Tram cycle safety improvements programme Martyn Lings Active Travel Officer The City of Edinburgh Council First few slides are a quick background on cycling in Edinburgh and the Active Travel Action Plan (ATAP)
Phase 1: Cycle Lane Crossings & Give Space Awareness Raising Autumn 2017 First few slides are a quick background on cycling in Edinburgh and the Active Travel Action Plan (ATAP)
Phase 2: Advanced Stop Lines and Awareness Raising Spring 2018 Spokes and Sustrans consulted through the design process. First few slides are a quick background on cycling in Edinburgh and the Active Travel Action Plan (ATAP)
Phase 3: Early Green Release Signals, Junction Changes & Cycle Lanes Consultation – 14 March – 11 April 2018 Construction: Autumn/Winter 2018 Spokes, Sustrans and Living Streets consulted through the design process. Early Green Release Signals – 14 junctions
Waverley Bridge x S St Andrews Street Topshop Topman
South Charlotte Street x Princes St
Junction of Dalry Rd, Grosvenor Street and West Maitland Street Two options for Grosvenor St proposed: 1. Build out with two way traffic 2. One way out (turning left only) Modelling, Counts and TRO’s
Haymakert Station, Clifton Terrace
Haymarket Yards
Cultins Road, Edinburgh Park Tram Station
Phase 4 – larger scale junction changes Central Edinburgh Transformation Project - Public and stakeholder consultation Summer 2018 Sustrans Deputy Director, Daisy Narayanan, appointed as Project Director West End Junction