LHC operation in week 42 Coordination:, Malika Meddahi, Joerg Wenninger Thanks to OP crews, HW and SW teams + experiments Aims for the week Cure aperture.

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
ADT Tune Measurement F. Dubouchet, W. Hofle, D. Valuch Acknowledgement: R. Calaga, F. Roncarolo, E. Bravin, shift crews New developments and tests on August.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Ion Commissioning: Thursday & Friday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
Machine Coordinators: G. Arduini, J. Wenninger
Saturday 21st April 00:33 Interlock during ramp on BLM HV
MD Report 24 June 2012 Machine coordinators: Barbara Holzer, Mike Lamont MD Coordinators: Ralph Assmann, Giulia Papotti, Frank Zimmermann MD#2 News & Plan.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
LHC summary week 32 Coordination: Mike Lamont & Jan Uythoven
LHC Operation Week 41 Coordination G.Arduini, M. Lamont
Status of LHC Operations
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Machine availability reaching well over 80%
Monday 18 October : Collimation system
Saturday 1.3 e32 Overnight Morning
Summary of Week 11: 14 – 21 March
Tuesday 23/11/10 8:00 Physics fill #1511 dumped
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
LHC operation in week 39 Coordination: Mike Lamont, Jan Uythoven, Malika Meddahi Thanks to OP crews, HW and SW teams + patient customers Aims for the week.
Summary of Week 16 G. Arduini, J. Wenninger
Lost at 12:05 to power converter (RTQX2.R1) problem
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 35 – Technical Stop and Restart
Friday 14th December - morning
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Friday morning 10:30 Optics measurements and corrections.
Wire almost entirely through beam before BLM triggers dump
Saturday 7th May Sat – Sun night
Programme for Saturday 10 July
(on behalf of the LHC team)
Summary Thursday h21: Stable beams fill #1303.
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
LHC Morning Meeting - G. Arduini
LHC - Week 38 Technical stop: Katy Foraz
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Wednesday h18: 228b fill lost just before start of ramp.
Another Immortal Fill….
Monday 27th August & night
Tuesday End of fill 1393 Movement of suspicious Roman pots OK
Saturday 26 November 2011.
Tuesday
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
HI2011 Commissioning Status
Monday 152 bunch operation summary
Saturday Morning used to complete the loss maps and asynch dumps (with RPs). All loss maps OK (B. Salvachua), but the off-p cleaning for B1 (Lead) was.
Presentation transcript:

LHC operation in week 42 Coordination:, Malika Meddahi, Joerg Wenninger Thanks to OP crews, HW and SW teams + experiments Aims for the week Cure aperture restriction in TI 2 MSI (TS week 42) Complete 312b stable beam period Complete tests for 32b injection 368bx368b stable beams 11/18/2018 LHC status

Week 42 in short Monday 18th October Loss maps Abort Gap cleaning at 450 GeV RF studies PLL commissioning Tuesday 19th 06:00 am to Friday 22nd October 17:30 Technical Stop – Coordination by Katy Foraz All work done and complete on schedule Friday 22nd October Night : recovering from TS Saturday 23rd October Until 16:00: stopped by various hardware problems (pre-pulse distribution crate, re-phasing, cryo losses) . Injection studies: B1 and B2 both ready for 32b injection Overnight: LHCb spectrometer polarity switched to positive. Test ramps with 1bx1b (dump validation) and 2bx2b (loss map on momentum) Sunday 24th October Stable beams, fill 1439, 312b, peak lumi 1.51e32 Stable beams, fill 1440, 368b, peak lumi 2.05e32 11/18/2018 LHC status

Week 42: Stable beams Date Fill # b # Inj. Fill dur. Peak L cm-2 s-1 Fill L nb-1 Dump 24 Oct. 1439 312 8b 16b 24b 10.5h 1.51e32 4200 Programmed dump TOTEM RPs in CMS length scale cal. 25 Oct 1440 368 16b 24b 32b 6+ 2.05e32 3200+ Emittance approx 2.3 um 11/18/2018 LHC status

Week 42: fill 1439 11/18/2018 LHC status

Fill 1440 11/18/2018 LHC status

Vacuum fill 1439 7E-8 11/18/2018 LHC status

Vacuum 368b 1.5E-7 11/18/2018 LHC status

Vacuum spike F1440 – Pt5 3.5E-7 11/18/2018 LHC status

Week 42 in numbers 4 days of TS Machine closed Friday at 18h30 - beam injected Sat. 04h30. Statistics over 3 days of beam operations: System faults : 10h  15% Stable beams : 16h  23% Setting-up without beam 17h  25% Setting up with beams : 25h  37% Week 42 peak luminosity: 2.05e32 cm-2s-1 Week 42 delivered luminosity: 7.5+ pb-1 LHC total integrated luminosity ~31 pb-1 11/18/2018 LHC status

From last week: Injection losses B1 Radiation survey and X-ray (Tue 12/10) have evidenced a clear aperture restriction at the transition between the injection septa MSIB/MSIA due to a non-conformity in the mounting of the interconnection Circulating beam Injected beam J-M. Dalin Conditions for injection degraded too much  decision to anticipate the week 44 TS to week 42.

Injection after TS - Brennan Goddard and team Injection of up to 32b checked for both beam. Trajectories and losses small again. Injection of 32b with batch spacing of 225 ns.  MSI aperture restriction fixed. No more problems– Acknowledgments to TE/VSC Tuning of IQC settings after the PFN changes. Finer tuning after collection some statistics.  Injection ready for 32b / 368b filling 11/18/2018 LHC status

Saturday 23 October 11/18/2018 LHC status

Loss maps – OP - Ralph Assmann - Daniel Wollmann Betatron loss maps 3.5 TeV with colliding beams (1x1) Both beams and both planes (one at a time). Leakage to IRs at the 0.1% level. No unexpected losses. Cleaning inefficiency: 2.2e-4 to 3.5e-4 Off-momentum loss map 3.5 TeV with colliding beams (2x2) Negative momentum offset (RF freq. +800 Hz). Leakage to IRs at the level of 1%. Final analysis to be done. 11/18/2018 LHC status

Betatron losses, B1 vertical Daniel Wollmann 11/18/2018 LHC status

Momentum losses (+800 Hz) 11/18/2018 LHC status

Abort Gap Cleaning Andrea Boccardi, Adam Jeff, Federico Roncarolo, Enrico Bravin, Wolfgang Hofle, Daniel Valuch, Verena Kain, Eliana Gianfelice, Malika Meddahi AG cleaning tested using the vertical damper for beam1 and beam 2. With the voltage and frequency that were used, no emittance growth was observed, no lifetime problems. 450 GeV, 1e11/ bunch. B1: buckets 1 and 31130, B2: buckets 1 and 31140. RF voltage was decreased in steps and cleaning of the beam leaking into the AG was observed. Experiment repeated with both beams in the machine. The beams were injected while the cleaning systems were on. No anomalous observation made  ready to be switched on during regular operation 11/18/2018 LHC status

Abort Gap monitor Adam Jeff – Andrea Boccardi Beam 1 Beam 2 11/18/2018 LHC status

Emittance measurements during AGC tests Federico Roncarolo 11/18/2018 LHC status

RF noise induced beam diffusion Philippe Baudrenghien and team Beam conditions: 4 x 4 b (1E10/bunch) both beams ramped to 3.5 TeV, no blow-up. Very short (400 ps long) bunches Motivation: Prepare for higher intensity next year when 2 new systems will be introduced: longitudinal damper (active only at inj.) and 1-Turn feedback (active all the time). These will add RF noise. Need to assess the margin. Data must be analyzed – no conclusions could be drawn online. 11/18/2018 LHC status

Preliminary results: from observation of BQM only, the bunch profiles suggest modification of bunch shape that goes from parabolic to triangular with the excitation. It was realized that the method for introducing the excitation in the cavity was not ideal. BFCT synchro error phase error sl 11/18/2018 LHC status

PLL commissioning - Marek Gasior–Ralph Steinhagen PLL kept lock during ramp- used as primary input to the Tune-FB Achieved 99% transmission for both beams PLL operation visible on life-time but always above 25 h Stable PLL gains depend on the ADT settings and varied by more than a factor hundred between ADT 'off' and 'on‘. Tune resolution acceptable and in agreement with FFT estimate. Emittances: Before ramp : B1-H = 1.8, B1-V = 1.6, B2-H = 2.6, B2-V = 2.9 3.5 TeV : B1-H = 3.3, B1-V = 2.7, B2-H = 3.6, B2-V = 3.2 >> suggests very strong emittance blowup ! Very encouraging results. Effect on emittance to be confirmed (or improved…). 11/18/2018 LHC status

What’s next? - 368b operation to continue for stable beams - 400+b operation stable beams - Switch to 50ns bunch spacing – to note: LHCb spectrometer polarity O.K. - Long list of “to-be-done” before the end of the p operation… Week 43 coordinators: Mike Lamont and Ralph Assmann 11/18/2018 LHC status

On the list of TBD before the end of p run Orbit shift vs TCT check – Joerg Wenninger + Ralph Assmann Push b-b tune shift with 150 ns – one test already performed with #1410 – Werner Herr Beta* measurement in IP8 – Rogelio Tomas IP aperture at 450 GeV (not 3.5 TeV) – Massimo Giovannozzi RF noise induced beam diffusion – P. Baudrenghien 11/18/2018 LHC status

On the list – Wolfgang Hofle Multi-bunch acquisition of the damper pick-ups signals, update - slot on Wednesday  to reboot crates Gain in ramp 50 ns set-up (2x4 hours) Abort gap cleaning 450 GeV and 3.5 TeV and cleaning of injection slot (see ABT) LHC status

On the list from ABT/BTP – Brennan Goddard Abort gap cleaning tests B1/B2 at 450 GeV and 3.5 TeV [2 shifts] + Calibrate the abort gap over the whole ramp (BI) Injection gap cleaning deployment tests, 450 GeV, B1/B2 [1 shift] MKI8.B2 fine timing adjustment (1st bunch in train always gets too large a kick) and also synchronisation checks [2 h] 50 ns bunch train injection for B2 [1 shift?]  Studies SPS-LHC emittance preservation at injection, and growth on flat bottom [1 shift]  Asynch dump tests 3.5 TeV for B1/B2, to check stability [1 ramp] 11/18/2018 LHC status

On the list from BI – J.J. Gras Check the linearity of the fast BCT’s in the new configuration for nominal bunches Tune the High BW/Low Gain fast BCT calibration for the coming ion run Measure the High BW/Low Gain fast BCT sensitivity limit and linearity for low intensity bunches (ion run) + Re-check BPM sensitivity limit Commission BGI in preparation to ions – started… Check BSRT/BGI/BWS cross-calibration including corresponding emittance logging – Test and compare bunch/bunch profile measurement via BWS and/or BSRT - to be continued – 4h with a ramp PLL studies during ramp continued