Modifications at Existing WTP: $450,000 Construct New WTP: $39,100,000 Upgrade Existing RWPS: $1,300,000 Construct New RWTM: $5,000,000 Construct New FWTM: $13,300,000 1
Estimated Costs (Includes engineering) Project Element Modifications at existing WTP $450,000 Construct new 6 MGD water treatment plant $39,100,000 Upgrade existing raw water pump station $1,300,000 Construct new raw water main (12,000 lf) $5,000,000 Construct new finished water main (36,000 lf) $13,300,000 Total Estimated Cost $59,150,000 (Includes engineering)
Next Steps Make critical decisions (project timing, growth/demand projections, project phasing) Project schedule if decision made to proceed today
Questions?