Four Logical Relationships Between Tasks

Slides:



Advertisements
Similar presentations
Projmgmt-1/12 Depaul University Scheduling Tasks In MicroSoft Project Instructor: David A. Lash.
Advertisements

Microsoft Project Entering and Organizing Tasks Adapted from the Microsoft Step by Step Series by Aaron Schroeder.
Microsoft Project Notes Amir. Tasks Types Fixed Unit tasks – Unit refers to assignment Units as percentages. A resource can be assigned to a task 100%
PERTEMUAN 3 PPSI Microsoft Project Presentation. What is a Gantt Chart? A Gantt Chart is a visual tool to help Plan, Manage, and Track a project or projects.
Phonics Base Words and -s, -ed, -ing Endings
Topological Sort Example This job consists of 10 tasks with the following precedence rules: Must start with 7, 5, 4 or 9. Task 1 must follow 7. Tasks 3.
Management & Development of Complex Projects Course Code - 706
BSBPMG503A Manage Project Time 6.2 Sequence Activities Adapted from PMBOK 4 th Edition InitiationPlanning ExecutionClose Monitor Control The process of.
TUTORIAL 3 INSTRUCTOR: HANIF ULLAH ID: OFFICE #: 2029 DATE: 14/10/2012 Introduction to MS Project 2007.
TABLE MANNERS. Guidelines for Table Manners Be Polite  Don’t put your handbags or briefcase on the table.  Wait until after the meal is ordered before.
Activity networks – Example 1 TaskDuration (hours)Immediate predecessors A3- B4- C6- D5A E1B F6B G7C, D, E The table below shows the tasks involved in.
Adding Fraction With Different Denominator. Definition Common Denominator – When the fractions in an addition problem do not have the same denominators,
5.6.2 Thread Synchronization with Semaphores Semaphores can be used to notify other threads that events have occurred –Producer-consumer relationship Producer.
Chapter 7.1: Deadlocks.
ORDERING ORDERING in a work guides the way the events fall together. It also allows for changing conditions, “tickling” the mind of the reader, giving.
Scheduling CTC-415. Activity Network Development Network Models Activity on Node Precedence Diagram Method Activity on Arrow Network Characteristics Discrete.
Microsoft Project Presentation By Corey Johnson 10/11/00.
 Definition: A demonstrative pronoun points out a specific person, place or thing.  There are four demonstrative pronouns.
Network Scheduling : Precedence Diagram Method
The switch StatementtMyn1 The switch Statement Sometimes there can be a multiple-choice situation, in which you need to execute a particular set of statements.
1 Completing Job Applications Making a good first impression.
Inquiry learning What do inquiry tasks look like in mathematics? Tool IE-2: Comparing structured and unstructured problems.
Define plancontrol BudgetQuality Time BUS 4017 HR. Welcome to: Project Management Week 4. Professor Fred Pentney.
Verb Tense Review: Present, Past, & Future. Present Tense Present tense may express action which is going on at the present time or which occurs always,
Queuing Queues are a part of life and waiting to be served is never really pleasant. The longer people wait the less likely they are to want to come back.
TENSE - THE TIME OF THE ACTION INDICATED BY A VERB Verb Tenses.
Microsoft ® Office Project 2007 Training Linking Project tasks [Your company name] presents:
Know the fundamental logic circuits So that You understand how computers process data We’ve been looking at how data is stored as binary. What about how.
Define plancontrol BudgetQuality Time BUS 1040 Welcome to: Project Management Week 4. Professor Fred Pentney Team slogan ? Give me a “B”?
Table Setting and Etiquette. Why Dining Etiquette? Definition: Courtesy shown by good manners at meals. Makes eating a pleasant experience for everyone.
Mark Kelly Vceit.com Gantt Having Fun with. 2 Well, “fun” might be optimistic At least they’re more fun than this…
When comparing two objects of the same proportion... Proportional Relationships Proportion: a statement that two ratios are equal.
A restaurant is a place people go to eat Today I am going to a restaurant!
Welcome to... A Game of X’s and O’s
Creating a Task List. Task Tasks are the most basic building blocks of any project Task represent the work to be done to accomplish the goals of the project.
Thanksgiving Project. Getting ready to eat!  Between now and Thanksgiving, we will create FunMat for your family dinner.
JavaScript Modularity. Goals By the end of this lecture, you should … Understand why programmers use modularity. Understand how to create a function in.
The Four Seasons Miss. Stalheim Kindergarten Science Next.
Leads and Lags Prepared by: Celeste Ng Date: April, 2016 Source: planning/51758-examples-of-leads-and-lags/
CMGT 410 Week 3 DQ 2 The Start to Finish (SF) logical relationship is the dependency where the second task cannot finish until the first task starts. When.
The suitability event driven programs for non-graphical applications
6.3 Sequence Activities The process of identifying and documenting relationships between the project activities. Every activity, except the first and last,
Christmas in the Czech Republic
Logic Gates and Truth Tables
a valid argument with true premises.
Activity networks – Example 1
In September after the summer holidays, you will start in the Reception class at St Matthew’s. This is the school gate, it is along the pathway.
Verb Tense Tense denotes the time of the action indicated by a verb. The time is not always the same as that indicated by the name of the tense.
Fact Families.
Demonstration Speech.
Project Time Management.
CHAPTER 6 PROJECT TIME MANAGEMENT
Lavish Dinner Rajasthani Thali in Udaipur Bawarchi Restaurant
Lavish Dinner Thali in Udaipur Bawarchi Restaurant
Customer Service for Schools
1 Total Slack A 3d Task Early Start Late Start Early Finish
Project Scheduling: Lagging, Crashing and Activity Networks
Flip-Flops Last time, we saw how latches can be used as memory in a circuit. Latches introduce new problems: We need to know when to enable a latch. We.
Demonstration Speech.
Going to McDonalds!.
Entering the Task List Dr. George.
SD5953 Successful Project Management Predecessors and Successors
Mode.
Get ready... Which sight word is next?
Project Timeline using Microsoft Project
Unit 1, Lesson 6: Lab Equipment
CHAPTER 6 PROJECT TIME MANAGEMENT
Chapter 12 Media Access Control (MAC)
SYEN 3330 Digital Systems Chapter 2 – Part 1 SYEN 3330 Digital Systems.
Presentation transcript:

Four Logical Relationships Between Tasks

Four logical relationships between tasks Finish to Start (default – what we’ve been doing in MS Project) Finish to Finish Start to Start Start to Finish

A Start-to-Start relationship is typically displayed as follows: In essence, they all sound the same. The start of the successor task is gated by the start of the predecessor activity. Until the predecessor starts, the successor cannot start. But here is another meaning people miss. It simply states the successor cannot start UNTIL the predecessor starts. It does not mean it has to start at exactly the same time. It can occur sometime after the beginning of the predecessor’s activity.

A Finish-to-Finish relationship is typically displayed as follows: In finish-to-finish relationships, we must wait for the predecessor task to finish before we can finish, or declare, the successor finished. And just as in start-to-start relationships, the successor doesn’t necessarily finish at the same time as the predecessor; it can finish after the predecessor. When serving dinner, we typically experience, or want to experience, a finish-to-finish relationship. We want all the food to be ready for eating at the same time and placed on the table, arranged for the family to eat.

A Start-to-Finish relationship is typically displayed as follows: The successor task finishes when the predecessor activity starts. Wait! How can the successor task finish, which means it started, before the predecessor activity starts? I don’t know about you, but this definition sounds screwy!. Fortunately, this relationship only occurs less than 1% of the time, so most people miss it, or simply don’t know it exists,