Saturday 1.3 e32 Overnight Morning

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Ion Commissioning: Thursday & Friday
Wednesday
Wednesday 8.9 External crossing angles:
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Summary Friday h38: Ramp down and pre-cycle.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Monday 11/07: Recovery Plenty of accesses.
LHC Operation Week 41 Coordination G.Arduini, M. Lamont
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Thursday morning – optics correction
LHC operation in week 42 Coordination:, Malika Meddahi, Joerg Wenninger Thanks to OP crews, HW and SW teams + experiments Aims for the week Cure aperture.
Machine availability reaching well over 80%
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
LHC Morning Meeting - G. Arduini
LHC commissioning Week 38
Lost at 12:05 to power converter (RTQX2.R1) problem
Friday 31st August & night
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 35 – Technical Stop and Restart
Monday February 28th 8h00: Injection
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Planning at 5 o’clock meeting Friday
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
Wire almost entirely through beam before BLM triggers dump
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Sunday
Summary Thursday h21: Stable beams fill #1303.
Aims for the week Recover from technical stop and precycle at 10A/s
Monday 24 October hours of 25ns MD
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Summary week 18 Intensity ramp up & production
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Thursday 22 September 2011.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
LHC Morning Meeting - G. Arduini
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Thursday 30th September De-bunching test
Thursday Aperture studies (foreseen until ~ midday, nothing done) Problems with single bunch B2 from SPS (extraction kicker not enabled) Setting.
Coordination: Eva Barbara Holzer, Mike Lamont
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Another Immortal Fill….
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Tuesday End of fill 1393 Movement of suspicious Roman pots OK
Daniel, Gianluca and Belen (for the Collimator team)
HI2011 Commissioning Status
Monday 152 bunch operation summary
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Saturday 1.3 e32 Overnight Morning Struggle with beam 1 injection – inter-septa obstruction has worsened Morning re-steer around obstruction 11/21/2018 LHC status

Vacuum . 11/21/2018 LHC status

Vacuum Vacuum activity at the transition MSIB-MSIA during the last fill. It seems not related to losses in that area - Arcing? A first spike in vacuum (this is a ion pump) can be observed on Friday 08/10 morning. The level of the vacuum remains then high starting from ~10:30 in the morning. A spike can also be seen at the moment of the intervention in the tunnel (12/10 at ~10 AM) and finally some more activity on 16/10 night V. Baglin: Regarding the pressure, it is hard to say that what you observed for VPIB.245.6L2.B is due to arcing. I remark that this pressure increase appears during the ramp and at the flat top (this night, the 12th, the 11th, the 8th). There is also a signal the 12th at 10h, but this is when we were in the tunnel as said in the logbook. The equivalent ion pump (VPI.245.6R8.R) in MSI8R is under-range (less than 1e-9 mbar).  11/21/2018 LHC status

Injection adjustments Checked losses with 4b injected and different steerings in TI2 Resteered TI2 again to reduce losses in MSI-situation now is -5 mm in V and + 2 mm in H. reduction in losses by factor 10, with 4b Additional 1 mm H and -1 mm V bump Adjusted matching bump in H in LHC to reduce inj oscillations - now near acceptable limit. Need 1 unit of V bump and 1.5 units of H. Adjusted all TI2 TCDIs around new trajectory Opened auxiliary inj prot collimator TCLIB.6R2 by 2 sigma New references and thresholds trimmed in everywhere for collimators and correctors Test fill with 24b OK for transvserse losses (dumped on uncaptured beam) Should (just) be able to fill like this but MSI needs repairing asap as we cannot realistically keep chasing after this degrading situation Brennan Goddard & Malika Meddahi (young Goddards doing homework in CCC) 11/21/2018 LHC status

Injection issues - summary Un-captured beam from SPS Thursday-Friday night Swept across TDI by injection kick – dumped by LHCb Tracked down to 800 MHz in SPS Obstruction in MSI at IP2 Last week & Saturday morning Capture losses in LHC Saturday afternoon Beam swept by injection kickers grazing TDI, proving BLM beam dump down stream Very dependent on longitudinal beam quality from the injection Very low tolerances in LHC – general issue with fast losses at 450 GeV – dumping beam after the event 11/21/2018 LHC status

Saturday afternoon continued 14:00 re-filling for physics Looking OK re transverse losses - only the Q.L2 slightly above the IQC threshold, and not at BLM warning for 24b. 1st attempt lost to un-captured beam Next at over-injection SPS adjusted – shorter bunches 16:32 MKI is faulty. Spark on BEAM2 MKI magnet D at the end of the kick. --> vacuum interlock, IQC interlock, no fast interlock. Acknowledged vacuum interlock. Restart system with normal SoftStart. Some vacuum activity visible on magnet D during the KISS. 11/21/2018 LHC status

Saturday afternoon continued 17:07 2 beam 1 dumped because of error on LBDS : generator fault on LBDS.UA63, E. Carlier - access in UA63 ASI-Monitoring module corrupted. Hard restart of the module solved the problem. Source of the corruption not identified. Strong suspicion of a glitch on the safety power supply. No hardware modification performed. Access in ALICE in the shadow of the access in point 6 19:39 end access Pre-cycle #1427 312b – slightly lower bunch currents – defensive move at injection 11/21/2018 LHC status

Bunch intensities 11/21/2018 LHC status

Beam losses at all primaries versus time 11/21/2018 LHC status

BLM BLM Christos Zamantzas 1/2 optical links from card 29.R5 measured on surface, comes from tunnel no MP issue, only availability to fixed next week – 2 in tunnel, 1 in tunnel if problem over night – could disable all 6 monitors on the quad concern – in arc so should be enough coverage. (Mariusz or Anitka) Checking historically, the operational link has been a stable one and has not given single errors in weeks (didn’t check further back) and might be able to sustain the link for days. 11/21/2018 LHC status

Might need an access for QPS before going back to 3.5 TeV Weekend planning Friday 07:00 – 19:00 vdM Friday evening Check injection Friday overnight Physics 312b 12 hour fill Saturday Remedial injection Saturday overnight Sunday 10:00 TL BL calibration 4 hours Sunday 14:00 Quench test 6 hours Sunday overnight Might need an access for QPS before going back to 3.5 TeV 11/21/2018 LHC status

MSI MSI aperture restriction was again found to be worse early this morning, and despite very carefully adjusting the transfer lines, we have had to increase the beam position offset through the septum again, with all the attendant adjustments. There seemed to be some vacuum activity (ion pump currents) on the MSI which seems correlated with the times we see reduction in aperture, and with higher beam current. Little to no margin left 11/21/2018 LHC status

Options MSI solution is not stable Weekend is covered Monday can be covered – the list is long… Do we open up the MSI next week? Install mobile pumping unit, inject Neon open and fix pump, bake, pump around 3 -4 days “we are ready to intervene in MSI2L and remove the RF fingers if required. We will put them back during Xmas break And move technical stop to Tues-Wed-Thurs next week no show stoppers when first proposed last week Vincent Baglin Katy Foraz, Simon Baird 11/21/2018 LHC status

To-do list

OP Periodic loss maps Orbit shift versus TCT check: Betatron loss map done week 40. Orbit shift versus TCT check: collide 1 bunch and check the TCT center change as compared to predicted orbit change. All in one ramp, squeeze, collide - 1 shift Plus test of 'dynamic' references for the OFB (varying Xing.separation bump): injection, then test of ramp + first part of squeeze IR aperture at 3.5 TeV 50 ns – pilot runs After 3-4 fills with ~400 bunches Push beam-beam tune shift with 150 ns one test already performed with #1410 11/21/2018 LHC status

ABT Abort gap cleaning tests B1/B2 at 450 GeV and 3.5 TeV [2 shifts] Injection gap cleaning deployment tests, 450 GeV, B1/B2 [1 shift] Loss calibration on TCDIs downstream TI2 and TI8 [4 h] High intensity 32b injection for B2 - filling and P6 interlock checks for 350 and 400b schemes [4h] MKI8.B2 fine timing adjustment (1st bunch in train always gets too large a kick), and also synchronisation checks [2 h] 50 ns bunch train injection for B2 [1 shift?] Studies SPS-LHC emittance preservation at injection, and growth on flat bottom [1 shift] Asynch dump tests 3.5 TeV for B1/B2, to check stablity [1 ramp] Brennan Goddard 11/21/2018 LHC status

BI studies – list to be updated Check the linearity of the fast BCT’s in the new configuration for nominal bunches Tune the High BW/Low Gain fast BCT calibration for the coming ion run Measure the High BW/Low Gain fast BCT sensitivity limit and linearity for low intensity bunches (ion run) Re-check BPM sensitivity limit Calibrate the abort gap over the whole ramp Check the abort gap acquisition gate timing resolution and stability Commission BGI in preparation to ions – started… Check BSRT/BGI/BWS cross-calibration including corresponding emittance logging Test and compare bunch/bunch profile measurement via BWS and/or BSRT PLL studies during ramp continued JJG: for all this, we would need the 2 rings for a few hours at 450 GeV then a ramp and again a few hours at 3.5 TeV. One shift Quench test at 3.5 TeV – pilot beam Bernd & co 11/21/2018 LHC status

Experiments 50 pb-1 total (22 delivered so far) 10 fills@3 pb-1 ~ 10 good days Alice – fill without dipole Totem – dedicated fill Totem – 90 m optics LHCb – switch polarity – plus test ramp (combine with BI plus map) 11/21/2018 LHC status