Cannon Falls Roundabout Modification Project Jai Kalsy | Project Manager January 25th, 2017
Agenda 5 mins Staff Introductions Project Purpose/Needs 10 mins Time Topic 5 mins Staff Introductions Project Purpose/Needs 10 mins Project Description 20 mins Construction Staging/Traffic Impacts Schedule & Next Steps 15 mins Questions & Answers 11/22/2018
Introductions Jai Kalsy – Project Manager/Plans Engineer Paul Schauer – Construction Engineer Adam Wellner Assistant Traffic Engineer Greg Paulson – Assistant District Engineer Mike Dougherty – Public Affairs Coordinator 11/22/2018
Project Purpose/Need Trucks having trouble using east roundabout Noticeable curb height at east ramp roundabout– issues with loads. Constructability issue. Trucks feeling pinched negotiating all roundabouts Purpose Replace east ramp roundabout inside curb with updated curb design. Alleviate roundabout pinch points by moving island curb and signing back Construct with minimal traffic impacts, advanced planning and notice. 11/22/2018
Staging Plan – Stage I 11/22/2018
Staging Plan – Stage II 11/22/2018
Staging Pan – Stage IIIa 11/22/2018
Staging Plan – Stage IIIb 11/22/2018 Optional Tagline Goes Here | mndot.gov/
Staging Plan – Stage IV 11/22/2018
Schedule Begin Construction – Mid April to Early May (weather permitting) Contract Time: 30 working days (weekend work not anticipated) End Construction: Mid June 11/22/2018
Questions? Jai Kalsy Jai.Kalsy@state.mn.us 507-286-7545 11/22/2018