Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13

Slides:



Advertisements
Similar presentations
Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
Advertisements

Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
Goal of the week: Stable beams with trains of 200 & 248 bunches 1 OP summary of week 40 R. Bailey, J. Uythoven & J. Wenninger.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
LHC Wire Scanner Calibration
Wednesday
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Thursday 25/11/10 & Night Work on: 16:15 Inject fill #1520
MD Report 24 June 2012 Machine coordinators: Barbara Holzer, Mike Lamont MD Coordinators: Ralph Assmann, Giulia Papotti, Frank Zimmermann MD#2 News & Plan.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
LHC Operation Week 41 Coordination G.Arduini, M. Lamont
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
LHC operation in week 42 Coordination:, Malika Meddahi, Joerg Wenninger Thanks to OP crews, HW and SW teams + experiments Aims for the week Cure aperture.
Saturday 1.3 e32 Overnight Morning
Tuesday 23/11/10 8:00 Physics fill #1511 dumped
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Lost at 12:05 to power converter (RTQX2.R1) problem
Friday 31st August & night
Mike Lamont, Jorg Wenninger
Week 35 – Technical Stop and Restart
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
Wire almost entirely through beam before BLM triggers dump
Yesterday’s morning’s controls issues
Friday Morning 7:30 injection for fill 2908
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Thu 6/4 End of fill #2470. ~1 pb-1 in 4 hours. Dumped by CMS BCM.
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Thursday Fill 1364 (24 bunch) dumped at 07h
Saturday Nov Stop proton operation. Switch back to ions
Thursday 26th July 13:21 Fill 2880 beam dumped
Thursday – Morning Energy matching at injection with H CODs
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Thursday 22 September 2011.
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
LHC Morning Meeting - G. Arduini
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Wednesday h18: 228b fill lost just before start of ramp.
Another Immortal Fill….
Tuesday End of fill 1393 Movement of suspicious Roman pots OK
Wed 12/10 09:30 – 10:30 Ramp down of ALICE solenoid to 50% nominal field on request of ALICE. Increase of the vacuum (e-cloud in this area that has not.
Wednesday 6.10 Morning: Quench test at 450 GeV
HI2011 Commissioning Status
Monday 152 bunch operation summary
Tuesday
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13 Average bunch current 1.04e11 Emittance (reconstructed from lumi) 1.8 micron Approx beam size at IP 41 micron Approx beam-beam tune shift 0.021 Time in collisions 61 seconds Integrated luminosity 8.5 nb-1 Stored beam energy 14.9 MJ 11/16/2018 LHC status

No apparent transverse blow-up Beam size No apparent transverse blow-up Beam loss spike Beam size 11/16/2018 LHC status

Going into collision Separation bump Beam loss spike Luminosity (BRAN) Beam current 11/16/2018 LHC status

Into collision Separation bump Beam loss Still cleaning beam dump The LHC beams will cross each other and experience perturbations as a result of the beam-beam effect at the interaction points, which can result in emittance growth and halo creation. The beam-beam force is approximately linear for small offsets and highly non-linear for larger offsets with peaks in growth close to 0.3 and 1.5 σ separation S. M. White, H. Burkhardt, S. Fartoukh, T. Pieloni Still cleaning beam dump On set of losses at: 6.4 sigma Peak losses at: 1.4 sigma 11/16/2018 LHC status

Tune amplitudes 11/16/2018 LHC status

Bunch by bunch 11/16/2018 LHC status

Wednesday 13th October 06:30 Start preparation for van der Meer scans somewhat tardily 10:15 Following 9:30 meeting - stop vdM scans and move to: aperture scans of problematic region in injection septa L2 TL steering and associated correction in LHC Over to the I-team… 11/16/2018 LHC status

Wednesday evening 23:25 Clean injection of 24 bunches into ring 1 00:20 BLM intervention IP7 Thanks and apologies - Christos Zamantzas & Mariusz Sapinski intervention to exchange the processing module that had triggered a dump request on 12/10/2010 19:03. The trigger come from a failure in the optical link transmission and the unavailability of data to process in a 40 us cycle. Looking the history of statuses of this card shows a slow and constant degradation and we expect it to have another failure in the short future (few hours to days). Thresholds changed on warm elements – MQWs up a factor of 10 11/16/2018 LHC status

Thursday morning Filled for physics and brought the beams into collisions: 10e32 peak lumi reached in both IP 1 and 5 with 248 bunches/ring. 11/16/2018 LHC status

Fill 1418 Peak luminosity ~1.03e32 Beam current 2.62/2.61 e13 Average bunch current 1.04e11 Emittance (reconstructed from lumi) 2.4 micron Approx beam-beam tune shift 0.016 Stored beam energy 14.9 MJ 11/16/2018 LHC status

Options If MSI solution not stable: Fill time thorough to weekend Vacuum: open up: install mobile pumping unit, inject Neon open and fix pump, bake, pump 3 -4 days Move technical stop to Mon-Tues-Wed-Thurs next week 11/16/2018 LHC status

Backup MD

OP Periodic loss maps Orbit shift versus TCT check: Betatron loss map done week 40. Orbit shift versus TCT check: collide 1 bunch and check the TCT center change as compared to predicted orbit change. All in one ramp, squeeze, collide - 1 shift Plus test of 'dynamic' references for the OFB (varying Xing.separation bump): injection, then test of ramp + first part of squeeze IR aperture at 3.5 TeV 50 ns – pilot runs After 3-4 fills with ~400 bunches Push beam-beam tune shift with 150 ns one test already performed with #1410 11/16/2018 LHC status

BI studies – list to be updated Check the linearity of the fast BCT’s in the new configuration for nominal bunches Tune the High BW/Low Gain fast BCT calibration for the coming ion run Measure the High BW/Low Gain fast BCT sensitivity limit and linearity for low intensity bunches (ion run) Re-check BPM sensitivity limit Calibrate the abort gap over the whole ramp Check the abort gap acquisition gate timing resolution and stability Commission BGI in preparation to ions Check BSRT/BGI/BWS cross-calibration including corresponding emittance logging Test and compare bunch/bunch profile measurement via BWS and/or BSRT PLL studies during ramp continued JJG: for all this, we would need the 2 rings for a few hours at 450 GeV then a ramp and again a few hours at 3.5 TeV. This would be really difficult to fit in a 4 hour slot. 8 would be perfect but we could try with 6. 11/16/2018 LHC status

Other Abort Gap Cleaning – on at injection for physics continue testing Injection studies 32 Bunches when required (344 bunches) Injection studies with 50 ns Setting-up of the SPS with tighter batch spacing (225 ns) Quench test at 3.5 TeV – pilot beam Bernd & co 11/16/2018 LHC status

Experiments 50 pb-1 Alice – fill without dipole Totem – dedicated fill 12 fills@3 pb-1 ~ 12 good days Alice – fill without dipole Totem – dedicated fill LHCb – switch polarity vdM continued – count 1 – 2 shifts 11/16/2018 LHC status