Carleton College Summer 2018 Science and Campus Construction Plan Carleton College Summer 2018 Science and Campus Construction Plan* January 11, 2018 *Subject to change
New Building Completion Summer 2019 Auditorium New Building Completion Summer 2019 New Building We chose to locate the new construction so that it would fully integrate with Olin and Hulings—this is key for fostering interdisciplinary work.
Construction Milestones New Building Completed Summer 2019 Olin Renovation Summer 2019 – Summer 2020 Hulings Renovation – Vivarium Summer 2018 Remaining Hulings Renovation Summer 2019 – December 2020
New Building Construction Schedule January 2018 – March 2018 Footings and Foundations February 2018 – July 2018 Structural Steel and Slab on Metal Decks May 2018 – October 2018 Exterior Skin May 2018 – January 2019 Mechanical, Electrical, Plumbing and Fire- Protection Rough-in July 2018 – January 2019 Interior Framing September 2018 – May 2019 Interior Finishes
Summer 2018 Impact on Olin and Hulings Connection to Hulings Auditorium Summer 2018 Impact on Olin and Hulings New Building East Earmuff 3rd floor classroom bump-out We chose to locate the new construction so that it would fully integrate with Olin and Hulings—this is key for fostering interdisciplinary work. Lower level Vivarium
East Earmuff Location
Ground Floor Olin; Construction Highlighted Blue Ground Floor Olin; Construction Area Highlighted Blue Cognitive Science/Psychology Chemistry Laboratories
Ground Olin—Temporary Walls Enlarged Olin Ground and First Level Corridor areas to be shut down Summer of 2018 from June 5th to September 4th. Men’s restrooms on level one will also be inaccessible during this duration. Restrooms on 2nd and 3rd Levels will have to be used during this duration. Summer of 2018 only—June 5th to September 4th
First Floor Olin; Construction Area Highlighted Blue Classrooms Psychology Offices Psychology/Cognitive Science Offices and Labs
First Olin—Temporary Walls Summer of 2018 only—approx. June 5th to September 4th Men’s restrooms on level one will be inaccessible. Restrooms on 2nd and 3rd Levels will be accessible
Olin First Floor Temporary Egress Olin First Floor Temporary Egress Path. Exiting will take place out the north sets of double doors.
Olin Ground Floor Temporary Egress Olin First Floor Temporary Egress Path. Exiting will take place out the north sets of double doors.
Olin 3rd Floor Classroom Bump Out
Olin Future 3rd Floor Classroom Location 3rd Floor Classroom Location of Construction
Olin 3rd Floor Plan with Future Classroom Area Highlighted
Temporary Walls Constructed June 5, 2018 Remain through July 2020
Hulings Connection to the New Building Location
Olin 3rd Floor Plan with Future Classroom Area Highlighted First and Second Floors—Temporary Walls around Ornamental Staircase Constructed June 5, 2018 Remain through July 2019
Olin 3rd Floor Plan with Future Classroom Area Highlighted Third Floor—Temporary Wall Partitioning Hulings 300 300 Constructed June 5, 2018 Remain through Summer 2019
Vivarium Construction Location
Scope of Vivarium Work Timeframe Replace Air Handler Upgrade HVAC Controls Replace Cage Washer Upgrade Lighting Upgrade Fire Alarming Isolate Mechanical & Electrical Systems UPS Backup Timeframe Spring Break (less invasive) Spring Term (less invasive) June 18-29 (major construction)
Next Steps in Planning Finalize Furniture for Department Spaces January Complete Lab Casework Review for New Building February Review Furniture for Offices February-March Begin Science Migration Summer 2019 Planning February Wood Millwork Review Spring Term
2018 Summer Project Work Offline summer and fall BALD SPOT Preliminary plan as of 1/8/18. Project durations and locations still subject to change.
2018 Summer Project Work Offline all summer (June 18 to August 31) Offline summer and fall Offline all summer (June 18 to August 31) Preliminary plan as of 1/8/18. Project durations and locations still subject to change.
2018 Summer Project Work Utility excavation Offline summer and fall Offline all summer (June 18 to August 31) Utility excavation Preliminary plan as of 1/8/18. Project durations and locations still subject to change.
2018 Summer Project Work Offline all summer (June 18 to August 31) Offline summer and fall Offline all summer (June 18 to August 31) Utility excavation Building exterior work: roofs, walls, tuck-pointing, roofs, windows Preliminary plan as of 1/8/18. Project durations and locations still subject to change.
2018 Summer Project Work Offline all summer (June 18 to August 31) Offline summer and fall Offline all summer (June 18 to August 31) Utility excavation Building exterior work: roofs, walls, tuck-pointing, roofs, windows Offline for 2-4 weeks 2-4 wk. shut-down 3-4 wks. Preliminary plan as of 1/8/18. Project durations and locations still subject to change.
2018 Summer Project Work Offline summer and fall Offline all summer (June 18 to August 31) Utility excavation Building exterior work: roofs, walls, tuck-pointing, roofs, windows Offline for 2-4 weeks 2-4 wk. shut-down BALD SPOT 3-4 wks. STEAM PLANT SHUT-DOWN: June 18-24 Preliminary plan as of 1/8/18. Project durations and locations still subject to change.