependent failure Single failure

Illustration to Justification of Compliance with SFC (for ECCS) On the diagram the passive component failure leading to complete failure of 1 ECCS train is shown Канал не эффективен из-за единичного пассивного отказа

Illustration to Justification of Compliance with SFC (for ECCS) Reserve of the 1 train is lost due to IE 2 train is lost due to single passive failure SF – leak compensation is maintained by remaining part of the 1-st train and HA-2 with PHRS 1 train is effective 2 train

Illustration to Justification of Compliance with SFC (for ECCS) 1-st train is lost due to IE and single failure 2 train is effective SF – leak compensation is maintained by the 2-nd train and HA-2 with PHRS 1 train 2 train

«N+2 failure» Criterion - DETERMINISTIC ASSESSMENT (1) When the unit is operating at power, Scheduled maintenance of equipment of safety systems is not allowed Therefore, in this state, the "N+2 failure" criterion is automatically satisfied The design justifies the permissible time for repairs at power using the criterion of the minimum frequency of severe core damage, the value of which is significantly lower than 1E-06 per year When a single train is put into unscheduled repair of a system, the redundant components in another train (with the exception of the DGs) ensure the compliance with the "N+2 failure" criterion without the use of passive systems. In case of station black-out, heat removal from refuelling pool is done in a passive way, the water reserve (about 10 days) is sufficient to fulfil the autonomy criterion (6h) Providing sufficient time for connecting an additional heat removal system from the refuelling pool based on an alternative independent from designed safety systems heat transfer circuit to the ultimate heat sink using mobile DG and dry cooling tower Connecting a mobile DG also makes it possible to use a sprinkler system to reduce the pressure in the containment In all cases, the function of heat removal from the reactor and the refuelling pool is carried out, the limitation of radioactivity releases is ensured by the contaminant, the integrity of which is maintained

«N+2 failure» Criterion - DETERMINISTIC ASSESSMENT (2) In the state of shutdown for refuelling Planned maintenance on safety systems is allowed only when volumes of the reactor shaft and the pool are combined In case of failure of the second DG during loss of of-site power lthe time reserve for fuel assemblies uncovery is at least 80 h (about 10 hours before the boiling point) An additional system of heat removal from the pool will remove heat from the total volume of the reactor-pool, preventing the boiling away of the coolant. Conclusion => the "N+2 failure” criterion is satisfied for all operational states

ASSESSMENT OF COMPLIANCE WITH FAILURE CRITERIA USING PSA (1) Deterministic justification of the compliance with the criteria obviously does not guarantee the completeness, in particular There is no explicit consideration of failures caused by initiating event There is no comprehensive analysis of dependencies from the support systems (instrumentation and control, cooling water, power supply, ventilation systems) and between support systems that can violate the “N+2 failures” criterion. The most effective way to verify the compliance of the design with the criteria is an analysis based on the PSA One of the most important elements of PSA is the construction of a logical model that takes into account all interrelations between systems and equipment, both intra- system and inter-system The analysis of such a logical model using mathematical tools based on the application of Boolean logic allows identifying the minimum combinations of failures and operator errors sufficient to damage the core for the entire range of possible initiating events, including the events falling in the design extension conditions envelope These combinations are usually called "minimal cutsets" (MCSs) If the calculation of the model is organized in such a way that there is no truncation on probability, it can be ensured that all MCSs containing at least two of the following: equipment failures and/or operator error and/or basic events representing maintenance unavailability are identified

ASSESSMENT OF COMPLIANCE WITH FAILURE CRITERIA USING PSA (2) The analysis of the MCSs allows confirming: Compliance with the single failure criterion (in addition to the deterministic analysis) if it is shown that there are no MCSs containing initiating event and one equipment failure or one operator error. Compliance with the criterion "N + 2 failure", if it is shown that there are no MCSs containing initiating event, unavailability of the equipment due to maintenance and repair (planned or not planned) and one equipment failure or one operator error. The developed full-scale Level 1 PSA for NVNPP-2 [3] allowed revealing all MCSs containing up to four basic events. MCSs containing more than four basic events are not of interest, since for them both criteria are obviously satisfied Based on the results of the analysis presented in Table 1, it can be concluded that the analysis of MCSs confirms the compliance with the SFC and the "N + 2 failures” criterion in the NVNPP-2 design

ASSESSMENT OF COMPLIANCE WITH FAILURE CRITERIA USING PSA (3) Analysis of Minimal Cutsets Conclusion 1. Review of MCSs containing only an IE (single basic event) The MCSs contain only the following initiating event caused by passive components failures directly leading to core damage: SGVR – steam generator rupture SGCR- steam generator header rupture RPRV – reactor vessel rupture These IEs are not part of the design envelope and do not require to be considered for compliance with SFC and “N+2 failure” criterion. Compliance with the SFC and “N+2 failure” criteria is not required. 2 Review of MCS containing two basic events   The MCSs, in addition to the IE identifier, contain basic events with “RPS” symbols. Such basic events are part of a simplified model of the reactor scram system, calculated outside the framework of the PSA model. The reactor scram system is designed in such a way that there are no single and double failures for any IE, leading to system failure. SFC and “N+2 failure” criteria are satisfied. The MCSs, in addition to the IE identifier, contain basic events with common cause failures that represent at least two equipment failures. The MCSs, in addition to the IE identifier, contain basic events with USBT symbols. Such basic events are part of a simplified model of a control system, calculated outside the framework of the PSA model. The USBT system is designed in such a way that there are no single and double failures for any IE, leading to its failure. 3. Review of MCS containing three basic events TheMCSs, in addition to the IE identifier, contain basic events with maintenance unavailability (identifier “___М”) and passive components (filters, heatexchangers, buses, electrical assemblies). Failures of passive components may not be considered when compliance with SFC and “N+2 failure” criterion is verified. Compliance with SFC and “N+2 failure” criteria is not required. The MCSs include: design extension IE «Steamline rupture and leak from primary to secondary circuit”, unavailability due to maintenance and single failure. Thus for these cutsets SFC is not fulfilled; however, for design extension conditions compliance with the criteria is not required. Other MCSs containing three basic events include: IE, unavailability due to maintenance and common cause failure. 4. Review of MCS containing four basic events Other MCSs containing four basic events include: IE, unavailability due to maintenance and two additional components failure or human errors. There are no MCSs with “conditional” basic events because the model is developed as a symmetric model.

CONCLUSIONS Requirement for implementation of PSA for justifying compliance with failure criteria Level 1 PSA model for NVNPP-2 was used as a tool for the analysis of the compliance with SFC and “N+2 failure” criterion for all operating modes of the plant The analysis procedure was developed and applied; it included: Calculation of the PSA model without probability truncation limit in order to identify all MCSs containing up to four basic events (up to three basic events if the PSA model is symmetric). The software used to build the PSA model, it should be possible to identify all the MCSs containing up to four basic events regardless their probability. Analysis of the MCSs for the absence of cutsets violating SFC and "N+2 failure" criterion. The analysis performed confirms the compliance with the SFC and “N+2 failure” criteria for NVNPP-2 design Complementary to deterministic assessment

REFERENCES [1] European utility requirements for LWR nuclear power plant, Revision D, October 2012 [2] Probabilistic Safety Assessment (PSA). Volume 1. Level-1 PSA. Book 3. PSA final report for internal initiating events for full power operation and shutdown modes, NW2O.B.120.&.&&&&&&.0103&.022.HH.0001, АО «Atomenergoproect», 2014