ELCITA UPDATE April 2018.

Slides:



Advertisements
Similar presentations
Peco Facet Sewage Water Treatment Plant
Advertisements

Briefing on Cape Town’s Integrated Rapid Transit System 2009.
 UAB Vilniaus waters - the largest water company in Lithuania, which operates not only in the city of Vilnius, but also the district, Svencionys and.
Improving Public Works Efficiency. Evaluating what we do: Are we doing the right work?
FERNS PARADISE AGM July 15th, 2012 Presentation By Management committee 1AGM, July 15th, 2012.
21 st Sep Election Process July & August
ELCITA Update 25 th August Update – Estate Management E – Toilets 8 e-toilets operational and work order placed for 4 more e-toilets Under Ground.
Procedures and Time Line DescriptionDate 1) Design and LayoutDefined Area, Water Level, Structure Level, Finalize design and Layout 3 rd. Week Sept 2)
October E – Toilets 8 e-toilets operational and work order placed for 4 more e-toilets. Under Ground Drainage System Completed & Tender Published.
Greetings from Spa Eco City & the creators of Frangipani Country Estates!! Greetings from Spa Eco City & the creators of Frangipani Country Estates!! 1.
Madison Avenue Reconstruction Department of Planning and Development.
10BLOCKS2REINVENT Environment based on Community.
November E – Toilets 8 e-toilets operational and 4 more e- toilets work in progress. Under Ground Drainage System Completed & Tender Published.
ESS KAY CONSULTANTS MEP CONSULTANTS. WHAT IS MEP ??? MECHANICAL ELECTRICAL MEP PLUMBING.
Gujarat’s First Metro City.  Life at Dholera Metro City is actually an incredible moment to expertise.Dholera Metro City  This town is loved by millions.
Greetings from Spa Eco City & the creators of Frangipani Country Estates!! Greetings from Spa Eco City & the creators of Frangipani Country Estates!! 1.
Clarification Meeting: Provision of Cleaning, Horticulture & General Maintenance Services for Majuba Rail Project 04 February 2016.
Light Rail Project Community Light Rail Support Plan Committee 14 August 2014 Kensington Kingsford.
City Manager Report – May, 2016 Presented to: Minot City Council City Manager Report – May, 2016 Presented to: Minot City Council Lee Staab, City Manager.
June Skywalk M/s mayaPRAXIS have submitted the draft report - Preliminary Feasibility Study on Skywalk system for Electronics city phase 1. E.
Excellence - Integrity - Service - Creativity - Communication Courts of Canterbury HOA Meeting Rufe Snow Reconstruction Project Construction Update Keith.
Water Management System Review of the Existing System – Sources Intended to be used Bore wells Open Wells Tanker Supply KWA Rain water (??) STP Recycled.
Implementation of Smart Cities mission DAVANAGERE SMART CITY LIMITED
We would like to list below an update on the Progress of the Project.
ELCITA UPDATE April 2017.
ELCITA UPDATE February 2017.
ELCITA UPDATE March 2017.
ELCITA UPDATE JULY 2017.
ELCITA Update December 2015.
Town of Brighton, Department of Public Works
View display boards and speak one-on-one with staff
ELCITA UPDATE January 2017.
Review of Implementation of Smart Cities Mission
ELCITA UPDATE AUGUST 2017.
ELCITA UPDATE November 2016.
San Luis Potosi – New plant April 24th 2015
ELCITA Update May 2016.
ELCITA Update April 2016.
Review of Implementation of Smart Cities Mission
Review : Implementation of Smart Cities Mission
Manchester’s CSO Program: A Look Behind and a Look Ahead
Eagle P3 Project Update RTD Board of Directors Sept. 2, 2014.
We would like to list below an update on the Progress of the Project.
ELCITA UPDATE SEPTEMBER 2017.
ELCITA UPDATE October 2016.
ELCITA UPDATE August 2016.
Water Reclamation Plant Feasibility Study Update May 28, 2014
ELCITA UPDATE November 2017.
Electronics City Industrial Township Authority
Atal Mission for Rejuvenation and Urban Transformation (AMRUT)
ELCITA Update March 2016.
ELCITA UPDATE March 2018.
We would like to list below an update on the Progress of the Project.
How to Live More Gently on Earth Steps to Take For Us in the United States to Lower Resource Consumption Reduce Water Use Remove front lawns: Plant vegetation.
We would like to list below an update on the Progress of the Project.
Community Assistance Center Update May 2, 2016
ELCITA UPDATE July 2016.
ELCITA UPDATE December 2016.
SE 12th Street Roadway Improvements February 8, 2005.
OVERVIEW & PROGRESS Presentation before the Sub Collector cum Sub Divisional Magistrate, Cuddalore.
ELCITA Update January 2016.
ELCITA UPDATE September 2016.
Upscaling Basic Sanitation for the Urban Poor (UBSUP)
A133 IPSWICH ROAD SCHEME COMMUNICATION UPDATE ( )
A133 IPSWICH ROAD SCHEME COMMUNICATION UPDATE ( )
River Story This is the story of a river travelling through its catchment. It begins in the higher parts of the catchment where the rain runs off the slopes.
ELCITA UPDATE June 2019.
ELCITA UPDATE August 2019.
ELCITA UPDATE July 2019.
ELCITA UPDATE April
Presentation transcript:

ELCITA UPDATE April 2018

FOB across Hosur Road

RCC Drain & Footpath West Avenue 11 (Cyient Road) West Avenue 9 (3M Side) West Avenue 11 (Cyient Road) West Avenue 9 (3M Side)

RCC Drain & Footpath West Avenue 8 (Devon Innovation Side) West Avenue 8 (Pump House Side)

Railing Work

ABR STP - 9 KLD

RCC Pedestal Work East Avenue 3

New street light pole installed West Avenue 3

4 –Way RMU installation near 3M – West phase

Tenders Infrastructure works Supply & Fixing Chain-link Fencing at East Phase. Construction of Footpath along West Avenue 5. Construction of RCC Culvert, Electronics City West & East Phase. Communication related Media and communication Management, Smart City Laying of OFC 48F for Ring 2 & 3 Command center S/W platform

Commencement Certificate Occupancy Certificate Town planning Details FY 2013-14 FY 2014-15 FY 2015-16 FY 2016-17 FY 2017-18 FY 2018-19 (As on 04-05-2018 Khatha 6 18 12 11 02 Building License 2 13 24 31 30 Commencement Certificate 1 4 7 17 8 01 Occupancy Certificate Nil 23

SWM Tendering Process Results QCBS EVALUATION Technical Weightage Technical Score = 70% of the Technical Weightage Financial Amount Financial Score = (L1 Amount/Bidder Amount) * 30 Consolidated Score = Technical Score + Financial Score Position/Ranking WWMNCS 53.25 37.28 351260 2.14 39.41 3 Sweep Smart 47.75 33.43 273823 2.74 36.16 4 Hasirudala 55.00 38.50 25000 30.00 68.50 1 Saahas 74.25 51.98 314252 2.39 54.36 2

E-city Segregates 2.0 3rd set of companies on board 1.Tescom 2.Flextronics 3.Momentive 4.Tata power solar 5.Tuv Rheinland 6.C-Dot 7.Teknic Euthner 8.Lemon Tree Hotels 9.Elcia Cluster 10. Zone by the park Kick off meeting on 6th April Provided Appreciations' and certificates to the 2nd phase participated companies

A – Tree event on Urban Biodiversity at ELCITA on 28th March To gather again after 6 months to check on individual developments. An event that brings together different vendors who work on Biodiversity – Seeds, plants, organic food/products, garden equipment's -Vertical garden ,composting for companies ELCITA can keep a database/some equipment's maybe of these vendors for references. A trip to Wipro/A tree - Suggestion

ELCITA Organic waste treatment plant.

World water day celebration at ISBR on 22/03/2018

E-waste and compost February 5 tons 400 Kgs March April 250 kgs Month E-waste collected Compost sold February 5 tons 400 Kgs March 1 tons 2315 Kgs April 250 kgs 500 kgs Shredding of leaves Pouring Treated water to compost beds

Sewage Treatment Plant Sl. NO. Month Total Raw Water Total Treated Water Efficiency 1 February 4595 4465 97.2% 2 March 5612.2 5567 99.2% 3 April 5647 5548 98.3% Sl. No. STP with Quantity Description of Work Status of work 1 CSTP -300 KLD Plumbing & installation work of New FLOW METER at CSTP Commissioning work for Flow meter Brought 2 more companies for sewage pick up service and 1 for Treated water supply Work completed Work under progress Work going on 2 E-SBR -7 KLD Submergible Pump at Final Treated Tank is repair and re-install 3 SBT – 8 KLD Removal of unwanted plant growth surrounding SBT Chamber Work completed 4. ABR SBT - 9 KLD DEWATS Anaerobic Baffle Reactor STP Civil work

Description of Activities Sl. No. Description of Activities Description of Work Status of work 5 World water day World water day celebration at ISBR on 22/03/2018 Attended 6 Rain Water Recharge Pit Construction of Rain water Recharge pit of 2 Nos. Completed Rain Water Recharge Pit

Plumbing & Installation work of FLOWMETER AT 300KLD CSTP

Security and Traffic related