Wimberley Wastewater Treatment Plant Project Thursday, March 8, 2018 Wimberley Wastewater Treatment Plant Project
Background
History September 9, 2013 April 19, 2017 November 16, 2017 Council Approves Contract with Alan Plummer Associates Inc to Design the Wastewater Project April 19, 2017 Four (4) Bids were Received November 16, 2017 Council Approves a Contract with Black Castle BG to Construct the Wastewater Plant
Funding Available Funding TWDB Loan $5,255,000 Expenses EDA Grant $1,000,000 Principal Forgiveness $ 243,005 Way Foundation Grant $1,000,000 $7,489,005 Expenses Black Castle BG $3,068,900 Capital Excavation $3,616,230 (Collection Line Project) Fees $ 339,657 $7,024,787 Balance/Contingency $ 473,218
Wastewater Treatment Plant
Schedule
Key Dates March 12 - First Day of Project March 22 - Site Survey March 30 - Site Clearing to Begin April 6 - Work on Roadway to Begin June 12 - Irrigation Work to Begin October 1 - Plant Arrives November 9 - Plant Startup
Communication
Outreach Website Blue Hole Park Facebook Email Council Updates
Contact Information Wimberley Contact Shawn Cox - City Administrator scox@cityofwimberley.com 512-847-0025 Contractor – Black Castle Project Start Date – Monday, March 12 Wimberley Project Manager – Jim Schoonover