Scope management Chapter 5 Copyright ©2016 Pearson Education, Inc.

Slides:



Advertisements
Similar presentations
ELC 347 project management Day Agenda Questions Assignment 3 graded –3 A’s, 5 B’s, 2 C’s, 1 D, 2 F’s and 2 answered the wrong questions Assignment.
Advertisements

Day 8 ELC 347/BUS 348/PSA 347.
Project Management 6e..
Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall 3.1.
Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall 3.1.
Defining the Project CHAPTER FOUR Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
ELC 347 project management Week 5. Agenda Assignment 2 re-graded –Missing case 2.3 found and graded Assignment 3 Graded –Could have used more effort –case.
Project Management Session 7
Project Management Lecture 5+6 MS Saba Sahar.
Scope Management Chapter 5.
Copyright © 2009 Pearson Education, Inc. Publishing as Prentice Hall Essentials of Systems Analysis and Design Fourth Edition Joseph S. Valacich Joey F.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Essentials of Systems Analysis and Design Fourth Edition Joseph S. Valacich Joey F.
What’s a Project? AD642. Why the Emphasis on Project Management? Copyright 2011 John Wiley & Sons, Inc. 1-2  Many tasks do not fit neatly into business-as-usual.
Scope Management Chapter 5 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall5-1.
5-1Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Scope Management Chapter 5.
Scope Management Chapter 5.
DEFINING THE PROJECT CHAPTER 4.
Week 2 Seminar: Project Scope Management
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
Scope Management. 5-2Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Scope Project scope is everything about a project –
Scope Management Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Chapter 5 Learning Objectives After completing this chapter,
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
Copyright © 2009 Pearson Education, Inc. Publishing as Prentice Hall Chapter 3 Managing the Information Systems Project 3.1.
~ pertemuan 4 ~ Oleh: Ir. Abdul Hayat, MTI 20-Mar-2009 [Abdul Hayat, [4]Project Integration Management, Semester Genap 2008/2009] 1 PROJECT INTEGRATION.
David M. Kroenke and David J. Auer Database Processing Fundamentals, Design, and Implementation Appendix B: Getting Started in Systems Analysis and Design.
Project Charter 1.Overview / Background Section 2.Governance / Authority Section 3.Approach Section.
Module Four, Session One Develop Project Charter.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson PowerPoint Presentation by Charlie Cook The University of West Alabama Defining the Project Chapter.
Project Management 6e..
Chapter 11 Project Management.
Part II Project Planning.
Project Management 6e..
Project Planning: Scope and the Work Breakdown Structure
IF 3507 Manajemen Proyek Perangkat Lunak
Managing the Information Systems Project
Project Plan <Publish Date>
Project Management BBA & MBA
Systems Analysis and Design in a Changing World, 4th Edition
Chapter 4 Defining the Project.
Project Management -- Defining the Project
Information Technology Project Management – Fourth Edition
SCOPE MANAGEMENT Information Technology Project Management
SCOPE MANAGEMENT Information Technology Project Management
Project Management 3. Project Management Plans
Project Integration Management
TechStambha PMP Certification Training
Information Technology Project Management – Fifth Edition
Project Management.
Chapter 3 Managing the Information Systems Project
Chapter 3 Managing the Information Systems Project
Defining the Project Chapter 4.
DEFINING THE PROJECT CHAPTER 4.
Where We Are Now. Where We Are Now Defining the Project (100) Step 1: Defining the Project Scope Step 2: Establishing Project Priorities Step 3: Creating.
Defining the Project Step 1: Defining the Project Scope
Information Technology Project Management
Scope Management Chapter 5
Project closeout and termination
Project Management Process Groups
Chapter 3 Managing the Information Systems Project
Planning a Project Chapter 2.
Effective Project Management: Traditional, Agile, Extreme
Project Integration Management
Project Integration Management
Scope Management Chapter 5
Chapter 3 Managing the Information Systems Project
Project Overview.
Executive Project Kickoff
Chapter 2 Managing the Information Systems Project
Chapter 3 Managing the Information Systems Project
Presentation transcript:

Scope management Chapter 5 Copyright ©2016 Pearson Education, Inc.

Chapter 5 Learning Objectives After completing this chapter, you should be able to: Understand the importance of scope management for project success. Understand the significance of developing a scope statement. Construct a Work Breakdown Structure for a project. Develop a Responsibility Assignment Matrix for a project. Describe the roles of changes and configuration management in assessing project scope. Copyright ©2016 Pearson Education, Inc.

PMBOK Core Concepts Project Management Body of Knowledge (PMBoK) covered in this chapter includes: Develop Project Charter (PMBoK 4.1) Plan Scope Management (PMBoK 5.1) Collect Requirements (PMBoK 5.2) Define Scope (PMBoK 5.3) Create WBS (PMBoK 5.4) Validate Scope (PMBoK 5.5) Control Scope (PMBoK 5.6) Copyright ©2016 Pearson Education, Inc.

Project Scope Project scope is everything about a project – work content as well as expected outcomes. Scope management is the function of controlling a project in terms of its goals and objectives and consists of: 1) Conceptual development 4) Scope reporting 2) Scope statement 5) Control systems 3) Work authorization 6) Project closeout Copyright ©2016 Pearson Education, Inc.

Conceptual Development The process that addresses project objectives by finding the best ways to meet them Key steps in information development: Problem or need statement Requirements gathering Information gathering Constraints Alternative analysis Project objectives Business case Copyright ©2016 Pearson Education, Inc.

Statement of Work (SOW) A SOW is a detailed narrative description of the work required for a project. Effective SOWs contain: Introduction and background Technical description of the project Timeline and milestones Copyright ©2016 Pearson Education, Inc.

Statement of Work Components Background Objectives Scope Task or Requirements Selection Criteria Deliverables or Delivery Schedule Security Place of Performance Period of Performance Copyright ©2016 Pearson Education, Inc.

Project charter Many organizations establish after the SOW A document issued by the project initiator or sponsor formally sanctioning existence of project and authorizes project manager to begin applying organizational resources to project activities Is created once project sponsors have done their “homework” to verify that there is: a business case for the project elements of project are understood company-specific information for the project has been applied Demonstrates formal company approval of the project Copyright ©2016 Pearson Education, Inc.

Scope Statement Establish project goal criteria to include: cost schedule performance deliverables review and approval “gates” Develop management plan for project Establish a Work Breakdown Structure Create a scope baseline Copyright ©2016 Pearson Education, Inc.

Work Breakdown Structure (WBS) A deliverable-oriented grouping of project elements which organizes and defines the total scope of the project. Each descending level represents an increasingly detailed definition of a project component. Project component may be products or services. Copyright ©2016 Pearson Education, Inc.

Work Breakdown Structure purpose WBS serves six main purposes: Echoes project objectives Organization chart for the project Creates logic for tracking costs, schedule, and performance specifications Communicates project status Improves project communication Demonstrates control structure Copyright ©2016 Pearson Education, Inc.

Defining a Work Package Lowest level in WBS Deliverable result One owner Miniature projects Milestones Fits organization Trackable Copyright ©2016 Pearson Education, Inc.

Partial wbs (figure 5.3) Deliverables are major project components Work Packages are individual project activities (lowest level in WBS)

Sample WBS in MS Project 2013 (figure 5.6) Copyright ©2016 Pearson Education, Inc.

Organizational Breakdown Structure Organizational Breakdown Structure (OBS) allows Work definition Owner assignment of work packages Budget assignment to departments OBS links cost, activity & responsibility Copyright ©2016 Pearson Education, Inc.

Intersection of the WBS and OBS (figure 5.7)

Cost Account Rollup Using OBS (figure 5.9)

Responsibility Assignment Matrix (figure 5.10) Copyright ©2016 Pearson Education, Inc.

Defining a Project Work Package Work package forms lowest level in WBS. Work package has a deliverable result. Work package has one owner. Work package may be considered by its owner as a project in itself. Work package may include several milestones. Work package should fit organizational procedures and culture. The optimal size of a work package may be expressed in terms on labor hours, calendar time, cost, reporting period, and risks. Copyright ©2016 Pearson Education, Inc.

Work Authorization Cost Plus The formal “go ahead” to begin work. Contractual documentation possesses some key identifiable features: Contractual requirements Valid consideration Contracted terms Contracts range from: Lump Sum or Turnkey Cost Plus Copyright ©2016 Pearson Education, Inc.

Scope Reporting Determines what types of information reported, who receives copies, and when and how information is acquired and disseminated. Typical project reports contain: Cost status Schedule status Technical performance status Copyright ©2016 Pearson Education, Inc.

Reasons Why Projects Fail Politics Naïve promises Naïve optimism of youth Startup mentality of fledgling entrepreneurial companies “Marine Corps” mentality Intense competition caused by globalization Intense competition caused by appearance of new technologies Intense pressure caused by unexpected government regulations Unexpected and/or unplanned crises Copyright ©2016 Pearson Education, Inc.

Types of Control Systems Configuration control Design control Trend monitoring Document control Acquisition control Specification control Copyright ©2016 Pearson Education, Inc.

Configuration management Configuration Management is defined as: A system of procedures that monitors emerging project scope against the baseline. It requires documentation and management approval on any change to the baseline. Baseline is defined as: The project’s scope fixed at a specific point in time – for example, the project’s scheduled start date. Copyright ©2016 Pearson Education, Inc.

Project changes Occur for one of several reasons: Initial planning errors, either technological or human Additional knowledge of project or environmental conditions Uncontrollable mandates Client requests Copyright ©2016 Pearson Education, Inc.

Project Closeout The job is not over until the paperwork is done… Closeout documentation is used to: Resolve disputes Train project managers Facilitate auditing Closeout documentation includes: Historical records Post project analysis Financial closeout Copyright ©2016 Pearson Education, Inc.

Summary Understand the importance of scope management for project success. Understand the significance of developing a scope statement. Construct a Work Breakdown Structure for a project. Develop a Responsibility Assignment Matrix for a project. Describe the roles of changes and configuration management in assessing project scope. Copyright ©2016 Pearson Education, Inc.

Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall