Machine availability reaching well over 80%

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
:00 meetingEBH 1  8:40 – 9:30 access for MKB (dilution kicker) LBDS B2 – PLC exchange  Pre-cycle  11:17 – 12:50 RF problem with ion injection.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Week 13: R. Assmann, J. Wenninger
Ion Commissioning: Thursday & Friday
Wednesday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
Wednesday 8.9 External crossing angles:
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Day :00-11:30: Optics at 3.5 TeV Optics re-measured with AC-dipole. Excellent reproducibility. Small emittance increase from AC-dipole. Collapsed.
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Summary Friday h38: Ramp down and pre-cycle.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Summary of week 7 Hardware Commissioning:
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Monday morning 08:30 Start of rephasing MD. Dry tests in the morning.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
LHC Morning Meeting - G. Arduini
Thursday morning – optics correction
Tuesday TOTEM and transverse loss map (1) OK
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Monday – recovery from MKI flashover
LHC commissioning Week 38
Lost at 12:05 to power converter (RTQX2.R1) problem
Friday 31st August & night
Mike Lamont, Jorg Wenninger
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 36 plan Todo’s: And also: 12+b injection.
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Week 35 – Technical Stop and Restart
Week 36 Machine coordinators R.Assmann, R.Bailey
Planning at 5 o’clock meeting Friday
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Yesterday morning Held 1647 for a while – SPS kicker problem
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
Friday 23rd March 08:00 Access
Summary Thursday h21: Stable beams fill #1303.
Aims for the week Recover from technical stop and precycle at 10A/s
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Summary week 18 Intensity ramp up & production
Saturday Nov Stop proton operation. Switch back to ions
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Sat morning Until 12:40: Loss maps at injection
Summary for LPC (March 7th, Ralph Assmann)
Plan for 1 m b* J. Uythoven & J. Wenninger
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
LHC Morning Meeting - G. Arduini
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Tuesday
Daniel, Gianluca and Belen (for the Collimator team)
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Machine availability reaching well over 80% Summary of week 10 Last official week of beam commissioning: M. Lamont and J. Wenninger for the commissioning teams, Special thanks to collimation, optics and inject & dump teams. Machine availability reaching well over 80% 11/19/2018 LHC 8:30 meeting

Stable beams @ D-1 First stable beams at 18:05 on 13th March 2011 Filling scheme: 1 probe + 3 nominal bunches (2-2.5 um) L ~ 1.2E30 cm-2s-1 for ATLAS/CMS 11/19/2018 LHC 8:30 meeting

What an end for week 10 ! Protection validation ‘factory’, 1.38 TeV ramp & collisions, and finally stable beams at 3.5 TeV. 1.38 TeV 11/19/2018 LHC 8:30 meeting

No 2 First fill dumped after 7 hours at 01:00. Repeat H betatron loss map and asynch. dump test for B1. Refill – during the ramp shift crews realized that one bunch was in the wrong bucket. Dump and restart. Second fill 1615 in at 05:10. Bunch intensities slightly higher. Initial L ~ 1.5E30 cm-2s-1 for ATLAS/CMS. Lost at 07:20 – electrical network – EDF non-transparent tests.. 11/19/2018 LHC 8:30 meeting

Injection Inject and dump mode setup. Injection protection. TDI setup and protection validation. Completion of the TI8/2 collimator protection validation. 11/19/2018 LHC 8:30 meeting

Injection Multi-bunch injection. MKI energy tracking. ‘Pushed’ up to 8 bunches (75 ns) without problems. Injection of 24 and more bunches was ‘sacrificed’ in order to go ahead with collimation (for stable beams). MKI energy tracking. Checked interlocks on energy for MKI. ‘Abort gap keeper’ limits have been verified: Presently the last bucket for injection is 31181. Access needed to extend to 31241. 11/19/2018 LHC 8:30 meeting

Injection - SPS For almost the entire week the SPS injection kicker was missing a good fraction of its strength (1 out of 4 generators effectively missing !). Injection steering proved difficult. But emittances were good ! Was only discovered Saturday night !! Repair TODAY ! 11/19/2018 LHC 8:30 meeting

Dump BIS-LBDS teams have worked on the BIS-LBDS interface (optical receivers) on Wednesday since some issues had been observed during arming of the LBDS even after TSU firmware downgrade to 2010 version. Beam position interlocks in IR6. Interlock limits adjusted to new orbit (most changes in the range of a fraction of mm). Protection functionality tested. Extracted beam apertures (dump lines) were verified. Results are good and consistent with 2010. Dump with 14 out of 15 kickers was checked to be OK. Simulated with an orbit bump ! 11/19/2018 LHC 8:30 meeting

BLM firmware update BLM firmware was updated after vertical slice testing to fix an issue with the ‘capture’ buffer that was affecting the IQC (Inj. Qual. Check). Final validation of the firmware: BLM dump trigger initiated by sending a probe bunch on a closed collimator. Event chain and delays (100-120 microsec from injection to dump) were verified.

General MPS tests with beam Reaction time of FMCM installed on warm magnet circuit for fast detection of failures have been validated with beam. RQ5.LR3, RD34.LR7 at 3.5 TeV squeezed. Dump septa MSD checked at injection. RF frequency interlock validated (+- 100 Hz). Last SIS (Software Interlock System) interlocks checked. All interlocks now armed. Orbit surveillance throughout the cycle. 11/19/2018 LHC 8:30 meeting

Aperture The local triplet aperture was verified with local bumps, the beam edge is defined by a TCP – preliminary results IR1 V B1: 16 sigmas 16 in prev. meas. IR1 V B2: 14 sigmas 15 in prev. meas. IR5 H B1: 13.5 sigmas 15 in prev. meas. IR5 H B2: 13 sigmas 17 in prev. meas. 11/19/2018 LHC 8:30 meeting

Ramp & squeeze RT trims Ramp & squeeze cleaned and consolidated. Orbit corrector functions entirely cleaned on Thursday. Ramp Squeeze RT trims Orbit Tune 11/19/2018 LHC 8:30 meeting

Optics at 3.5 TeV squeezed Following the last global optics correction (in w9) the beta-beating in collisions is at the level of ~5%. 11/19/2018 LHC 8:30 meeting

Optics at 3.5 TeV squeezed b* measurements at IR1 and IR5 with AC-dipole and K-modulation. b* is extracted from the amplitude of the tune modulation when changing the gradient of triplet quadrupoles. 11/19/2018 LHC 8:30 meeting

Latest b* ‘Final’ b* values from K-modulation: Errors around 4-10%. Imbalance is 2.5 +- 8% in favor of CMS. Beam/plane IR5 IR1 B1H 1.50 1.53 B2H 1.48 1.57 B1V 1.52 B2V 11/19/2018 LHC 8:30 meeting

Collimation setup at 3.5 TeV Full collimation setup at 3.5 TeV before the squeeze. IR3, IR7, IR6 and TCTs. Typically 20-25 minutes / collimator thanks to improved SW tools. TCT setup at end of squeeze and for colliding beams. Setup time of 1.5 hours achieved. Collimation setup completed Friday late afternoon. Collimators driven by functions (also for interlocks) for: Ramp, Squeeze, Collide. 11/19/2018 LHC 8:30 meeting

Collimators in ramp & squeeze Ramp functions of the collimation system TCTs in squeeze 11/19/2018 LHC 8:30 meeting

Validation Extensive validation campaign between Friday evening and Sunday morning. List of validation steps for that were made for collimation and dump protection: Condition Betatron H Betatron V Dp/p + Dp/p - Dump Injection X Flat top Squeezed Collisions 11/19/2018 LHC 8:30 meeting

Loss maps Example of a betatron loss map @ 1.5 m beta* 11/19/2018 LHC 8:30 meeting

Validation results - collimation Preliminary of qualification tests (R. Assmann): Highest losses always at primary collimators. Leakage to cold magnets at 1e-4 level. Leakage to TCT's at 1.5m beta* as expected (1e-3 level). Leakage to TCTV's in IR1 and IR8 is at 1e-2 level for off-momentum loss maps. H collimators in IR3 produce a vertical halo that is intercepted at the vertical tertiary collimators. OK. No leakage of losses to the triplets observed. Interlock thresholds have been set. Summary: collimator and protection hierarchy is qualified for 1.5m beta*. The triplets are protected and the TCT's are safe themselves. 11/19/2018 LHC 8:30 meeting

Validation results – beam dump Preliminary analysis of qualification tests (B. Goddard): Leakage to TCTs with 1.5m beta* is the level of few e-4, as expected. No unusual losses seen on cold elements or elsewhere. All tests passed - ready for stable beams. 11/19/2018 LHC 8:30 meeting

Protection – to be done Repeat betatron loss map in H with colliding beams (better quality). Done for B1. Repeat asynchronous dump test with colliding beams with more intensity. Activate b* dependent interlocks (collimators). Update the collimator interlock threshold with new LVDT-settings offsets. 11/19/2018 LHC 8:30 meeting

1.38 TeV Test ramp and collisions for 1.38 TeV run (Sunday). Ramp: 320 secs (-> 1.38 TeV) + 280 secs (waiting for decay). Keep orbit constant (crossing and separation) in ramp. Ramp crossing angles to 0 when bringing beams into collisions. Some collisions observed… a bit more work needed. 11/19/2018 LHC 8:30 meeting

1.38 TeV optics Beta-beat rather similar to 1.2 TeV case. Peak beating around 20% 11/19/2018 LHC 8:30 meeting

Next Final MPS checks + approval. Then progressive intensity increase over the next 2 weeks. 32, 64, 104, 152, 200 bunches. Injection of multiple bunches (> 8 !). For physics and for the scrubbing run. Abort gap and injection cleaning. And more details to tune… 11/19/2018 LHC 8:30 meeting

Thank you to all who contributed to this remarkable startup ! Thank you everybody ! Thank you to all who contributed to this remarkable startup ! Special applause for our optics team ! Rarely seen during daytime! R. Thomas & friends 11/19/2018 LHC 8:30 meeting