Summary of Week 11: 14 – 21 March

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
07:30 – 10:30 Asynchronous dump test with Beam 2. No issue found. FIDEL update. Now chromaticity decay corrected. 12:13 Beam dump due to problem in the.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
LHC Status Fri Morning 3-June
Wednesday
Wednesday 8.9 External crossing angles:
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Machine Coordinators: G. Arduini, J. Wenninger
Friday 18/03 07:15 Test ramp with pilot after the test of dynamic FIDEL correction. Ramp was OK, but fill was stopped due to the trip of several RQTFs.
Thursday 25/11/10 & Night Work on: 16:15 Inject fill #1520
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Monday fill with 1092 bunches (6 h stable beams)
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
LHC Operation Week 38 Coordination G.Arduini, R.Bailey
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
LHC commissioning Week 38
Summary of Week 16 G. Arduini, J. Wenninger
Lost at 12:05 to power converter (RTQX2.R1) problem
Scrubbing progress - 09/12/2012
Friday 31st August & night
Friday day 00:51 Fill #1862 Beams lost to inner triplet skew quad power converter fault. Delivered lumi 33 pb-1 Access required for repair RQSX3.L1 converter.
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
LHC Operations overview Week 28 – Getting back
Sunday morning Recovering from 400 kV disturbance.
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Friday :00 machine setup for luminosity run. Better b-to-b stability from injectors. 01:58 stable run with 228 bunches 11:00 luminosity leveling.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday morning 10:30 Optics measurements and corrections.
Yesterday’s morning’s controls issues
Finally.... We had to wait a long time.... We had many problems....
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Sunday
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Summary Thursday h21: Stable beams fill #1303.
Aims for the week Recover from technical stop and precycle at 10A/s
Monday 24 October hours of 25ns MD
Thu 6/4 End of fill #2470. ~1 pb-1 in 4 hours. Dumped by CMS BCM.
Thursday Fill 1364 (24 bunch) dumped at 07h
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Another Immortal Fill….
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Wednesday 26 October 2011.
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
31/3/2010 Difficult day… but at the end stable beams.
Saturday 26 November 2011.
Tuesday
Sunday 12th 00:29 Stable beam fill #1864. Initial lumi 1.1e33
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Tuesday
Presentation transcript:

Summary of Week 11: 14 – 21 March First week of intensity ramp up Gianluigi Arduini and Jan Uythoven for the LHC teams Aim of the week: Physics with 100 + bunches, Luminosity > 1e32 136 bunches ! 21/03/2011 LHC 8:30 meeting

136 bunches: Lumi lifetimes: GOOD Sunday 20/03 05:50 Dump fill #1639 Cryo lost S18 matching section. Temperature oscillation in QRL line C affecting DFB MB. Second fill of 64 bunches after 7 hours in coast 09:22 Cryo recovered – access CMS 10:15 Injecting for physics 11:40 Stable beams 64 bunches – 3rd fill 18:00 Dump 21:30 Stable beams 136 bunches – 1st fill 06:00 Operator dump RB S12 and S23 tripped during ramp up, active filter 136 bunches: Lumi lifetimes: GOOD 21/03/2011 LHC 9:00 meeting

Injecting pilot + trains of 8 + trains of 24 Great job from the injector shift crews who changed settings from 8 to 24 bunches (75 ns) in 5 minutes! But bunches could be a bit more equal… BPMS IP6 Interlock test 24b 8b 21/03/2011 LHC 8:30 meeting

Vacuum Experimental Areas 136 bunches ATLAS had vacuum spikes at about 21:00... until 21:15 it went up by a couple of orders of magnitude, by now recovered 10%. 1e-6 mbar !!! M.Jimenez 21/03/2011 LHC 8:30 meeting

136 bunches - Vacuum activity starting Vacuum around the injection kickers MKI IP2 and IP8 136 bunches IP2 – Kicker tank changed 64 bunches IP8 – not opened 21/03/2011

Vacuum at the IPs during fill o-night 21/03/2011 LHC 8:30 meeting

Timing Distribution problem Overview of the week 160 x 1030 cm-2s-1 Lumi’s 2e13 DC BCTs Inj. tests 48 b 32 b 64 b 136 b Skip 8 b Stable Beams: 3b Timing Distribution problem Tot. L = 8.7 pb-1 MPS tests 21/03/2011 LHC 8:30 meeting

Fills of the week Tot. L = 8.7 pb-1 1634 32 1.18/1.12 30 2.8 0.51 # bun ches Average bunch population@coll [1011 p] Initial luminosity [1030 cm-2s-1] eHV @coll (from init. Lumi) Integrated luminosity [pb-1] Coast duration [hours] Turn-around to next fill 1634 32 1.18/1.12 30 2.8 0.51 06:00 02:25 1635 1.18/1.17 33 2.7 0.009 00:06 05:00 (RF) 1636 1.16/1.15 0.56 02:41 1637 64 1.18/1.15 66 1.3 06:40 02:45 (Inj) 1638 1.14/1.14 2.6 1.34 07:05 05:50 (CRYO) 1639 65 1.21 06:20 02:30 (MPS) 1640 136 1.18/1.18 148 3.7 08:30 Tot. L = 8.7 pb-1 21/03/2011 LHC 8:30 meeting

rMPP ok for every intensity step Check list filled in for each step On edms 21/03/2011 LHC 8:30 meeting

What kept us busy during the week Test ramp with 8 bunches Aim: validation ramp and squeeze with 75 ns beam and transverse feedback ON through the squeeze Larger oscillations observed on B2 H tune corrections – tune feedback locking on mains harmonics leading to QPS trigger on RQTF.A23B2 and RQTF.A34B2 8 bunches 21/03/2011 LHC 8:30 meeting

Test ramp with 8 bunches Mains harmonics, not side bands Reduced gain of the transverse feedback all through the ramp Easier with 32+ bunches ! 100 Hz 21/03/2011 LHC 8:30 meeting

Wednesday Evening Problem with the timing distribution RQTD.A12B2 and RQTD.A67B2 tripped off due to large trim request – still not completely understood Resulting dump was proper, but badly timestamped Post Mortem and XPOC data New release of the MTG firmware failed Took 36 h to convince that MPS is ok to continue 32 b Mean time 1.38 TeV prep. FIDEL, decay comp. at injection Validation tests Jump in Time 21/03/2011 LHC 8:30 meeting

Continue the intensity increase: RF dump on Friday night Following a modification introduced during the Xmas stop, the RF FGCs crash if they receive 3 or more simultaneous timing events (as in the case of the automatic optimization of all the IPs) The bug has been identified and fixed by Q. King – new firmware version to be released at the next best occasion. This explain why the problem occurred when using the application to optimize the separation simultaneously at all IPs For the moment we do not to use the 'optimize all' option in the luminosity scan application! Continue the intensity increase: 136 bunches = 8.5 MJ/beam 21/03/2011 LHC 8:30 meeting

Plans Coordinators this week R.Assmann, M.Lamont Recover RB trip Next: fill another 136 bunches This week (possible program) Increasing to 200 bunches 1.38 TeV run Injection studies, prepare scrubbing 21/03/2011 LHC 8:30 meeting

Outstanding Injection of 96 bunches Timing distribution FGC firmware update Collimation system controls fix 1.38 TeV setting-up Crossing angle all zero: OK TCTs to set up & loss maps Interlock tests for the roman pot RF voltage limit interlock Longitudinal blow-up Wire scanners Abort gap cleaning Injection gap cleaning 21/03/2011 LHC 8:30 meeting

Timing Distribution problem Overview of the week 160 x 1030 cm-2s-1 Lumi’s 2e13 DC BCTs Inj. tests 48 b 32 b 64 b 136 b Skip 8 b Stable Beams: 3b Timing Distribution problem Tot. L = 8.7 pb-1 MPS tests 21/03/2011 LHC 8:30 meeting