Minuteman Vocational Technical Regional High School Progress February 12th, 2018 – March 19th, 2018
March 15th View of Area A & B - Interior Excavation & backfill of underground plumbing elements in progress.
March 15th View of Area G – Facing North-West Steel Erection and Decking & Detailing Complete.
March 15th View of Area G – Second Floor Construction of edge form and installation of reinforcing in preparation for concrete slab on deck placement.
March 15th View of Area E – Facing West Concrete Foundations Complete. Building foundations completed on March 6th. Area C Steel Erection in progress in the background.
February 26th View of Area E South – Facing North Decking & Detailing activities in progress. March 15th View of Area E South – Facing South Decking & Detailing activities in progress.
March 15th View of Area F – Facing West Steel Erection Complete. Decking & Detailing Substantially Complete.
February 26th View of Area C – Facing East Steel Erection in Lower Level of Theater in progress. Forming of electrical duct back in progress.
March 6th View of Area C – Facing East Steel Erection in progress with the setting of steel columns. March 15th View of Area C South – Facing East Steel Erection in progress with upper framing being set.
March 16th View of Area C – Facing South Steel Erection of theater low roof in progress. Two crane pick required due to size and weight of roof beams.
Excavation & Foundation Progress 3/19/18. Building Foundations were completed on 3/6/18
Steel Erection Progress 3/19/18
March Construction Schedule Look Ahead: Area A+B Continue excavation & backfill for underslab utilities. Commence roof parapet framing and wood blocking. Installation of Roof Drain bodies. Place concrete slab on deck on Level 2. Area G Installation of Roof Drain bodies Commence roof and exterior framing. Area E – Lower Continue decking & detailing of steel. Area C Continue/Complete steel erection Commence decking & detailing of steel