9/09/20091 Risk Analysis Bob Sklar Engineering Fellow & Chief Engineer (Retired) Raytheon Company University of Arizona SIE-554 Fall 2009.

Slides:



Advertisements
Similar presentations
COMP 110: Introduction to Programming Tyler Johnson Feb 25, 2009 MWF 11:00AM-12:15PM Sitterson 014.
Advertisements

COMP 110: Introduction to Programming Tyler Johnson Mar 16, 2009 MWF 11:00AM-12:15PM Sitterson 014.
COMP 110: Introduction to Programming Tyler Johnson Apr 20, 2009 MWF 11:00AM-12:15PM Sitterson 014.
COMP 110: Introduction to Programming Tyler Johnson Apr 13, 2009 MWF 11:00AM-12:15PM Sitterson 014.
Schedule Risk Analysis (SRA) Tariq Ashraf Systems Engineering Feb 24, 2005.
Large Scale Integration of Senses for the Semantic Web Jorge Gracia, Mathieu dAquin, Eduardo Mena Computer Science and Systems Engineering Department (DIIS)
Risk Analysis Fundamentals and Application Robert L. Griffin International Plant Protection Convention Food and Agriculture Organization of the UN.
Objectives To introduce software project management and to describe its distinctive characteristics To discuss project planning and the planning process.
Wouter Noordkamp The assessment of new platforms on operational performance and manning concepts.
Risk Management Awareness Presentation
Ziehm Academy - User Guide for online registration portal Nuremberg, February 2009.
October FUEL PRICE EVALUATION Comparing different fuel costs is a complex issue requiring an in-depth knowledge of fuel properties and characteristics,
Efficient Solutions For Water Supply Helix High-Pressure Vertical Multistage Pump.
1 Cathay Life Insurance Ltd. (Vietnam) 27/11/20091.
Technology Module: Technology Readiness Levels (TRLs) Space Systems Engineering, version 1.0 SOURCE INFORMATION: The material contained in this lecture.
Determining the Significant Aspects
Presented by: Yaseen Ali, Suraj Bhardwaj, Rohan Shah Yaseen Ali, Suraj Bhardwaj, Rohan Shah Mechatronics Engineering Group 302 Instructor: Dr. K. Sartipi.
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
Prescriptive Process models
1. (c) Alan Rowley Associates Laboratory Accreditation Dr Alan G Rowley Quality Policy based on Quality Objectives Quality Management System Communicate.
30 min Scratch July min intro to Scratch A Quick-and-Dirty approach Leaving lots of exploration for the future. (5 hour lesson plan available)
PROJECT RISK MANAGEMENT
Flexible Scheduling of Software with Logical Execution Time Constraints* Stefan Resmerita and Patricia Derler University of Salzburg, Austria *UC Berkeley,
PROJECT TITLE Project Leader: Team: Executive Project Sponsor (As Required): Date: Month/Day/Year 110/17/2014 V1.
The System and Software Development Process Instructor: Dr. Hany H. Ammar Dept. of Computer Science and Electrical Engineering, WVU.
Note: See the text itself for full citations. Information Technology Project Management, Seventh Edition.
Chapter 15 Design, Coding, and Testing. Copyright © 2005 Pearson Addison-Wesley. All rights reserved Design Document The next step in the Software.
Project Risk Management
PURPOSE OF DFMEA (DESIGN FAILURE MODE EFFECTS ANALYSIS)
SQM - 1DCS - ANULECTURE Software Quality Management Software Quality Management Processes V & V of Critical Software & Systems Ian Hirst.
LSU 10/09/2007Risk Management1 Risk & Risk Management Project Management Unit #5.
Development and Quality Plans
Chapter 2 A Strategy for the Appraisal of Public Sector Investments.
Don Cole Risk Assessment and Mitigation Project Management for ARA Engineers and Scientists.
S/W Project Management
Project Risk Management. The Importance of Project Risk Management Project risk management is the art and science of identifying, analyzing, and responding.
S/W Project Management Software Process Models. Objectives To understand  Software process and process models, including the main characteristics of.
Project Risk and Cost Management. IS the future certain? The future is uncertain, but it is certain that there are two questions will be asked about our.
PROJECT RISK MANAGEMENT Presentation by: Jennifer Freeman & Carlee Rosenblatt
Risk Management - the process of identifying and controlling hazards to protect the force.  It’s five steps represent a logical thought process from.
Risk Management in the Built Environment Qualitative and Quantitative Risk Management By Professor Simon Burtonshaw-Gunn – licensed under the Creative.
Module 4: Systems Development Chapter 12: (IS) Project Management.
1 TenStep Project Management Process ™ PM00.7 PM00.7 Project Management Preparation for Success * Manage Risk *
1 Chapter 5 Project management. 2 Project management : Is Organizing, planning and scheduling software projects.
Chapter 12 Project Risk Management
Chapter 11. Intro  What is Project Management?  Project Manager  Project Failures & Successes Managing Projects  PMBOK  SDLC Core Process 1 – Project.
2013 NWHA CONFERENCE FERC’S RISK-INFORMED DECISION MAKING Doug Johnson – Regional Engineer - Portland From PFMA to Risk Assessment.
Chapter 3 Project Management Chapter 3 Project Management Organising, planning and scheduling software projects.
The System and Software Development Process Instructor: Dr. Hany H. Ammar Dept. of Computer Science and Electrical Engineering, WVU.
Ch 10 - Risk Management Learning Objectives You should be able to: List and describe risk management processes, inputs, outputs, and tools List and describe.
Meeting Management/Planning. Today Go over basics of meeting management Introduce key elements of creating a plan.
Introducing Project Management Update December 2011.
SOFTWARE PROJECT MANAGEMENT
Project Risk Management Planning Stage
Chapter 1: Fundamental of Testing Systems Testing & Evaluation (MNN1063)
Stand Up Comedy Project/Product Management
Information Technology Project Management Managing IT Project Risk.
RLV Reliability Analysis Guidelines Terry Hardy AST-300/Systems Engineering and Training Division October 26, 2004.
Smart Home Technologies
Failure Modes and Effects Analysis (FMEA)
1 Chapter 2 SW Process Models. 2 Objectives  Understand various process models  Understand the pros and cons of each model  Evaluate the applicability.
Organizations of all types and sizes face a range of risks that can affect the achievement of their objectives. Organization's activities Strategic initiatives.
Stoimen Stoimenov QA Engineer SitefinityLeads,SitefinityTeam6 Telerik QA Academy Telerik QA Academy.
ON “SOFTWARE ENGINEERING” SUBJECT TOPIC “RISK ANALYSIS AND MANAGEMENT” MASTER OF COMPUTER APPLICATION (5th Semester) Presented by: ANOOP GANGWAR SRMSCET,
Project management. Software project management ■It is the discipline of planning, organizing and managing resources to bring about the successful completion.
Ashima Wadhwa.  Probably the most time-consuming project management activity.  Continuous activity from initial concept through to system delivery.
ITPD ISSUE MANAGEMENT PROCESS SEPTEMBER 5, 2008
Air Carrier Continuing Analysis and Surveillance System (CASS)
GE 6757 TOTAL QUALITY MANAGEMENT
Failure Mode and Effect Analysis
Presentation transcript:

9/09/20091 Risk Analysis Bob Sklar Engineering Fellow & Chief Engineer (Retired) Raytheon Company University of Arizona SIE-554 Fall 2009

9/09/20092 Benefits of Risk Analysis Increases probability of program success –Potential to reduce program schedule & cost Facilitates proper allocation of resources –Helps in program planning Communicates program status / health –Informs program / company management –Informs customer Effective risk analysis is not easy, but a process and tools are available

9/09/20093 Concept Design System Subsystems Components Preliminary Design Detailed Design Production Design DESIGN Initial Analysis Assessment Management Communication Updated Analysis RISK ANALYSIS Initial Plans Components Subsystems System Updated Plans PROGRAM TEST PLANS Risk Analysis is a Continuous Process As the design evolves, risk analysis & test plans are updated, leading to design improvements & program success

9/09/20094 Risk Topics What is Risk? Types of Risk Assessment of Risk Reporting & Tracking Risk Risk Management Risk Mitigation Example

9/09/20095 What is Risk? - 1 From the dictionary: –The possibility of loss or injury. –The chance or possibility of incurring loss or misfortune. –The uncertainty of future returns (financial risk). Risk is the potential of an adverse condition occurring on a project which will cause the project to not meet expectations - University Information Services, Georgetown University

9/09/20096 What is Risk? - 2 Risk is a measure of the potential harm or loss associated with an activity executed in an uncertain environment. -Terry Bahill Risk is Uncertainty - Bob Sklar Something that is unknown because it has not yet been designed is a design task; not a risk

9/09/20097 What is Risk Analysis? Risk analysis includes: –Risk assessment involves identifying sources of potential harm, assessing the likelihood that harm will occur and the consequences if harm does occur. –Risk management evaluates which risks identified in the risk assessment process require management and selects and implements the plans or actions that are required to ensure that those risks are controlled. –Risk communication involves an interactive dialogue between stakeholders and risk assessors and risk managers which actively informs the other processes. - Wikipedia Risk analysis = risk assessment + risk management + risk communication

9/09/20098 Performance Risk –Technical risks, normally tracked using technical performance measures. Inability to achieve technical requirements. Schedule Risk –Unforeseen delays in completing tasks. Cost Risk –Unforeseen cost overruns, often associated with performance and schedule risks. Project Risk –The potential of an adverse condition that will cause the project to not meet customer expectations Different Types of Risk

9/09/20099 Interrelationship of Risks Major performance, cost & schedule risks work their way up to the overall project

9/09/ Low Risk –Technology mature and can be applied operationally. Multiple technology options available. Moderate Risk –Technology development required before operational application. Few technology options exist. High Risk –Technology immature. Extensive development needed even before laboratory demonstration. Only one plausible technology option exists. Evaluating Performance Risk

9/09/ Suppose we conduct a test and discover that a subsystem does not meet a key requirement Since the uncertainty has been eliminated, has risk also been eliminated? No, there may be a high level of project risk caused by not meeting this requirement Therefore, the subsystem design must be fixed (unless the overall system can somehow accommodate this performance problem) Is Elimination of Uncertainty Sufficient? It is not enough to eliminate uncertainty; program requirements must still be satisfied

9/09/ Accepting risk is desirable if: –It offers the potential of large payoffs in performance, cost or schedule Normally, risk buys performance potential Sometimes, reduced cost or schedule is the objective Rarely do all 3 benefit from accepting risk –The risk can be managed Risk management plan is critical & must be seriously implemented –The risk is accepted by the customer Must understand risk and potential consequences Risks dont always pay off Example: Use of unproven technology could provide performance improvement if successful; more cost & delayed schedule if not Accepting Risk Can Be Good

9/09/ Fear of some harm ought to be proportional not only to the magnitude of the harm, but also to the probability of the event. - Logic, or the Art of Thinking Antoine Arnauld, 1662 We refer to these as: 1. Severity of Consequence 2. Relative Likelihood of Occurrence Risk has 2 Components For convenience, the product of these 2 risk components is often used as an overall measure of risk

9/09/ Since risk represents uncertainty, its components are difficult to explicitly quantify Engineers with appropriate expertise can use their experience and judgment to estimate relative risk levels Relative risk levels, while not precise probabilities, provide a means of tracking and communicating areas needing special attention How do We Quantify Risk? Risk assessments highlight areas demanding special attention

9/09/ Legend 1 = 2 = 3 = 4 = 5 = 6 = 7 = (Brief descriptions) Reporting & Tracking Risk Report Date: Arrows indicate changes from previous report Potential Severity of Consequence Relative Likelihood of Occurrence High Moderate Low The goal is to reduce all risks to low levels during the development process

9/09/ Relative Likelihood of Occurrence Potential Severity of Consequence High Moderate Low Some Observations on Risk Plot The ordinate (vertical axis) is not probability Probabilities cannot be calculated because of uncertainty and unknown unknowns This axis is labeled relative likelihood –Relative because it concerns relationships between risks –Likelihood not in the mathematical sense, but in the dictionary sense indicating risks that are most likely

9/09/ Estimated risks could increase or decrease due to –Design changes –Analysis or test results –Other new information What Causes Risks to Change? The design evolves; knowledge evolves – always look for new risks & better estimates for previously known risks

9/09/ Negligible 2 Unlikely 3 Likely 4 Highly Probable 5 Near Certainty Likelihood 1 Marginal 2 Significant 3 Serious 4 Very Serious 5 Catastrophic Consequence High Risk Moderate Risk Low Risk Alternate Form of Risk Plot Some customers prefer this form

9/09/ Negligible 2 Unlikely 3 Likely 4 Highly Probable 5 Near Certainty Likelihood 1 Marginal 2 Significant 3 Serious 4 Very Serious 5 Catastrophic Consequence High Risk Moderate Risk Low Risk Alternate Form of Risk Plot Some customers prefer this form - but it has the disadvantage that risks with potential catastrophic consequences can never be retired

9/09/ Preferred Form of Risk Plot Relative Likelihood of Occurrence Potential Severity of Consequence High Moderate Low This is basically a communications aid, so do it the best way for your customer

9/09/ Good risk management will not prevent bad things from happening. But when bad things happen, good risk management will have anticipated them and will reduce their negative effects. -Terry Bahill Performance, schedule and cost risks at the lower (subsystem) levels can often be accommodated at the project level by reallocating resources or requirements, but this requires that program management be aware of problems early. Risk Management

9/09/ Develop comprehensive risk management plan –Risks identified; mitigation plans developed By engineers with related expertise Assign each risk to a responsible engineer –In design area impacted by this risk –Manages risk mitigation plan; reports status Conduct tests at all levels as early as possible –Uncover design problems in time to fix deficiencies –Validate or refine analytic models (confidence) Keep customer informed –Focus on moderate and high risks; report status & program impact Ways to Manage Risk

9/09/ Develop program plan, schedule, and budgets that can accommodate risk –Test intensive (all levels & early; prototypes) –Spare parts (to preserve schedule if failures) –Back-up plans (work-arounds) –Anticipate failures –Ample design margins Continually search for new risks as knowledge evolves over time Risk Mitigation The program plan must tradeoff performance risk and the cost of additional tests

9/09/ For each high or moderate risk area, the plan should include: – Analysis, simulations, tests and other activities capable of progressively reducing uncertainty Plan for each activity should include detailed schedule and required resources (including personnel) –Activities should be conducted as soon as allowed by available hardware/software –Reassess risks based on results of activities –Have backup plan in case activity fails Risk Mitigation Plan Development Risk management is an integral part of the overall program plan. It is a continuous & iterative process.

9/09/ High Moderate Low Risk CY07CY08CY09 Analysis & Preliminary Simulation Updated Dynamic Simulation Initial Integration (Prototype Performance Test) Final Integration (Final Performance Test) Mitigation Plan (Risk Waterfall Chart) Risk 352: Mechanical integration Subsystem: Staging Assembly Responsible Engineer: John Stager Every risk item is assigned to a specific responsible design engineer Plan should include detailed descriptions of each mitigation activity Initial Mechanical Fit Check Activities are introduced to progressively reduce risk

9/09/ If you are the responsible engineer for a missile subsystem and need to make a risk status presentation at the monthly meeting with your customer, consider presenting the following: – Overview – list key changes from last month –Updated risk register Subsystem risks & risk assessments; highlight changes –Risk plot (likelihood vs. severity) Indicate changes from previous month –Risk waterfall charts for high/medium risks Indicate changes from previous month –Results of any risk mitigation activities completed in last month, justifying risk assessment changes Reporting Risk

9/09/ Risk Analysis Example For this risk example, we will address the MK104 Dual-Thrust Rocket Motor (2 nd stage) Public Released Raytheon Images Example intended to illustrate risk analysis process, not actual SM-3 history

9/09/ Initial design trades and at least preliminary subsystem designs have been completed –Rocket motor size (consistent with other missile stages) –Case materials –Propellant type (solid) –Propellant design (thrust profile) –Stage interfaces (mechanical/electrical) Some Design Status Assumptions Design Challenges are tasks, not risks

9/09/ Risk No.RiskConsequencesLikelihoodSeverityRisk Factor 1May not achieve specified total impulse Overall missile performance may not be acceptable nd thrust may not initiate properly Would reduce mission effectiveness May exceed weight allowanceOverall missile performance may not be acceptable Mechanical interfaces with other stages may be inadequate Missile failure during transportation, launch or flight Stage production cost may exceed allowance Total missile cost may not be acceptable Propulsion development time may exceed plan Development time (and associated cost) may not meet program objectives Propulsion stage may not meet safety requirements Missile may not be acceptable to customer Risk Register Example Risk Factor = Likelihood x Severity 2 nd Stage Rocket Motor

9/09/ Legend 1 = Total impulse 2 = 2 nd thrust 3 = Stage weight 4 = Interfaces 5 = Stage cost 6 = Schedule 7 = Safety Example Risk Assessment Report Date: 1/15/ Relative Likelihood of Occurrence Potential Severity of Consequence High Moderate Low These estimates, based on judgment, may not reflect reality 2 nd Stage Rocket Motor

9/09/ Example Risk Waterfall Chart Each high or moderate risk needs a mitigation plan High Moderate Low Risk CY08CY09CY10 Heavyweight Motor Combustion Test (Prototype Performance Test) Environmental Tests Subsystem: 2 nd Stage Rocket Motor Risk 1 (may not achieve specified total impulse) Responsible Engineer: Mary Burns Descriptions of each mitigation activity should be included as part of the plan (with detailed description, schedule, required resources, etc.) Propellant & Igniter Tests Lightweight Motor Combustion Test (Final Performance Test)

9/09/ Some Final Thoughts The parts of risk analysis we observe are only the communication tools. That is why they dont have to be precise. Real risk analysis takes place at lower levels, where design & test engineers are busy at their work. Systems engineers facilitate this process. Risks cannot really be controlled – bad things happen. But the anticipation of risks and the control of their consequences can indeed be managed. - Bob Sklar