Troy School District 2013 Bond Program – Series 1 Construction Update 04.14.15 Barton Malow | TMP
Troy High School Additions Classroom & Storage Additions Completion Date ≈ December 2015
Troy High School Additions Classroom & Storage Additions Completion Date ≈ December 2015
Troy Athens High School LGI & Multi Use Classroom Renovation – Spring 2015
Boulan Park & Larson Middle Schools Office Additions Completion Date ≈ December 2015
Boulan Park Middle School Office Additions Completion Date ≈ December 2015
2015 Projects BP #8 Athens High School Mechanical & Electrical Upgrades Scheduled Out for Bids August 2015 BP #9 Larson and Boulan Park Middle Schools Mechanical & Electrical Upgrades, Site Paving Bids due April 7, 2015 BP #11 International Academy East Convert Pool to LGI Room BP#13 Smith Middle School and Niles Community High School Gymnasium/Locker Room renovations Restroom renovations at Niles Award Contracts April 14, 2015