Water Main Rehabilitation Cured-In-Place-Pipe Technology

Slides:



Advertisements
Similar presentations
TIGER PROGRAM LESSONS LEARNED Great PA/NJ Regional Trail Projects Presentation to the Circuit Coalition May 15, 2014 Chris Stanford, P.E., PTOE, PMP Michael.
Advertisements

Project Delivery Approaches for Wastewater Utilities in Minnesota June 24, 2008 Metropolitan Council Environment Committee.
11 Grant Park Sewer Rehabilitation Project BES Project #E10346 Bid # SCOPE: Rehabilitation, Replacement, or Relocation of Sanitary & Combined Sewers,
Innovative solutions for the rehabilitation of lead service connection lines and adjacent water mains.
2014 STREET & UTILITY IMPROVEMENT PROJECT CITY COUNCIL MEETING November 18, 2013.
Lander Streets and Utilities 2015 Public Meeting No. 2 McDougall & Cliff Project Area.
Dillon and Christina Project Area Lander Streets and Utilities 2015 Public Meeting No. 2.
Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011.
Gwinnett County’s Post Development Stormwater Management Program
1402 Hybrid Firefighter I 6 th Edition Chapter 14 Water Supply.
Triton Lining Systems LLC. The City of Sac City, Sac City Iowa, Water Distribution Pipe In-Situ Rehabilitation July 2012.
Crafting Stormwater Programs Oregon Coastal Planners Fall Network Meeting October 9, 2008 Florence Event Center Alissa Maxwell, PE.
PUBLIC WORKS ORGANIZATION (S) by John Lisenko Definition: A public works organization is any organized system set up for the purpose of managing the physical.
Module 6: Design Process Preliminary Field Review Preliminary Erosion and Sediment Control Design Report, including Preliminary NOI Package Alignment and.
September 2005Urban Planning Carleton University 1 Drainage Systems _____________________________.
PLANNING DEPARTMENT CITY OF PEARLAND PLANNING DAY MARCH 13, 2008.
Project Scoping Fundamentals Alan Lively Project Delivery Specialist Local Government Section April 6, 2010.
City of Auburn Streetscape: A Complete Street Presented by: Ed Armstrong, RLA.
The ABC ’ s of the Development Review Process: Navigating the Bureaucratic Maze 2007 GPA Fall Conference.
WVSD SANITARY SEWER REHABILITATION PROGRAM 2006 Sewer Smart Summit Presented by Peter V. Sevcik, P.E. West Valley Sanitation District Campbell, California.
Student Book © 2004 Propane Education & Research CouncilPage Performing Gas Distribution System Leak Checks Requirements for vapor distribution.
Lift Station No. 1 and 2 Force Main Replacement Ronald Wastewater District Summer 2015.
“Pushing the Limits of Constructability Pushes the Limits of Stakeholder Involvement” Case Study: Myrtle-Morehead SDIP City of Charlotte, North Carolina.
I Wear My “Safety” Glasses at Night: Maximizing Planning Tools to Reduce Utility Construction Costs and Headaches 95 Th Annual Conference Raleigh, NC November.
Webster Water System Board of Selectmen Public Hearing on Water Quality October 13, 2015 Doran Crouse, Webster Water Department Scott Charpentier, P.E.,
HAMPTON ROADS REGIONAL WATER RESOURCES MANAGEMENT PROGRAM Presentation John M. Carlock, AICP Deputy Executive Director, Physical Planning Hampton Roads.
Aaron Cosentino City of Elgin Rob Linke, P.E., CFM Trotter & Associates, Inc. Lord Street Basin CSO Green Infrastructure Retrofit Project November 14,
Department of Public Works FY Capital Improvement Program (CIP) Budget Adoption & Amendments to FY 16 CIP May 16, 2016.
CITY OF BELLEVILLE ROAD IMPROVEMENTS PROGRAM
Water & Sewer CCTV Inspection Methods & Techniques
Urban Runoff Pollution Ordinance 2017 Proposed Update
Heritage Park Area Construction Update July 28, 2015
Innovative Approach to Water Main Renewal
Interagency Coordination in Long Range Transportation Planning
Village of east aurora full depth road reconstruction & infrastructure improvements West Fillmore Avenue.
NASHVILLE, TN Brandon Taylor, P.E.
City of Orinda 2017 Annual and Measure J &L Pavement Rehabilitation Projects City Projects No & 4115.
Village of east aurora sycamore street water improvements
Town of Brighton, Department of Public Works
Stewart Crossing Phases 3 & 4.
AND AFTER INSTALLATION Technical Director, NASSCO
PROJECT INFORMATION SESSION Small Business Enterprise
THE DESIGN CRITERIA FOR WASTEWATER SYSTEMS (30 TAC Chapter 217)
City of Johnston East of Merle Hay Road Infrastructure Improvements
General Road Construction Information
Interstate 15 North Phase 4 Cost Estimates 09/03/2015
FOR LOCAL AGENCY FEDERAL AID PROJECTS
CTC 450 Review Water Processes.
107th & 110th Avenue North Public Utilities Renewal Projects
NORTH TRUNK SEWER REPLACEMENT PROJECT
NORTH TRUNK SEWER REPLACEMENT PROJECT
IA 122 RECONSTRUCTION PRE-BID MEETING
WATER MAIN REHABILITATION
NSF International Drinking Water Product Standards
Water Department has Six Divisions
Traceability of Gas Pipeline Materials Research & Materials Manager
PLUMBING PLANS CHAPTER 31
WENDELL PARK STORMWATER IMPROVEMENTS
Calvin, Giordano & Associates, Inc.
City of Roundup, Montana
THE ROLE OF THE PLANSET IN CONTRACT DOCUMENTS
FOR LOCAL AGENCY FEDERAL AID PROJECTS
National Association of State Conservation Agencies
City of Greater Sudbury Lining Program Overview. Brittany Hallam, P
Print Reading.
Construction Considerations
Chapter 6 Site Construction.
2019 Capital Program Title of Presentation
Change Order Request Contract S02013C01 SSWRF RAS System Improvements Restore ED’s Original Delegated Authority Approve Changes in TPC Commission.
Ron Hancock, PE NCDOT State Construction Engineer
Presentation transcript:

Water Main Rehabilitation Cured-In-Place-Pipe Technology 4th Street Water Main Lining Project Jason Cook, PE, PMP

AGENDA General Construction Sequence Project Background Preliminary Engineering Final Design Efforts Construction Key Takeaways/ Lessons Learned

GENERAL CONSTRUCTION SEQUENCE Locate and verify pipe size Install temporary bypass system Excavate access pits Cut, clean, and inspect existing main Map and plug all service connections Wetout, install, and cure liner CCTV inspection of liner Hydrostatic testing

GENERAL CONSTRUCTION SEQUENCE Reinstate services Disinfect newly lined main Reconnect water distribution system Remove temporary bypass and restore site

PROJECT BACKGROUND Pilot Project for CFPUA Is CIPP a viable option? Can it mitigate typical construction impacts? When and where else should it be considered? CFPUA is familiar with CIPP of gravity sewers

PROJECT BACKGROUND Project Location 4th St. between Castle St. and Willard St. Established urban area of downtown Wilmington, NC. Encroachment on multiple right-of-ways: City of Wilmington NCDOT CSX Project Area

PROJECT BACKGROUND Numerous above/below ground utilities: Sanitary Sewer Stormwater Gas Telecom Power, etc. Historical site features: Brick Roadways Granite Curb Old Growth Trees, etc.

PROJECT BACKGROUND Water Main Characteristics 12” CI installed in mid-1960’s. Mostly straight alignment. Residential service and branch main connections. History of maintenance requirements.

PRELIMINARY ENGINEERING Is CIPP a viable option? Establish key design considerations Overall condition of the existing main? General alignment of the existing main? Number/location of valves, hydrants, fittings, etc? Working pressure of existing main? Semi-structural or fully structural liner per AWWA M28? Quantity and type of service connections?

PRELIMINARY ENGINEERING Tools and Available Resources As-built drawings GIS information Field survey Water system model Maintenance records Discussions with operations

PRELIMINARY ENGINEERING CIPP Product Requirements NSF 61 certification Class IV per AWWA M28 Exceed system operating pressures Future tapping

PRELIMINARY ENGINEERING Available CIPP Products AquaPipe by Sanexen RS Blueline by RS Technik NordiPipe by Sekisui InsituMain by Insituform

PRELIMINARY ENGINEERING Additional Preliminary Engineering Steps Cost Comparison between CIPP & Open Cut Manufacture estimates, past experience, etc. Isolation options & temporary water setup Permitting requirements

PRELIMINARY ENGINEERING

FINAL DESIGN EFFORTS Need a Clearer Picture SUE and Survey How far should we go? What has changed? Notable site characteristics: Location/depth of existing utilities Unique system connections Historical elements System isolation options

FINAL DESIGN EFFORTS Locate Access Pits What are system reconnection requirements? What are the maximum lining lengths? What impacts will result from access pits? Traffic control Existing utilities R/W encroachment

FINAL DESIGN EFFORTS

FINAL DESIGN EFFORTS Traffic Impacts

FINAL DESIGN EFFORTS Permits and Agency Approvals NCDOT NC DEQ Public Water Supply Erosion & Sediment Control City of Wilmington Engineering (right-of-way, streets cuts) Fire Department CSX

FINAL DESIGN EFFORTS Bidding and Award Approval Criteria Licensed/Certified Installer 40,000 LF of similar size in past 3 years Bid Structure and Range Base Bid, Alt #1 and Alt #2 $1.3M, $1.9M, and $5.1M

CONSTRUCTION Locate and verify pipe size Unlined Cast Iron Cement Lined Cast Iron

CONSTRUCTION 2. Install temporary bypass system

CONSTRUCTION 3. Excavate access pits

CONSTRUCTION 4. Cut, clean, and inspect existing main

CONSTRUCTION 5. Map and plug all service connections

CONSTRUCTION 6. Wetout, install, and cure liner

CONSTRUCTION 6. Wetout, install, and cure liner (cont.)

CONSTRUCTION 6. Wetout, install, and cure liner (cont.)

CONSTRUCTION 7. CCTV inspection of liner 8. Hydrostatic testing

CONSTRUCTION 9. Reinstate services

CONSTRUCTION 10. Disinfect newly lined main 11. Reconnect water distribution system

CONSTRUCTION 12. Remove temporary bypass and restore site

KEY TAKEAWAYS & LESSONS LEARNED Key Project Drivers Configuration of Distribution System Influence number pits required System isolation and temporary water requirements Location of Distribution System Permitting (R/W encroachments, city/state requirements) Paving and site restoration requirements Traffic impacts

KEY TAKEAWAYS & LESSONS LEARNED Key Project Drivers (cont.) Condition of Distribution System Semi-structural or fully-structural liner Existing valve operation Variation in system materials Operation of Distribution System System operating pressures CIPP liner thickness NSF 61 certification Future tapping of lined main

KEY TAKEAWAYS & LESSONS LEARNED Risk of cost variance Weather can change lining operation procedures Plan for temporary water impacts Testing of the installed liner is a must

QUESTIONS Jason Cook, PE, PMP Jeff Theberge, PE jcook@hazenandsawyer.com Jeff.Theberge@cfpua.org